What is the ALCMS interface?

The link between the control and monitoring system and the field — proving commands go out, and status and alarms come back, exactly as they should.

ALCMS INTERFACE · DOES THE SCREEN MATCH THE FIELD COMMANDS OUT · STATUS AND ALARMS BACK 1 COMMS LINK Link to each CCR Network & protocol set Loss of link seen RECORD: link 2 POINT MAP Point list checked Each point one by one Right circuit named RECORD: points 3 COMMANDS On, off, steps Sent from screens CCR obeys at once RECORD: commands 4 FEEDBACK Status shown true Alarms raised Time-stamped RECORD: alarms 5 SCREENS & LOGS Graphics match field Event log kept Reports produced RECORD: displays INTERFACE PROVED EVERY POINT · END TO END 6 DEFECT TRACE · FIX · RE-TEST PASSED READY FOR NEXT COMMISSIONING STEP SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
interface check
record taken
defect
passed
The Fact Commissioning practice

The airfield lighting control and monitoring system (ALCMS) is how operators see and command the lights. Once the field system has been integrated, the interface between the ALCMS and the field is proved: commands sent from the screens must reach the CCRs, and the status and alarms shown must match what the field is really doing.

Each command and status point is checked one by one against the point list, together with the communication link, the screens and the event log. Each result is recorded. A defect is traced, fixed and re-tested. When the checks pass, operators can rely on the display.

  1. Comms link. Confirm the link to each CCR or controller, and that loss of link is detected.
  2. Point map. Check every command and status point against the point list and its circuit.
  3. Commands. Send on, off and brightness steps from the screens; confirm the CCR responds.
  4. Feedback. Confirm status is shown true and alarms are raised and time-stamped.
  5. Screens and logs. Check graphics match the field, and the event log and reports are kept.
  6. Record. Log each result; trace, fix and re-test any defect.
Purpose Prove the ALCMS commands and monitors the field correctly
System state Live, field system already integrated
Checks Link, point mapping, commands, status and alarms, screens and logs
Output Interface test record per point, with defects and re-tests
Follows System integration
Reference ICAO Annex 14 Vol I Ch 8; ICAO Doc 9157 Pt 5; FAA AC 150/5345-56 (L-890 ALCMS); FAA AC 150/5340-30; project specification and FAT/SAT procedures
Schematic — checks shortened for clarity. The point list, communication protocol, screens and acceptance criteria are set by the project specification, the applicable standard and the ALCMS and CCR manufacturers’ instructions. Live work follows your site’s permit-to-work procedure.
Entry 25 · System integration Entry 27 · PAPI commissioning

Frequently Asked Questions

Q1What is the ALCMS interface in airfield ground lighting?

The connection between the airfield lighting control and monitoring system (ALCMS) and the field equipment, mainly the CCRs. Commands go out from the screens, and status and alarms come back. Commissioning proves each of these exchanges works end to end.

Q2What does the ALCMS interface test cover?

The communication link to each CCR or controller, that every command and status point is mapped to the right circuit, commands from the screens, status and alarm feedback, and the screens, event log and reports that operators rely on.

Q3How is it different from system integration?

System integration joins the field parts, such as power, CCRs, local and tower control and interlocks, and proves they work as one. The ALCMS interface then checks that the control and monitoring software sees and commands that system correctly.

Q4What is a point list and why does it matter?

A point list is the schedule of every command, status and alarm signal between the ALCMS and the field, with the circuit each belongs to. Checking each point one by one finds swapped, missing or mislabelled signals before operators depend on them.

Q5Why test alarms and loss of communication?

Operators trust the display to show faults. Creating real or simulated faults, and cutting the communication link, shows whether the alarm appears on the right screen, is time-stamped in the log, and whether circuits stay safe and the display marks stale data.

Q6What happens if an interface check fails?

The defect is recorded, the cause is traced to the field wiring, the communication settings or the ALCMS configuration, and it is corrected. The affected points are re-tested, and the record keeps the failure, the correction and the passing re-test.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.