India AGL · CAT II / CAT III

AGL FOR CAT II / CAT III AIRPORTS IN INDIA

CAT II and CAT III operations require specialised aerodrome facilities and carefully maintained visual aids.

Indian AIP material documents CAT II/III AGL installations, critical runway lighting circuits and power-supply arrangements at Indian airports.

01 · Low-Visibility AGL

Precision Approach and Low-Visibility AGL

CAT II and CAT III operations require specialised aerodrome facilities, carefully designed visual aids, dependable power systems and controlled operational procedures. Airfield Ground Lighting (AGL) is one part of this wider precision-approach infrastructure — the exact arrangement is airport- and runway-specific and must be established from the applicable aerodrome documentation, approved design and project requirements.

Precision approach lightingRunway edge lightingRunway centreline lightingRunway threshold lightingRunway end lightingTouchdown zone lightingTaxiway centreline lightingStop barsRunway guard lightsControl & monitoringCritical electrical powerStandby power
02 · The Operational Chain

What CAT II / CAT III Means for AGL

CAT II and CAT III are precision-approach operational categories associated with progressively lower visibility conditions and additional aerodrome facilities. From an AGL engineering perspective, lower-visibility operations can require more extensive and carefully controlled visual guidance systems — considered as part of a wider chain rather than in isolation.

ILS / Approach System
RVR Information
AGL
Power Supply
Control & Monitoring
Surface Movement Guidance
Operational Procedures
03 · Why It Matters

Why AGL Is Critical in CAT II / CAT III Operations

In low visibility, the visual environment available to aircraft crews is reduced. The airfield lighting system therefore has an important role in supporting the guidance functions below — which is why AGL maintenance and serviceability become especially important during Low Visibility Procedures (LVP).

Approach guidanceRunway alignmentLanding guidanceRunway identificationTaxi guidanceHolding-position identificationRunway access controlSurface movement
04 · Approach Guidance

Precision Approach Lighting

Precision approach lighting provides visual guidance in the approach area leading toward the runway. The exact approach lighting configuration is determined by the runway, approach system and approved airport design.

High-intensity approach lightingCentreline guidanceCrossbar / lateral guidanceSequenced lighting where applicableAssociated electrical & control equipment

Approach Lighting Standards India

The approach lighting configuration for a CAT II / CAT III runway follows the runway, the approach system and the approved airport design. Indian projects commonly work to ICAO Annex 14 as implemented through DGCA requirements, with FAA-type equipment where the specification calls for it. The reference for each project belongs in the compliance matrix below, taken from the current project documentation. See AGL Standards & Compliance.

Approach Lighting Manufacturer India

When comparing an approach lighting manufacturer or supplier for an Indian airport, check compliance with the specified standard, type-test and photometric reports, compatibility with the CCR and series circuit, service life, spares and local support. See Equipment Manufacturers.

05 · Runway Facilities

Runway Lighting for CAT II / CAT III

Depending on the runway configuration, the AGL system may include the facilities below. Not every runway will have exactly the same combination of systems — the approved configuration must be checked for the specific aerodrome.

Runway Edge Lights

Define the lateral runway boundaries.

Threshold Lights

Identify the runway threshold.

Runway End Lights

Identify the runway end.

Runway Centreline Lights

Provide longitudinal runway guidance.

Touchdown Zone Lights

Provide additional visual guidance in the touchdown area.

Approach Lighting

Provide visual guidance leading toward the threshold.

06 · Taxi Guidance

Taxiway Lighting for Low-Visibility Operations

CAT II / CAT III operations can also require enhanced taxiway guidance. Indian AIP documentation provides airport-specific examples of the facilities below.

Taxiway centreline lightsStop barsRunway guard lightsHolding-position lightingLead-on lightingLead-off lightingOther associated visual guidance
07 · Centreline Circuit

Taxiway Centreline Lighting

Taxiway centreline lighting provides longitudinal guidance through designated taxi routes, and its role can become particularly important during low-visibility operations. The exact taxiway routes equipped with centreline lighting are airport-specific.

LED / Light Fixture
Secondary Connector
Isolating Transformer
Primary Connector
Primary Cable
CCR
Control / Monitoring
08 · Holding Positions

Stop Bar Lighting & Runway Guard Lights

Stop bars are associated with aircraft holding positions and runway-access control. Runway guard lights provide an additional visual indication at runway/taxiway interfaces, and can form part of the low-visibility taxi guidance system alongside stop bars, taxiway centreline lighting and holding-position markings.

A stop bar system can involve inset lighting fixtures, series circuits, isolating transformers, connectors, a CCR, and an associated control and monitoring system. For low-visibility operations, stop-bar serviceability can have direct operational consequences.

Current Kolkata AIP material, for example, specifies stop-bar serviceability conditions for operations at very low RVR values.

09 · Circuit Priority

AGL Critical Circuits

Not all airfield lighting circuits necessarily have the same operational importance. For CAT II / CAT III applications, airport documentation can identify critical AGL circuits and establish their power, monitoring and serviceability requirements. The specific classification should always be taken from the applicable airport documentation.

Runway edge lightingRunway centreline lightingRunway end lightingThreshold lightingTouchdown zone lightingPrecision approach lightingCertain taxiway lighting facilities
10 · Power Supply & Availability

AGL Power Supply for CAT II / CAT III

Power supply is a major part of the low-visibility AGL system. The exact architecture, changeover time and backup duration depend on the airport and project.

Normal Power
UPS
Critical AGL Loads
Standby Diesel Generator
11 · Continuity of Supply

UPS Support & Automatic DG Takeover

A UPS can provide continuity of supply to critical AGL loads during transfer from the normal power source to standby generation, while a standby Diesel Generator (DG) may provide the longer-duration backup source after loss of commercial power. The exact design parameters must be verified from the airport's approved electrical system.

Zero or near-continuous interruption during transfer
Temporary power support during changeover
Critical-circuit continuity
Controlled transition to generator supply
Automatic DG start on sustained loss of commercial power
Transfer arrangement and timing set by the airport system
12 · Failure Sequence

Power Failure Scenario

A simplified CAT II / CAT III critical-power sequence can be represented as below. The actual switching sequence, backup duration and affected circuits vary by airport.

Normal Supply
Power Failure
UPS Takes Over
Critical AGL Remains Available
DG Starts & Takes Over
Continued Supply
13 · Airport Example

Hyderabad Airport (VOHS) Example

Current AAI eAIP information for Rajiv Gandhi International Airport, Hyderabad demonstrates one airport-specific CAT II / CAT III AGL arrangement — not a universal design for every Indian airport.

Precision Approach CAT II/III lighting is installed for RWY 09R, while CAT I precision approach lighting is installed for RWY 27L, 09L and 27R.

Critical runway edge, runway centreline and runway end AGL circuits are supported by UPS with zero switch-over time and 30 minutes of power backup; during low visibility, the UPS takes over without interruption.

If commercial power is not restored after 30 minutes, the DG takes over automatically. Stop bars and taxiway centreline lights are provided on specified taxiways, and the airport's LVP documentation includes AGL serviceability requirements and operational actions when required facilities become unserviceable.

14 · Airport Example

Kolkata Airport (VECC) Example

Current AAI eAIP information for NSCBI Airport, Kolkata shows a different airport-specific arrangement — and should not be copied directly into another airport's design.

Kolkata's primary runway, 01R/19L, has ILS CAT III facilities from both ends as of the northern-end (19L) upgrade commissioned in late 2025; the AGL system is identified as a required serviceable facility for the applicable low-visibility operations.

UPS / standby DG arrangements are provided for the aeronautical ground lighting system, designed around the changeover requirements associated with the applicable DGCA CAR.

The airport's LVP procedures identify specific AGL facilities that must be inspected for serviceability, and specify operational consequences for certain lighting unserviceabilities during low-visibility operations.

15 · Serviceability

CAT II / CAT III AGL Serviceability

Serviceability becomes a critical engineering and operational consideration. The operational consequence of an AGL fault depends on the facility affected, the number and position of failed lights, circuit configuration, RVR / visibility, operational category and airport procedures.

Advisory to aircraft
Restriction of operations
Suspension of CAT II / CAT III operations
Closure of an affected taxi route
Restoration required before resuming affected operation
Consequences defined through airport-specific LVP procedures
16 · Circuit Design

AGL Redundancy & Interleaved Circuits

Critical lighting systems can use multiple circuits or independent power arrangements to reduce the operational effect of a single circuit failure. Some airport systems use interleaved circuits so that lighting points are distributed between circuits — the operational consequence of losing one circuit depends on the actual configuration.

Independent circuitsDependent circuitsInterleaved circuitsRedundant circuits

Current Hyderabad AIP information, for example, identifies different circuit arrangements for runway lighting and explains their effect on operational serviceability.

17 · Series Circuit

CCR, Transformers & Connectors

The CCR remains a core part of the AGL series-circuit system and should be assessed together with the connected series circuit and critical lighting load. A typical series circuit runs CCR → Primary Cable → Primary Connector → Isolating Transformer → Secondary Connector → Light Fixture, and for critical circuits the complete chain should be maintained and tested as an integrated system.

CCR

Current output, intensity steps, protection, monitoring, control, circuit status and fault indication.

Isolating Transformers

Transformer condition, insulation, connections, environmental condition, rating, compatibility and replacement availability.

Connectors

Primary and secondary connectors, L-823 plug/receptacle arrangements, mechanical condition, connection integrity and environmental sealing.

18 · Systems Integration

Control & Monitoring / Relationship with ILS & RVR

Critical AGL systems can require monitoring of CCR status, circuit status, faults, lighting status, power status and control-system status. CAT II / CAT III operations involve more than AGL — the AGL system operates alongside the ILS, RVR and surface movement systems below. The exact interface is airport-specific.

ALCMSATC systemsAirport control systemsSurface movement systemsILS localizerILS glide pathILS DMERVR systemsStandby powerOperational procedures
19 · LVP & Fault Diagnosis

Low Visibility Procedures & Fault Diagnosis

LVP is an operational procedure implemented to support safe airside operations in defined low-visibility conditions. A fault should be traced systematically to distinguish a local fixture failure from a system-level fault. The exact procedure is airport-specific.

Pre-LVP inspection of critical facilities
Activation of appropriate lighting
Power-system & standby DG readiness
Verification of UPS
Inspection of critical circuits
Withdrawal of incompatible maintenance works
Communication with ATC / SMC
Individual fault: fixture → connector → transformer → cable → CCR
Multiple failures: start from CCR → circuit → power supply
Current Kolkata AIP material identifies these inspection categories explicitly
20 · Photometry & Commissioning

Photometry, Electrical Design & Testing / Commissioning

Photometric verification can be especially important for precision visual guidance systems, and alignment matters particularly where the optical output of a fixture is directional — a physically illuminated fixture is not necessarily correctly aligned. CAT II / CAT III design also requires detailed evaluation across series circuit, CCR, power and control disciplines, verified through electrical, functional, photometric, power and final integrated testing.

Light intensityBeam alignmentBeam distributionColour / chromaticityFixture orientationUniformity where applicableCable continuity & insulationUPS / DG changeover testIntegrated commissioning
21 · Reference Tools

CAT II / CAT III Compliance Matrix

A useful project document is a dedicated low-visibility AGL compliance matrix. Actual references and acceptance criteria should be populated from the applicable project documentation.

RequirementSystemReferenceVerification
Precision approach lightingApproachProject / applicable standardDesign + inspection
Runway centrelineRunwayProject / applicable standardFunctional + photometric
Touchdown zoneRunwayProject / applicable standardFunctional + photometric
Critical powerAGL powerAirport / projectUPS / DG test
Stop barTaxiwayAirport / projectFunctional test
Taxiway centrelineTaxiwayAirport / projectFunctional / inspection
CCRElectricalApplicable specificationFactory / site test
ServiceabilityComplete systemAIP / LVP procedureInspection
ChangeoverPowerProject / airport requirementPower-failure simulation / test
MonitoringControlProject specificationFunctional test
22 · Precision AGL Solutions

CAT II / CAT III AGL Technical Support

Precision AGL Solutions positions its CAT II / CAT III support around specialised AGL engineering, equipment and technical coordination across the areas below — the answers to a project's key engineering questions should always come from the airport's current documentation.

Lighting

Precision approach, runway, taxiway, centreline & touchdown zone lighting, stop bars, runway guard lights.

Electrical

CCR support, isolating transformers, primary cable, primary & secondary connectors, L-823 connections.

Technical

Technical submittals, compliance documentation, BOQ support, equipment selection, replacement assessment.

Delivery

Installation support, testing & commissioning, photometry, ongoing maintenance support.

Important engineering principle: lighting availability is not only a fixture issue. It is a complete system issue involving lighting, series circuits, power supply, control, monitoring, inspection, maintenance and operational procedures — a runway light can be perfectly functional while the overall system still has a problem elsewhere in the chain.

The Hyderabad and Kolkata examples on this page demonstrate how airport-specific requirements can differ; an airport-specific AGL configuration should not be copied from one Indian aerodrome to another without checking the applicable design and operational requirements, current AIP/eAIP, DGCA requirements, approved design and project specification.

FAQs

Frequently Asked Questions

What AGL systems support CAT II/III operations in India?
Precision approach lighting, runway edge, centreline and end lighting, threshold and touchdown zone lighting, taxiway centreline lighting, stop bars, runway guard lights and associated control and monitoring.
How is power supply handled for critical AGL circuits?
Indian airports document arrangements such as UPS support and automatic DG takeover for critical AGL circuits, as seen in current AIP information for Hyderabad Airport.
Why does serviceability matter more for CAT II/III airports?
CAT II/III operations place greater importance on AGL serviceability, with AIP procedures for Indian aerodromes specifying inspection and operational consequences for unserviceable critical lighting facilities.
Why do stop bars matter more during low-visibility operations?
Stop bars control runway access at holding positions, and current Kolkata AIP material specifies stop-bar serviceability conditions for operations at very low RVR values, making their availability directly relevant to low-visibility taxi operations.
What happens if a critical runway light becomes unserviceable during CAT III operations?
The consequence depends on the facility, circuit configuration and RVR, and can range from an advisory to aircraft through to suspension of CAT II/III operations, as defined by the airport's own LVP procedures.
How is a CAT II/III AGL system commissioned?
Commissioning typically covers electrical testing (cable, insulation, CCR), functional testing (fixtures, stop bars, control), photometric verification, power testing (UPS/DG changeover) and a final integrated system test before operational handover.

Looking for an AGL Solution in India?

Share your BOQ, technical specification, existing AGL configuration or project requirement for application-focused AGL support.

Talk to Precision AGL Solutions

Follow Precision AGL Solutions

Our Academy: Precision AGL Academy