Approach & Landing Systems Comparison

CAT I CAT II CAT III

Precision Approach Lighting Across Three Low-Visibility Categories — CAT I, CAT II and CAT III represent progressively more demanding precision approach operations. The approach lighting system is an important part of this progression, but it is not the sole factor that determines the approach category. CAT III is not simply "brighter CAT II" — it is a higher-integrity low-visibility operation in which visual references may be extremely limited.

At a Glance

Parameter CAT I CAT II CAT III
Approach typePrecision approachPrecision approachPrecision approach
Typical decision height≥ 200 ft< 200 ft and ≥ 100 ftDepends on subcategory & applicable criteria
VisibilityHigherLowerVery low
RVRTypically ≥ 550 mTypically ≥ 300 mTypically < 175 m, per subcategory
Typical FAA ALSALSF-1ALSF-2ALSF-2
Approach lightingPrecision approach lightingEnhanced precision approach lightingHigh-integrity low-visibility system
Inner visual referencesStandardEnhancedEnhanced
Red side-row configurationNot the defining CAT I arrangementYes, with ALSF-2Yes, with ALSF-2
Runway centreline lightsDepends on runway/designRequiredRequired
Touchdown zone lightsDepends on runway/designRequiredRequired
Sequenced flashersApplicableApplicableApplicable
MonitoringRequired as applicableMore demandingHighly critical
Power continuityImportantCriticalExtremely critical
System redundancyApplicableHigherVery high
Dependence on visual referencesHigherReducedPotentially very limited
≥ 200 ft
CAT I Decision Height
100–199 ft
CAT II Decision Height
< 100 ft / No DH*
CAT III · Per Subcategory

*CAT IIIA/IIIB permit a DH below 100 ft (or no DH) depending on subcategory; CAT IIIC has no DH and no RVR limit. Always confirm exact values against the current governing standard for the specific project.

What Changes from CAT I to CAT III?

CAT I

Instrument approach → visual acquisition at a higher decision height → landing.

CAT II

Instrument approach → visual acquisition at a lower decision height → enhanced runway visual guidance → landing.

CAT III

Highly reliable instrument/landing system → extremely limited visual reference → highly controlled landing and rollout environment.

The CAT I → CAT II → CAT III progression means increasing requirements for low visibility capability, visual guidance, lighting availability, monitoring and overall system integrity.

CAT I Approach Lighting

CAT I precision approaches are generally associated with a decision height of 200 ft or higher. For FAA configurations, ALSF-1 is commonly associated with CAT I approaches. A typical CAT I system provides:

  • Approach centreline
  • Crossbars
  • High-intensity lights
  • Sequenced flashing lights where applicable
  • Red inner approach references
  • Threshold visual reference

The objective is to provide sufficient visual information for the pilot to transition from instrument guidance to the runway environment. Engineering memory: CAT I → ALSF-1 → standard precision visual transition.

CAT II Approach Lighting

CAT II allows operations at a lower decision height and lower visibility than CAT I. For FAA operations, ALSF-2 is the typical high-intensity approach lighting configuration. The inner approach area adds:

  • White centreline bars
  • Red side-row bars
  • White crossbars, incl. 500-ft & 1,000-ft crossbars
  • Sequenced flashing lights

CAT II also requires the appropriate runway lighting system, including runway centreline and touchdown zone lighting. Engineering memory: CAT II → ALSF-2 → enhanced inner approach + low-visibility runway lighting.

CAT III Approach Lighting

CAT III does not necessarily use a separate ALS configuration. In FAA practice, ALSF-2 provides visual guidance for both CAT II and CAT III instrument approaches. Therefore: CAT II ≠ ALSF-2 alone, and CAT III ≠ ALSF-3.

A better representation: CAT I → ALSF-1 · CAT II → ALSF-2 · CAT III → ALSF-2 + complete CAT III low-visibility system requirements. The approach lighting configuration alone does not establish CAT III capability.

CAT III Subcategories

CAT III operations are further divided according to the applicable regulatory system. A simplified engineering view:

CAT IIIA

Very low visibility with limited or no reliance on decision height, depending on applicable criteria.

CAT IIIB

Lower visibility than IIIA with greater system and operational requirements.

CAT IIIC

Conceptually no decision height and no RVR limitation, though operational implementation is highly constrained.

The exact values and operational criteria must be taken from the applicable current regulatory standard. For airport engineering, do not use a generic CAT III table to establish design requirements.

Approach Lighting Feature Comparison

Feature CAT I CAT II CAT III
High-intensity ALSYesYesYes
Approach centrelineYesYesYes
CrossbarsYesYesYes
Sequenced flashingApplicableApplicableApplicable
Red inner referencesALSF-1 configurationALSF-2 configurationALSF-2 configuration
Red side rowsNot the defining CAT I configurationYesYes
500-ft crossbarNot the defining CAT I featureYesYes
Visual transitionStrongly dependent on pilot acquisitionReduced visual acquisition windowVisual reference may be extremely limited

Runway Lighting Comparison

The approach lighting system cannot be considered separately from the runway lighting.

Runway Lighting CAT I CAT II CAT III
Runway edge lightsYes, as applicableYesYes
Threshold lightsYesYesYes
Runway centrelineDesign-dependentRequiredRequired
Touchdown zone lightingDesign-dependentRequiredRequired
Runway end lightsApplicableApplicableApplicable
High-intensity runway lightingAs requiredYesYes
Lighting monitoringApplicableEnhancedHighly critical

Touchdown Zone Lighting (TDZL)

TDZL becomes particularly important as approach visibility decreases, providing visual information about the touchdown area and helping the pilot identify longitudinal position relative to the runway.

CAT I

TDZL requirement depends on the applicable runway and approach configuration.

CAT II

TDZL is an important component of the low-visibility runway lighting system.

CAT III

TDZL remains part of the runway visual system, but CAT III cannot depend solely on visual identification of the touchdown zone.

Runway Centreline Lighting

Runway centreline lighting provides a strong longitudinal visual reference during final approach, flare, touchdown and rollout — its importance increases significantly with reduced visibility.

CAT I

Requirement depends on the runway and applicable design criteria.

CAT II

Required as part of the applicable CAT II runway lighting system.

CAT III

Critical component of the low-visibility runway lighting system, especially during rollout.

Electrical Engineering Progression

Simplified architecture: Main power supply → alternate/emergency power → CCR → primary series circuit → isolation transformers → AGL fixtures → monitoring & control.

For CAT II and CAT III, additional attention is required for

CCR and Series Circuit

The Constant Current Regulator (CCR) maintains the required current in the airport series circuit. Typical engineering checks include CCR rating, number of fixtures, transformer wattage, circuit load, cable length and resistance, voltage drop, power factor where applicable, insulation resistance, earth leakage and circuit monitoring.

For CAT II/III systems, the design must also account for the applicable power-transfer and serviceability requirements.

Power Supply Reliability

CAT I

Reliable power is required for the applicable lighting system.

CAT II

Rapid transfer and reliable availability of critical lighting systems become much more important.

CAT III

Power continuity, redundancy and monitoring become fundamental to the operational approval of the system.

Simplified concept: Normal power → automatic transfer → alternate/emergency source → critical AGL loads. The exact transfer time, redundancy and backup architecture must be established from the governing standard and airport operational approval.

Monitoring Requirements

CAT I

  • CCR status
  • Circuit status
  • Control status
  • Major equipment faults

CAT II

  • Approach circuits
  • Runway centreline & TDZ lighting
  • CCRs & flashers
  • Power supply & control systems

Monitoring becomes even more critical because failures of essential equipment can directly affect low-visibility operational capability. The system should provide appropriate fault indication and support rapid maintenance response per the applicable requirements.

Photometric Verification

All three categories require appropriate verification of lighting performance.

CAT I

  • Intensity
  • Colour
  • Alignment
  • Beam distribution
  • Crossbar performance

CAT II

  • Inner approach configuration
  • Red side-row performance
  • Centreline alignment
  • Runway centreline & TDZ lighting

CAT III

Same photometric principles apply, but consequences of degradation are more significant. Verification should include approach lighting, runway centreline, TDZ, edge and threshold lighting, colour, alignment, intensity and control functions.

Alignment Is Critical

A fixture can be electrically healthy but photometrically incorrect. Common causes include incorrect vertical/horizontal aiming, fixture movement, damaged optical assembly, prism contamination, improper installation and structural movement. For low-visibility systems, correct alignment of the approach and runway lighting system is essential.

Maintenance Comparison

Maintenance Activity CAT I CAT II CAT III
Routine visual / fixture inspectionRequiredRequiredRequired
Cable inspection / insulation resistanceRequiredRequiredRequired
CCR testingRequiredRequiredRequired
PhotometryRequiredRequiredRequired
AlignmentRequiredCriticalCritical
Flasher testingApplicableRequiredRequired
Power-transfer testingApplicableCriticalExtremely critical
Monitoring verificationRequiredCriticalExtremely critical
Fault responseNormalFastVery fast / operationally critical

What Does CAT III Really Add?

It is tempting to say "CAT III adds more lights." That is not the correct engineering interpretation — CAT III adds system capability and integrity requirements.

The complete system may require greater attention to

CAT III is a complete low-visibility operational system, not merely an approach-lighting upgrade.

CAT I vs CAT II vs CAT III: Engineering Matrix

Engineering Area CAT I CAT II CAT III
Visibility requirementHigherLowerVery low
Decision heightHigherLowerVery low / potentially none
ALSTypically ALSF-1Typically ALSF-2ALSF-2 in FAA configuration
Inner ALS complexityStandardEnhancedEnhanced
Runway centrelineAs applicableRequiredRequired
TDZ lightingAs applicableRequiredRequired
Power reliabilityHighVery highExtremely high
MonitoringRequiredEnhancedCritical
RedundancyApplicableHighVery high
PhotometryRequiredRequiredRequired
AlignmentRequiredCriticalCritical
Dependency on visual referenceHigherReducedVery limited
Overall system integrityHighVery highHighest

Myths vs Facts

Myth: CAT III needs ALSF-3
Fact

There is no simple FAA "ALSF-3 = CAT III" relationship. FAA uses ALSF-2 for CAT II/III visual guidance.

Myth: CAT III is just brighter CAT II
Fact

CAT III is primarily about complete system integrity and low-visibility operational capability, not simply light intensity.

Myth: More approach lights automatically mean a higher approach category
Fact

Approach category depends on the complete approved operational system.

Myth: ALSF-2 automatically makes a runway CAT II or CAT III
Fact

No. Navigation systems, runway lighting, power, monitoring, aircraft capability, procedures and regulatory approval are also involved.

Myth: CAT III means the pilot does not need any runway lighting
Fact

CAT III runways use extensive lighting systems. However, the pilot's ability to obtain external visual reference can be extremely limited.

Engineering Workflow

Sequence: Determine approach category (CAT I/II/III) → identify governing standard → determine ALS configuration → determine runway lighting requirements → design approach series circuits → design runway centreline & TDZ circuits → select CCRs → calculate circuit loading → select isolation transformers → design primary & secondary cabling → design control & monitoring → design emergency/alternate power → installation → electrical testing → photometric testing → alignment verification → power transfer testing → integrated system testing → operational approval.

CAT I vs CAT II vs CAT III

Engineering Verdict

The lighting system is one component of the overall approach and landing capability — CAT I, CAT II and CAT III are operational categories, not lighting-hardware tiers.

CAT IStandard precision approach + higher visual acquisition height. AGL: typically ALSF-1 + applicable runway lighting.
CAT IILower decision height + lower visibility + enhanced visual references. AGL: typically ALSF-2 + runway centreline + TDZ lighting + enhanced low-visibility infrastructure.
CAT IIIVery low visibility + highly reliable landing system + potentially extremely limited visual reference. AGL: ALSF-2 in FAA practice + CAT III-compliant runway lighting + highly reliable power, monitoring, navigation/landing and operational systems.

The key engineering lesson: CAT I, CAT II and CAT III are operational categories. ALSF-1 and ALSF-2 are approach-lighting configurations. They should not be treated as interchangeable classifications.

Engineering & Expert Notes

Treat Each Step as a Change of System, Not Just Intensity
Principle

Higher categories bring more demanding lighting, monitoring and power. Check each part.

Check Secondary Power and Switch-Over Times
Power

Verify behaviour against the applicable requirement by test.

Look at Monitoring and Control Requirements
Control

Status feedback and fault response matter more at lower visibility.

Verify With Current Official Documents
Compliance

Confirm requirements in the current edition before deciding.

Frequently Asked Questions

What is the single biggest difference across CAT I, II and III?

Decreasing decision height and visibility minima, paired with increasing requirements for runway lighting completeness, power reliability, monitoring and redundancy — CAT III is defined by system integrity, not just lighting hardware.

Do CAT II and CAT III use different approach lighting systems?

Not necessarily. In FAA practice, ALSF-2 provides visual guidance for both CAT II and CAT III approaches — CAT III is not automatically "ALSF-3."

Is touchdown zone lighting required at all three categories?

It depends on the runway and design for CAT I, but is required for CAT II and CAT III, becoming increasingly critical to overall landing capability as visibility decreases.

Can an airport be classified CAT III based on its approach lighting alone?

No. Approach category depends on the complete approved system — navigation/landing equipment, runway lighting, power reliability, monitoring, redundancy, aircraft/crew capability and operational approval.

What are CAT IIIA, IIIB and IIIC?

They are CAT III subcategories with progressively lower visibility and decision-height requirements, defined by the applicable regulatory framework — always verify exact values against the current governing standard rather than a generic table.

Why does power reliability matter more at higher categories?

Because the pilot has progressively less external visual reference to fall back on, so the lighting and landing system itself must remain available and accurate through automatic transfer, redundancy and continuous monitoring.

Governing Documents

For an actual project design, always verify the current edition of the applicable documents.

FAA AC 150/5340-30

Design and Installation Details for Airport Visual Aids — ALSF-1/ALSF-2 configurations, installation, photometric requirements and electrical systems.

ICAO Annex 14, Volume I

Aerodrome Design and Operations — precision approach categories, decision height and RVR criteria, approach lighting configuration and operational requirements.

DGCA / AAI Requirements

For Indian airport projects, also verify applicable DGCA requirements, AAI requirements, airport-specific technical specifications, project drawings and contract specifications.

Final Engineering Note

Do not classify an airport as CAT I, CAT II or CAT III based only on its approach lighting system. Verify approach category, decision height, RVR, navigation/landing system, lighting configuration, power-transfer requirements, monitoring, redundancy, aircraft/crew requirements, low-visibility procedures and current governing standards.

CAT I → visual transition at a higher decision height. CAT II → enhanced visual guidance at lower visibility. CAT III → maximum low-visibility system integrity with very limited visual reference.

Precision AGL Academy

Compare the Systems. Then Learn How to Engineer Them.

Understanding the difference between AGL systems is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how AGL systems work as part of a complete airport lighting system, not just as individual components or configurations.

Compare. Understand. Apply. Engineer.

Continue Exploring