Testing & Commissioning Comparison

FAT VS SAT

Factory Acceptance Test vs Site Acceptance Test — two distinct stages in the quality-assurance and commissioning lifecycle of AGL equipment and systems. FAT proves the equipment is ready for the site. SAT proves the installed equipment and system are ready for operation at the airport.

Equipment verification Site verification Acceptance milestone

At a Glance

Parameter FAT SAT
Full formFactory Acceptance TestSite Acceptance Test
LocationManufacturer's factoryProject / airport site
TimingBefore shipmentAfter installation
Main purposeVerify equipment manufacture & functionalityVerify installed system & site integration
EnvironmentControlled factory environmentActual project environment
Installation statusFactory assembledInstalled and commissioned
WitnessesClient / consultant / manufacturerClient / consultant / contractor
DocumentationFAT reportSAT report
Site interfacesLimited / simulatedFully checked
Handover relevancePre-shipment acceptanceFinal site acceptance
FAT
"Does the equipment work correctly before it leaves the factory?"
SAT
"Does the installed system work correctly at site?"

What Is FAT & SAT?

FAT — Factory Acceptance Test

FAT is performed at the manufacturer's facility before dispatch. The test verifies that the equipment has been manufactured in accordance with the approved design and project specification, and that it performs its intended functions correctly.

Typical AGL equipment that may undergo FAT

  • Constant Current Regulators (CCR)
  • AGL control panels
  • Remote-control / monitoring panels
  • Lighting control systems
  • Transformers
  • Other packaged electrical equipment

Main objective: Prove that the manufactured equipment complies with the approved design and specification before shipment.

SAT — Site Acceptance Test

SAT is performed at the project site after installation. The test verifies that the installed equipment and system function correctly under actual site conditions, with all site interfaces, cabling, fixtures and supporting infrastructure in place.

SAT verifies

  • Correct installation
  • Cable connections and polarity
  • Insulation resistance
  • CCR output and regulation
  • Lighting operation and brightness steps
  • Control and remote operation
  • Monitoring and alarms
  • Integration with other installed equipment

Main objective: Prove that the installed equipment/system is ready for operation at the airport.

FAT & SAT in the Project Lifecycle

DESIGN

Equipment designed to approved specification.

MANUFACTURE

Equipment manufactured and assembled at factory.

FAT

Factory Acceptance Test — verify equipment before dispatch.

PASS / DISPATCH

Equipment cleared for shipment to site.

DELIVERY

Equipment arrives at airport project site.

INSTALLATION

Equipment installed, cabled and connected.

SAT

Site Acceptance Test — verify installed system.

ACCEPT / HANDOVER

System accepted for operational use.

FAT vs SAT — Test Scope

Test Area FAT SAT
Visual inspectionYes — equipment conditionYes — installed condition
Wiring verificationYes — internal wiringYes — site cabling & terminations
Insulation testsYes — equipmentYes — complete circuit
Output current / regulationYes — test loadYes — actual installed load
Step / brightness controlYes — functional checkYes — with actual fixtures
Protection functionsYesYes — with site conditions
Alarm / monitoringYesYes — with site interfaces
Control interfaceSimulatedActual site control system
Fixture operationNot applicableYes — all installed fixtures
Cable continuity / polarityNot applicableYes
System integrationLimitedFull site integration
Emergency / failure functionsSimulatedActual site conditions

FAT vs SAT — CCR Example

Suppose a 6.6 A Constant Current Regulator (CCR) is supplied for an airport project.

FAT — At the Factory

CCR
  │
  ▼
TEST LOAD
  │
  ▼
MEASURE
CURRENT / VOLTAGE /
PROTECTION / CONTROL

The manufacturer verifies that the CCR performs correctly against the approved test procedure and specification.

SAT — At the Airport

CCR
  │
  ▼
6.6 A SERIES CIRCUIT
  │
  ▼
ISOLATION TRANSFORMERS
  │
  ▼
RUNWAY / TAXIWAY LIGHTS

The installed system is tested as a complete site installation — verifying that the CCR operates correctly with the actual installed circuit and equipment.

Key insight: The CCR may pass FAT perfectly, but SAT is still required to verify that the entire installed system — CCR, series circuit, isolation transformers and fixtures — operates together correctly at the airport.

Controlled Environment vs Actual Site Conditions

FAT — Controlled Factory Environment

  • Controlled temperature and conditions
  • Test load instead of actual fixtures
  • Simulated control signals
  • No site cable runs
  • No site interference
  • No site installation variables

SAT — Actual Airport Site

  • Actual site environment
  • Actual cables and cable runs
  • Actual fixtures and loads
  • Actual control system
  • Actual monitoring interfaces
  • Actual site installation conditions

SAT therefore provides information that cannot always be obtained during FAT — site cabling, actual fixture loads, control-system integration and the influence of the installed environment.

What Happens When a Test Fails?

FAT Failure

FAT
  │
  ▼
FAIL
  │
  ▼
CORRECTIVE ACTION
  │
  ▼
RETEST
  │
  ▼
PASS
  │
  ▼
DISPATCH

A failed item should generally be resolved before shipment.

SAT Failure

SAT
  │
  ▼
FAIL
  │
  ▼
SITE RECTIFICATION
  │
  ▼
RETEST
  │
  ▼
PASS
  │
  ▼
ACCEPTANCE

SAT failures may involve either equipment issues or installation/interface issues.

Example: CCR OK + Control Panel OK + Cable Installation ✕ → SAT Failure

FAT vs SAT Documentation

FAT Documentation

  • Approved FAT procedure
  • Inspection checklist
  • Test results
  • Calibration certificates
  • Equipment test records
  • Non-conformance records (if applicable)
  • FAT report
  • Certificate of acceptance / release

SAT Documentation

  • Approved SAT procedure
  • Site test records
  • Commissioning records
  • Cable test results
  • Functional test results
  • Alarm / monitoring test results
  • As-built verification
  • Punch-list / NCR records
  • SAT report
  • Site acceptance certificate

Who Is Involved?

FAT — Typical Participants

  • Manufacturer — conducts the test
  • Client / Consultant — may witness FAT
  • Inspection / QA Team — verification

The client or consultant may witness FAT according to the approved inspection and test plan (ITP).

SAT — Typical Participants

  • Contractor — installation and testing
  • Manufacturer / Commissioning Team — support
  • Client / Consultant — witnessing and approval
  • Site Operations — operational verification

The exact responsibilities are project-specific and defined in the contract and ITP.

Full Engineering Parameters

Parameter FAT SAT
Primary focusEquipmentInstalled system
LocationFactorySite
TimingPre-dispatchPost-installation
EnvironmentControlledActual
Equipment testYesYes
Installation testLimitedYes
System integrationLimitedYes
Site cablingUsually simulated / test setupActual
Field interfacesLimitedFully tested
Main acceptanceEquipment acceptanceSite / system acceptance
WitnessingClient optionalClient required
Remedial actionFactory rectificationSite rectification

Myths vs Facts

Myth: A successful FAT means SAT will also pass
Fact

No. A successful FAT does not automatically mean that the installed system will pass SAT. Site installation, cabling and integration issues can cause SAT failure even when the equipment is perfectly manufactured.

Myth: SAT can replace FAT
Fact

No. SAT does not replace FAT. Manufacturing defects should be identified during FAT, not discovered at site. Relying on SAT to catch equipment defects is not an acceptable quality-assurance strategy.

Myth: FAT and SAT are the same test performed in different locations
Fact

They are fundamentally different tests with different objectives, scopes and environments. FAT tests the equipment; SAT tests the installed system.

Myth: SAT is only about turning the system on
Fact

SAT involves comprehensive testing of installation, cabling, insulation, control, monitoring, alarm functions, intensity steps, system integration and operational performance — not just "power on."

Myth: If the equipment has a type-test certificate, FAT is not required
Fact

Type testing and FAT serve different purposes. Type testing validates the design; FAT verifies that the specific manufactured unit meets the specification and is free from manufacturing defects.

Easy Memory

FAT

FACTORY
  │
  ▼
EQUIPMENT
  │
  ▼
TEST
  │
  ▼
PASS
  │
  ▼
SHIP

FAT proves the equipment is ready for the site.

SAT

SITE
  │
  ▼
INSTALL
  │
  ▼
CONNECT
  │
  ▼
TEST
  │
  ▼
PASS
  │
  ▼
ACCEPT

SAT proves the installed system is ready for operation.

FAT vs SAT — The Engineering Perspective

Engineering Verdict

FAT and SAT are not interchangeable — they are complementary stages in the quality-assurance and commissioning lifecycle.

FAT provides confidence that the manufactured equipment meets the specification before it leaves the factory. SAT provides confidence that the installed system operates correctly at the airport, with all site interfaces, cabling and fixtures in place.

For an AGL project, FAT is primarily equipment-level verification before dispatch, while SAT is installation, functional and system-integration verification at the airport.

FATFactory — Equipment — Pre-dispatch verification.
SATSite — Installed system — Post-installation verification.

Critical engineering point: A successful FAT does not guarantee a successful SAT, and SAT should not be relied upon to catch manufacturing defects. Both tests are necessary and serve different purposes in the project quality-assurance framework.

Engineering & Expert Notes

Do Not Assume SAT Repeats FAT
Scope

FAT proves the equipment; SAT proves the installed system. Plan both and avoid gaps.

Use FAT Records as the Baseline for SAT
Baseline

Compare site results with factory data to spot transit or installation damage.

Test Interfaces on Site
Integration

Many problems appear only where equipment connects. Include those tests.

Close Punch Items Before Handover
Closure

Track defects to completion and retest as needed.

Frequently Asked Questions

What is the main difference between FAT and SAT?

FAT is performed at the factory before shipment to verify equipment manufacture and functionality. SAT is performed at the site after installation to verify the installed system and site integration.

Does a successful FAT guarantee SAT success?

No. SAT can fail due to site installation issues — cabling errors, incorrect terminations, damaged cables, site environment, control-system integration problems — even when the equipment itself is perfectly manufactured.

Can SAT replace FAT?

No. SAT does not replace FAT. Manufacturing defects should be identified during FAT, not discovered at site. Relying on SAT to catch equipment defects is not an acceptable quality-assurance approach.

Who typically witnesses FAT?

The client or consultant may witness FAT according to the approved inspection and test plan. The manufacturer conducts the test; the client/consultant provides verification.

What happens if FAT fails?

Corrective action is taken at the factory, followed by retesting. The equipment should generally not be dispatched until FAT is passed.

What happens if SAT fails?

Site rectification is carried out — this may involve rework, repair, replacement or adjustment. After rectification, the affected portion is retested. The system is accepted only after SAT is passed.

Is FAT required for all AGL equipment?

The requirement for FAT depends on the project specification, contract requirements and the inspection and test plan. Critical equipment such as CCRs, control panels and packaged systems typically require FAT.

Governing Documents

For an actual project, always verify the current applicable editions of the relevant documents and the approved inspection and test plan (ITP).

Project-Specific ITP

The approved Inspection and Test Plan defines the specific FAT and SAT requirements, scope, witness points and hold points for each project.

Contract Technical Specifications

The contract documents define the technical requirements, equipment specifications and acceptance criteria that FAT and SAT must verify.

Manufacturer's FAT/SAT Procedures

Approved test procedures from the manufacturer or commissioning team, detailing the test sequence, acceptance criteria and test records.

Final Engineering Note

FAT and SAT requirements are project-specific. Always verify the approved ITP, contract requirements and applicable standards for the specific project — do not rely on a generic comparison page for project execution.

FAT proves the equipment is ready for the site. SAT proves the installed system is ready for operation. Both are essential, complementary stages in the AGL project quality-assurance and commissioning lifecycle.

Precision AGL Academy

Compare the Systems. Then Learn How to Engineer Them.

Understanding the difference between AGL systems is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how AGL systems work as part of a complete airport lighting system, not just as individual components or configurations.

Compare. Understand. Apply. Engineer.

Continue Exploring