Airfield Ground Lighting cable fault diagnosis — primary series and secondary cable open circuits, short circuits, earth faults, insulation failure and leakage current, jacket and mechanical damage, crushing and cutting, water and moisture ingress, and joint-level faults from high-resistance connections through to full joint failure, plus installation and jointing faults: loose and incorrect joints, routing and bending errors, overheating, voltage drop, length and sizing errors, identification and phase/polarity errors, civil-works damage, rain- and flood-related failures, repeat faults, and hidden underground fault location. Each topic follows the full engineering diagnostic record: symptom → observation → measurement → decision → fault location → root cause → verification → corrective action → preventive action.
Symptom — An entire series circuit, or a defined section of it, goes dark and the CCR cannot maintain rated output current despite no other apparent circuit fault, consistent with a break in the primary series loop.
Primary series circuit cable (constant-current loop, typically 6.6A/8.3A/20A) connecting the CCR to the isolation transformers around the circuit.
After repair, re-energise and confirm the CCR returns to normal voltage/current regulation with full loop continuity, and megger the repaired section.
SOP: SOP-CBL-01 (Primary Series Circuit Fault Location Procedure), SOP-CCR-04 (CCR LOTO Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I, IEC 60364
Diagram: Circuit route and joint pit schedule
Case Study: Division 01 — CCR Troubleshooting; Division 24 — Complete Runway Lighting Failure
Symptom — An individual fixture is dark while the primary series circuit itself measures normal current, pointing to a break in the secondary cable between the isolation transformer and the fixture.
Secondary cable (single-core, low-voltage) between the isolation transformer secondary and the fixture, including its L-823 connectors.
Re-energise and confirm the fixture illuminates at the correct intensity across all steps.
SOP: SOP-CBL-02 (Secondary Cable Fault Procedure)
Standards: FAA AC 150/5345-26 (L-823 connectors), ICAO Annex 14 Vol I
Diagram: Base can and secondary cable wiring diagram
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — The CCR trips on overcurrent or shows abnormally low output voltage for a given current setting, consistent with a short circuit somewhere on the series circuit loop.
Primary or secondary cable insulation between conductors, or between adjacent conductors within a joint.
After repair, megger the full loop, re-energise, and confirm the CCR regulates normally without tripping across a full operating cycle.
SOP: SOP-CBL-03 (Short Circuit Fault Location Procedure), SOP-CCR-04
Standards: IEC 60364, FAA AC 150/5340-30
Diagram: Circuit route and joint pit schedule
Case Study: Division 01 — CCR Troubleshooting
Symptom — CCR earth-fault/ground-fault protection trips, or the earth-fault monitor shows a leakage path to ground, without necessarily a complete loss of circuit current.
Primary series cable insulation relative to earth/ground, including joints, base cans, and any point exposed to moisture.
Re-megger the full loop after repair and monitor the CCR earth-fault trend over subsequent operating cycles.
SOP: SOP-CBL-04 (Earth Fault Location Procedure), SOP-CCR-04
Standards: IEC 60364, ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: Circuit route drawing
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable section fails a routine or triggered insulation resistance test, reading below the acceptable threshold even though the circuit may still be operating without an active trip.
Primary or secondary cable insulation system across its full length, including conductor jacket, joints, and terminations.
Re-test the full loop after repair and confirm the reading is restored to, or above, the acceptable threshold.
SOP: SOP-CBL-05 (Insulation Resistance Test Procedure)
Standards: IEC 60364, ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: Circuit route drawing with installation dates
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A routine periodic insulation resistance test on a circuit or segment returns a value below the site's acceptable minimum, without any associated operational fault or trip yet occurring.
Full primary series circuit loop or a defined test segment, evaluated against the site's insulation resistance acceptance criteria.
Retest after any corrective action and confirm the reading is restored to, or trending toward, the acceptable range, then continue periodic monitoring.
SOP: SOP-CBL-05 (Insulation Resistance Test Procedure)
Standards: IEC 60364, ICAO Annex 14 Vol I
Diagram: Circuit route and joint schedule
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — The CCR or a dedicated leakage monitoring device reports leakage current above the acceptable threshold on a series circuit, without a full earth-fault trip having occurred.
Full primary series circuit insulation system, evaluated for cumulative leakage current to earth across all joints, transformers, and cable sections.
After repair, re-test the full loop and confirm leakage current is within the acceptable threshold, then monitor the trend over subsequent operating cycles.
SOP: SOP-CBL-06 (Leakage Current Investigation Procedure)
Standards: IEC 60364, ICAO Annex 14 Vol I
Diagram: Circuit route and transformer schedule
Case Study: Division 01 — CCR Troubleshooting
Symptom — Visual inspection or excavation reveals the outer jacket of a cable is cracked, abraded, or otherwise compromised, with or without an accompanying electrical fault yet detected.
Cable outer jacket/sheath along its buried or exposed route.
Re-megger after repair and re-inspect the repaired section after backfilling to confirm jacket integrity is maintained.
SOP: SOP-CBL-07 (Jacket Damage Assessment and Repair Procedure)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: Cable installation detail/bedding drawing
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable is found with visible mechanical damage beyond jacket-only abrasion, such as a deformed, kinked, or partially severed section, typically discovered during excavation, fault-finding, or a reported incident.
Cable conductor and insulation at the site of mechanical impact or deformation.
After repair, re-test insulation resistance and continuity and re-inspect after backfilling to confirm no further deformation.
SOP: SOP-CBL-08 (Mechanical Damage Assessment Procedure)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: Cable route and mechanical protection drawing
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A cable is found flattened or crushed along a section of its length, typically from vehicle, equipment, or heavy load contact, with possible conductor deformation even where the jacket remains intact.
Cable cross-section at the crushed location, including conductor strands and surrounding insulation.
After replacement, re-test insulation resistance and continuity, and confirm proper bedding/protection is restored before backfilling.
SOP: SOP-CBL-09 (Crushing Damage Repair Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Cable crossing protection drawing
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A cable is found fully or partially severed, typically discovered as a sudden complete circuit failure coinciding with nearby excavation, trenching, or other ground-disturbing work.
Cable conductor and insulation at the cut location, and the affected series/secondary circuit as a whole.
After repair, test the full loop for continuity and insulation resistance, re-energise, and confirm normal operation across an operating cycle.
SOP: SOP-CBL-10 (Cable Cut Repair Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Cable route drawing with splice location log
Case Study: Division 24 — Complete Runway Lighting Failure
Symptom — Standing water or moisture is found inside a cable joint, pull box, or base can, or is suspected due to an intermittent or gradually degrading insulation reading, without the cable itself necessarily being physically damaged.
Cable joints, pull boxes, base cans, and any point where the cable enters a below-grade enclosure.
After drying and resealing, re-megger, re-energise, and monitor through subsequent wet-weather cycles to confirm the entry point has been eliminated.
SOP: SOP-CBL-11 (Enclosure Moisture Inspection Procedure)
Standards: FAA AC 150/5340-30, IEC 60364
Diagram: Joint pit and base can drainage detail drawing
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — Moisture is confirmed or suspected within the cable's own insulation system, rather than just a joint or enclosure, typically identified through a gradually declining insulation resistance trend or a 'wet' characteristic on a cable diagnostic test.
Cable insulation and conductor system along its buried length, distinct from joint/enclosure water ingress.
Retest insulation resistance and, where available, the dielectric diagnostic after repair, and continue trending to confirm the condition has stabilised or improved.
SOP: SOP-CBL-12 (Cable Moisture Diagnostic Procedure)
Standards: IEC 60502/60840 (cable testing reference), IEEE 400 (VLF diagnostic guidance), FAA AC 150/5340-30
Diagram: Cable specification and installation record
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable joint (splice) fails electrically or mechanically, presenting as an open circuit, short circuit, earth fault, or a visibly damaged/overheated joint found during inspection.
Cable joint/splice kit and its enclosure, at any point along the primary or secondary circuit.
After remaking the joint, test continuity and insulation resistance, re-energise, and thermal-image the joint under normal load to confirm no abnormal heating.
SOP: SOP-CBL-13 (Cable Jointing Procedure)
Standards: IEC 60502, FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Joint location log and circuit route drawing
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A joint shows elevated electrical resistance without a complete open circuit, typically detected through a voltage drop measurement, a thermal imaging hot spot, or a gradually worsening symptom such as flicker or dimming downstream of the joint.
Cable joint/splice connection point, specifically the conductor-to-conductor crimp or connector interface within the joint.
After remaking the joint, re-measure resistance, re-energise, and thermal-image under normal load to confirm the hot spot has been eliminated.
SOP: SOP-CBL-14 (High Resistance Joint Detection Procedure)
Standards: IEC 60502, FAA AC 150/5340-30
Diagram: Joint location log and circuit route drawing
Case Study: Division 26 — Photometric & Intensity Compliance
Symptom — A joint is found mechanically loose — a connector not fully tightened/crimped, or physically able to move — during inspection, even though it has not yet produced a full electrical fault.
Cable joint/splice connector and its enclosure.
Re-check the joint after a subsequent PM cycle to confirm it has not worked loose again.
SOP: SOP-CBL-13 (Cable Jointing Procedure), SOP-CBL-14 (High Resistance Joint Detection Procedure)
Standards: IEC 60502, FAA AC 150/5340-30
Diagram: Joint location log and circuit route drawing
Case Study: Division 26 — Photometric & Intensity Compliance
Symptom — A joint is found to have been made using the wrong method, kit, or materials for the cable type/environment, discovered during inspection, fault investigation, or a failed insulation test at that location.
Cable joint/splice kit and installation method used at a specific location.
After remaking, test and document compliance with the approved procedure, and retain records for the circuit's joint log.
SOP: SOP-CBL-13 (Cable Jointing Procedure)
Standards: IEC 60502, FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Joint kit specification and approved method reference
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable is found routed differently from its as-built drawing, or routed through a location that creates an operational or safety risk, such as under a vehicle crossing without protection or too close to another service.
Cable route as installed, evaluated against the as-built drawing and applicable clearance/protection standards.
After correction, re-survey and confirm the route matches the updated as-built drawing, and archive the survey record.
SOP: SOP-CBL-15 (Cable Route Verification Procedure)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: Cable as-built route drawing
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A cable is found bent beyond its minimum bend radius, typically discovered during installation inspection, excavation, or as a contributing factor identified during an insulation/jacket fault investigation.
Cable at a bend point, particularly at transitions into base cans, pull boxes, conduit entries, or direction changes in the trench.
After correction, re-megger and re-inspect the corrected section, and confirm adequate slack/radius before backfilling.
SOP: SOP-CBL-16 (Cable Handling and Installation Procedure)
Standards: Cable manufacturer installation specification, ICAO Annex 14 Vol I
Diagram: Cable installation detail/bedding drawing
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable section runs measurably hotter than expected under normal load, identified via thermal imaging, a temperature alarm, or as a contributing factor in a repeated insulation/joint fault at the same location.
Cable conductor and insulation system along a specific section, evaluated for excess heating relative to its rated ampacity and installation conditions.
Monitor the section's temperature trend over subsequent operating cycles, including peak load conditions, to confirm the overheating has been resolved.
SOP: SOP-CBL-17 (Cable Thermal Assessment Procedure)
Standards: IEC 60287 (cable current rating), FAA AC 150/5340-30
Diagram: Cable ampacity/derating reference and circuit loading record
Case Study: Division 26 — Photometric & Intensity Compliance
Symptom — Measured voltage at a fixture or the end of a circuit run is lower than expected relative to the source, causing dim or marginal operation without a hard fault being present.
Cable conductor resistance across its full run length, evaluated for cumulative voltage drop under the circuit's operating current.
Re-measure voltage at the affected point after correction under normal operating load and confirm it falls within the acceptable range.
SOP: SOP-CBL-18 (Voltage Drop Assessment Procedure)
Standards: IEC 60364, FAA AC 150/5340-30
Diagram: Circuit voltage drop calculation record
Case Study: Division 01 — CCR Troubleshooting
Symptom — The as-installed cable length for a run differs from the design/as-built length, discovered through voltage drop issues, insufficient slack at a termination, or a discrepancy found during a route audit or fault location exercise.
Cable run length as installed, evaluated against the design specification and as-built record.
After correction, confirm the as-built record matches the field-verified length and that any downstream voltage drop or slack issue has been resolved.
SOP: SOP-CBL-15 (Cable Route Verification Procedure)
Standards: FAA AC 150/5340-30
Diagram: Cable as-built route and length record
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A cable is found to be a different conductor size (cross-sectional area) than specified for its circuit, discovered through a voltage drop issue, an ampacity/overheating concern, or a documentation audit.
Cable conductor size as installed, evaluated against the circuit's design specification.
After replacement, re-verify cable size and re-measure voltage/current at the affected point to confirm compliance.
SOP: SOP-CBL-19 (Cable Size Verification Procedure)
Standards: IEC 60364, IEC 60287, FAA AC 150/5340-30
Diagram: Circuit design specification and cable schedule
Case Study: Division 01 — CCR Troubleshooting
Symptom — A cable's physical identification — tag, marker, colour code, or route drawing label — does not match its actual circuit or destination, discovered during maintenance, fault-finding, or a routine audit, creating a risk of working on the wrong circuit.
Cable identification tags/markers at pull boxes, base cans, and panel terminations, and the associated as-built/circuit schedule documentation.
After correction, re-verify the tag against a tone-and-trace check, and confirm the as-built documentation is updated and consistent.
SOP: SOP-CBL-20 (Cable Identification and Tracing Procedure)
Standards: FAA AC 150/5340-30, site electrical safety procedure
Diagram: Circuit schedule and identification tagging standard
Case Study: Division 24 — Complete Runway Lighting Failure
Symptom — A fixture or group of fixtures exhibits abnormal behaviour — incorrect operation, a control/monitoring mismatch, or damage — traced to a cable connected with reversed polarity or, on a multi-phase feeder, an incorrect phase connection.
Cable conductor termination at a connector, transformer, or panel, where polarity or phase sequence must be correctly maintained.
After correction, re-verify polarity/phase, re-energise, and confirm the fixture(s) or downstream equipment operate correctly.
SOP: SOP-CBL-21 (Polarity and Phase Verification Procedure)
Standards: IEC 60364, FAA AC 150/5340-30
Diagram: Circuit wiring diagram with conductor marking standard
Case Study: Division 01 — CCR Troubleshooting
Symptom — A cable fault — open, short, earth fault, or physical damage — is discovered coinciding with nearby civil works such as excavation, trenching, paving, or construction, whether reported at the time or discovered afterward.
Cable conductor and insulation at the location affected by the civil works activity, and the associated circuit as a whole.
After repair, test the full loop for continuity and insulation resistance, re-energise, and confirm normal operation; log the incident against the works coordination process.
SOP: SOP-CBL-10 (Cable Cut Repair Procedure), SOP-CBL-22 (Civil Works Coordination Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Cable route drawing with civil works coordination log
Case Study: Division 24 — Complete Runway Lighting Failure
Symptom — A cable fault — typically an earth fault, short circuit, or reduced insulation resistance — appears or worsens specifically following a rainfall event, with the circuit having tested acceptable prior to the rain.
Cable insulation system and joints/enclosures at points vulnerable to rainwater ingress along the affected circuit.
After repair, monitor the circuit through at least one subsequent significant rainfall event and confirm the insulation resistance remains stable.
SOP: SOP-CBL-11 (Enclosure Moisture Inspection Procedure), SOP-CBL-04 (Earth Fault Location Procedure)
Standards: IEC 60364, FAA AC 150/5340-30
Diagram: Circuit route drawing with joint/enclosure locations
Case Study: Division 08 — Taxiway Centreline / Guidance Lighting Troubleshooting
Symptom — A cable fault occurs, or a previously marginal circuit fails outright, following a flooding event where an area of the airfield or a specific enclosure was submerged well beyond normal wet-weather conditions.
Cable, joints, pull boxes, base cans, and CCR/transformer enclosures within the flooded area.
After drying, cleaning, and repair, re-megger all affected sections, re-energise progressively, and monitor closely over the following days for any delayed degradation.
SOP: SOP-CBL-23 (Flood Response and Assessment Procedure), SOP-CBL-11 (Enclosure Moisture Inspection Procedure)
Standards: IEC 60364, FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Site drainage and flood risk map
Case Study: Division 24 — Complete Runway Lighting Failure
Symptom — The same cable section, joint, or circuit experiences a fault, of the same or varying type, on multiple separate occasions despite apparently successful repairs each time, indicating an unresolved underlying cause.
The specific cable section, joint, or circuit with a documented history of repeat faults, and the repair method(s) previously applied.
Monitor the location over an extended period, and multiple wet/dry and loading cycles, to confirm the fault does not recur following the upgraded repair.
SOP: SOP-CBL-24 (Repeat Fault Root Cause Analysis Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Circuit fault history log and route drawing
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A fault is confirmed to exist somewhere on a buried circuit via electrical testing, but its exact physical location cannot be readily determined from surface indications, requiring a structured fault-location process before any excavation.
The complete buried cable route for the affected circuit, evaluated using non-invasive fault-location techniques before physical excavation.
After excavation and repair, test the full loop for continuity and insulation resistance, and confirm the excavated location matches the electrical signature that was present before repair.
SOP: SOP-CBL-01 (Primary Series Circuit Fault Location Procedure), SOP-CBL-25 (Precision Fault Location Procedure)
Standards: FAA AC 150/5340-30, ICAO Annex 14 Vol I
Diagram: Circuit route drawing with fault-location survey markers
Case Study: Division 25 — Field Case Study Troubleshooting
Quick answers about AGL Cable troubleshooting in the AGL Troubleshooting Atlas.
Division 13 is the AGL Cable Troubleshooting reference. It publishes 30 diagnostic topics, CBL-341 to CBL-370, across 2 subsections: Cable Fault Diagnosis (15); Cable Installation & Jointing Faults (15).
Every topic follows the same diagnostic record: the symptom, equipment/system, possible causes ranked by likelihood (high, medium or low), required tools, safety precautions, diagnostic procedure, test points, root cause verification, corrective action, preventive action and related references (SOPs, standards, diagrams and case studies).
CBL-341 to CBL-355 (15 topics): Primary Cable Open Circuit; Secondary Cable Open Circuit; Cable Short Circuit; Cable Earth Fault; Cable Insulation Failure; Low Insulation Resistance; High Leakage Current; Cable Jacket Damage; Cable Mechanical Damage; Cable Crushing; Cable Cutting; Cable Water Ingress; Cable Moisture Ingress; Cable Joint Failure; High Resistance Joint.
CBL-356 to CBL-370 (15 topics): Loose Cable Joint; Incorrect Cable Jointing; Incorrect Cable Routing; Excessive Cable Bending; Cable Overheating; Cable Voltage Drop; Cable Length Error; Incorrect Cable Size; Cable Identification Error; Cable Phase/Polarity Error; Cable Damage During Civil Works; Cable Failure After Rain; Cable Failure After Flooding; Repeated Cable Fault; Hidden Underground Cable Fault.
Each procedure starts with observation before any intervention. For example, CBL-341 (Primary Cable Open Circuit) begins: Check the CCR panel: an open primary series circuit typically shows the regulator driving toward maximum voltage while current collapses, tripping an open-circuit alarm.
Each topic lists its own precautions. For example, CBL-341 (Primary Cable Open Circuit) starts with: LOTO the circuit before any work.
Related references in the topics include SOP-CBL-01 (Primary Series Circuit Fault Location Procedure), SOP-CCR-04 (CCR LOTO Procedure), SOP-CBL-02 (Secondary Cable Fault Procedure), SOP-CBL-03 (Short Circuit Fault Location Procedure), SOP-CBL-04 (Earth Fault Location Procedure), SOP-CBL-05 (Insulation Resistance Test Procedure), SOP-CBL-06 (Leakage Current Investigation Procedure) and SOP-CBL-07 (Jacket Damage Assessment and Repair Procedure), and 18 more.
Where a standard applies, it appears in the topic's Related References. Those cited in this division include FAA AC 150/5340-30, ICAO Annex 14 Vol I, IEC 60364, FAA AC 150/5345-26, IEC 60502/60840, IEEE 400, IEC 60502 and IEC 60287.
Use the search box at the top of the page to filter the 30 published topics by code, fault name or keyword; matching topics open automatically. Each diagnostic record can also be downloaded as a Word (.doc) file.
Cable faults are among the hardest to localize — buried, long, and often intermittent.
Build the technical knowledge to understand insulation resistance testing, fault-location methods, and how to distinguish a cable fault from a connector or fixture fault before you start digging.
Diagnose systematically. Understand the circuit. Build real AGL expertise.
Please read before relying on any content on this page or on any record downloaded from it.