Structured failure-investigation reference for recurring AGL component and system failures, plus the underlying human, installation, design, material, and manufacturing root-cause categories that drive them. Each topic follows a FRACAS-aligned investigative record: symptom pattern → equipment/system → contributing causes → data and tools → safety → investigation procedure → data points reviewed → root cause verification → corrective action → preventive action.
Symptom — The same isolation transformer position, transformer batch, or circuit repeatedly returns to the fault log with winding failure or short/open findings within a short interval of the last replacement, rather than the fixture population showing a normal random failure spread.
L-830 series-circuit isolation transformers across CCR-fed loops; maintenance/CMMS failure records, insulation resistance test history, and transformer batch/procurement records.
Install a correctly specified transformer from a known-good batch, correct any identified base-can drainage or CCR-side issue, and monitor insulation resistance and failure recurrence at that specific position for at least two full PM cycles before closing the investigation.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-RCL-12 (Transformer Test and Replacement Procedure)
Standards: FAA AC 150/5345-26 (isolation transformers), IEEE C57.12.91, ISO 9001:2015 Cl. 10.2 (nonconformity and corrective action)
Diagram: Circuit Design Specification and Base-Can Schedule for the affected loop
Case Study: Division 05 — Runway Centreline Light Troubleshooting (RCL-192 single transformer fault); Division 01 — CCR Troubleshooting
Symptom — A specific Constant Current Regulator repeatedly trips on the same protection (overcurrent, earth fault, over-temperature) at a similar time interval after reset, rather than the trip being a single isolated event, and the trip pattern survives a straightforward like-for-like component swap.
CCR (transformer-type or TSCR/inverter-type), its protection relays/settings, the series circuit and loop it feeds, and the CCR failure/trip log or SCADA/ALCMS event history.
After the identified cause is corrected — loop repair, relay re-setting, or component replacement — monitor the CCR trip log for at least 30 days or one full PM cycle spanning varied load and weather conditions with zero recurrence before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-CCR-04 (CCR LOTO Procedure), SOP-CCR-07 (Protection Relay Verification)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5345-10 (CCRs), IEC 61439 (protection coordination)
Diagram: CCR Single-Line Diagram and Protection Coordination Study
Case Study: Division 01 — CCR Troubleshooting; Division 24 — Complete Runway Lighting Failure
Symptom — Primary or secondary series cable faults recur along the same route, duct run, or joint location within a short interval of the previous repair, rather than cable faults being randomly distributed across the field.
L-824 primary series cable, secondary cable to fixtures, duct banks, pull boxes, and field splices/joints; cable fault location and repair history.
After repair with a correctly specified splice kit and, if required, duct/drainage remediation, megger the full loop end-to-end, re-energise, and re-test at the next two scheduled PM visits with no recurrence before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-RCL-02 (Series Circuit Fault Location Procedure)
Standards: IEC 60364 (insulation testing), ICAO Annex 14 Vol I, FAA AC 150/5340-30
Diagram: As-Built Duct and Cable Route Drawing
Case Study: Division 05 — Runway Centreline Light Troubleshooting (RCL-193 multiple light failure); Division 24 — Complete Runway Lighting Failure
Symptom — L-823 or similar plug/receptacle connectors at a specific fixture, base-can type, or region of the field repeatedly show corrosion, moisture ingress, or contact-resistance faults shortly after being reseated or replaced.
L-823 primary connectors, secondary lamp-to-transformer connectors, base cans, and the connector maintenance/replacement history for the affected population.
Reassemble with the specified grease and torque, or replace the base can/connector type where design is implicated, and re-check contact resistance at the next two PM visits with no recurrence before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-RCL-03 (Fixture Replacement Procedure)
Standards: FAA AC 150/5345-26, FAA AC 150/5345-46 (L-852), ICAO Annex 14 Vol I
Diagram: Base-Can Detail Drawing and Connector Assembly Specification
Case Study: Division 05 — Runway Centreline Light Troubleshooting (RCL-192 fixture-level fault)
Symptom — A specific fixture position, fixture model, or fixture batch returns to the fault log significantly more often than the general population, with the failure mode varying (lamp, LED, optics, housing) rather than pointing to one obvious component.
Complete inset or elevated AGL fixture assemblies (housing, optics, lamp/LED module, base), and the fixture-level failure history across the affected population.
Install the corrected fixture type or remediate the location-specific stressor, then monitor that position specifically for at least two PM cycles or one full winter/summer season, whichever is more relevant to the confirmed cause, before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-RCL-03 (Fixture Replacement Procedure)
Standards: FAA AC 150/5345-46 (L-852), ICAO Annex 14 Vol I, ISO 9001:2015 Cl. 8.7
Diagram: Runway/Taxiway High-Stress Zone Map
Case Study: Division 05 — Runway Centreline Light Troubleshooting; Division 25 — Field Case Study Troubleshooting
Symptom — LED modules at a specific fixture position, driver batch, or fixture model fail (dark, dim, wrong colour, or reduced photometric output) well before their rated life, and the pattern recurs after replacement with a nominally identical module.
LED light-emitting modules and their drivers within AGL fixtures, plus LED failure and photometric test history.
Install a correctly matched driver/LED combination or corrected thermal design, then re-test photometric output immediately and again at the next scheduled photometric survey, with hours-in-service tracked at that position to confirm life has returned to expected range.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-PHM-01 (Photometric Survey Procedure)
Standards: FAA AC 150/5345-46 (L-852 LED), ICAO Annex 14 Vol I Appendix 2 (chromaticity/intensity), IESNA LM-80/TM-21 (LED lumen maintenance)
Diagram: LED Fixture Thermal and Electrical Design Specification
Case Study: Division 05 — Runway Centreline Light Troubleshooting; Division 26 — Photometric Compliance Troubleshooting
Symptom — A specific illuminated taxiway/runway guidance sign, or a class of signs on a particular circuit, repeatedly returns to the fault log for internal lamp/LED, panel, or ballast/driver failure within a short interval of the last repair.
L-858 illuminated signs (mandatory instruction and information signs), their internal light sources/drivers, panel assemblies, and sign failure/repair history.
After repair or component correction, re-inspect the sign at the next two scheduled PM visits and confirm no recurrence of the same failure mode, with an interim inspection at approximately 90 days if the sign is in a high-risk category.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-SGN-01 (Illuminated Sign Maintenance Procedure)
Standards: FAA AC 150/5345-44 (L-858 signs), ICAO Annex 14 Vol I
Diagram: Sign Internal Wiring and Ventilation Detail Drawing
Case Study: Division 09 — Illuminated Sign Troubleshooting; Division 25 — Field Case Study Troubleshooting
Symptom — The earth-fault protection on a specific CCR or circuit trips or the earth-loop resistance test repeatedly fails at the same or a nearby location, despite apparently isolated repairs, rather than the earthing system showing a stable, compliant baseline across visits.
AGL earthing/grounding system — CCR earth bar, transformer secondary earthing, fixture body earthing, and earth-loop/earth-fault protection settings, plus the earth-fault trip and earth resistance test history.
After remediation, re-test earth-loop resistance immediately and again after the next significant rainfall event or seasonal change, confirming the reading remains within the acceptable threshold before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-EARTH-01 (Earthing System Test and Bonding Procedure)
Standards: IEC 60364-5-54 (earthing arrangements), IEEE 142 (grounding practice), ICAO Annex 14 Vol I
Diagram: As-Built Earthing and Grounding Ring Drawing
Case Study: Division 01 — CCR Troubleshooting; Division 22 — Lightning and Surge Protection Troubleshooting
Symptom — The same base can, pull box, sign housing, or CCR pit repeatedly shows standing water or moisture damage on inspection, shortly after being pumped out, resealed, or otherwise addressed on a previous visit.
Base cans, pull boxes, duct entries, sign housings, and CCR house/pit drainage systems across the affected location(s), plus the moisture-related inspection and repair history.
After remediation — corrected drainage, re-sealed duct entries, or improved site grading — inspect the location after the next significant rainfall event and again at the following PM visit to confirm no recurrence before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-CIVIL-02 (Drainage and Base-Can Remediation Procedure)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30, local civil/drainage design codes
Diagram: Site Drainage and Grading Survey; Base-Can Detail Drawing
Case Study: Division 05 — Runway Centreline Light Troubleshooting (RCL-199 base-can water ingress)
Symptom — Insulation resistance testing repeatedly fails or trends downward at the same cable section, transformer, or component group shortly after the last remedial action, rather than insulation values holding stable after repair as expected.
Primary and secondary cable insulation, transformer winding insulation, and the insulation resistance test/trend history across the affected population.
After remediation (moisture elimination, component replacement, or mechanical stress correction), re-test insulation resistance immediately and trend it at every subsequent PM visit for at least one year to confirm the decline has stopped before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-TEST-03 (Insulation Resistance Test Procedure)
Standards: IEC 60364, IEEE 43 (recommended practice for insulation testing), ICAO Annex 14 Vol I
Diagram: Circuit Insulation Trend Chart by Installation Cohort
Case Study: Division 05 — Runway Centreline Light Troubleshooting; Division 21 — Preventive Maintenance Troubleshooting
Symptom — A specific fixture group or division repeatedly fails periodic photometric survey (intensity, beam spread, or chromaticity out of tolerance) shortly after corrective cleaning, re-lamping, or alignment, rather than holding compliant values between surveys.
AGL fixture optics, lamp/LED modules, and the photometric survey history (intensity, chromaticity, beam pattern) across the affected population.
After the corrected cause is addressed — revised cleaning interval, fixture/lamp replacement, optic replacement, or mounting correction — re-survey at the next scheduled cycle and confirm the decline rate has normalised before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-PHM-01 (Photometric Survey Procedure)
Standards: ICAO Annex 14 Vol I Appendix 2, FAA AC 150/5340-30, IESNA measurement practice
Diagram: Photometric Survey Trend Chart by Fixture Cohort
Case Study: Division 26 — Photometric Compliance Troubleshooting; Division 21 — Preventive Maintenance Troubleshooting
Symptom — A specific fixture, PAPI/APAPI unit, or approach lighting element repeatedly drifts out of vertical or horizontal alignment tolerance between survey cycles, requiring re-alignment more frequently than the wider population at the same site.
Elevated and inset AGL fixtures with adjustable aim, PAPI/APAPI units, and the alignment survey/adjustment history for the affected unit(s).
After remediation — foundation repair, mounting hardware replacement, or procedure correction — re-survey at the next scheduled cycle and confirm the drift has stopped or fallen within normal tolerance before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-PAPI-01 (PAPI/APAPI Alignment Procedure)
Standards: ICAO Annex 14 Vol I (PAPI/APAPI alignment tolerance), FAA AC 150/5345-28
Diagram: PAPI/Fixture Foundation and Aiming Mechanism Detail Drawing
Case Study: Division 10 — PAPI/APAPI Troubleshooting; Division 26 — Photometric Compliance Troubleshooting
Symptom — A specific series or parallel circuit as a whole (not one fixture or cable segment) repeatedly presents with degraded performance — reduced current, unstable output, or partial dark sections — after each repair appears to resolve the immediate finding.
The complete circuit — CCR, series/parallel loop, all fixtures and transformers on it — and the circuit-level fault and repair history distinct from individual component records.
After the design margin is restored (CCR recalibration, circuit re-design/derating, or component upgrade), monitor circuit-level fault frequency for at least two full PM cycles and confirm it has returned to a rate consistent with the wider field before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-CCR-04 (CCR LOTO Procedure), SOP-DESIGN-02 (Circuit Design Change Control)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30, FAA AC 150/5345-10 (CCR)
Diagram: Circuit Design Calculation and As-Built Topology Drawing
Case Study: Division 01 — CCR Troubleshooting; Division 24 — Complete Runway Lighting Failure
Symptom — ALCMS/SCADA communication with a specific CCR, remote monitoring unit, or field device repeatedly drops or times out shortly after being restored, rather than the link remaining stable once re-established.
ALCMS/SCADA communication network — fibre, copper, or wireless links between the control room and field CCR/monitoring nodes — and the communication fault/downtime log.
After the physical, power, or configuration issue is corrected, monitor the communication uptime log for the specific node for at least 30 days including a range of temperature/weather conditions with no recurrence before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-COMMS-01 (ALCMS/SCADA Network Maintenance Procedure)
Standards: ICAO Annex 14 Vol I (monitoring requirements), relevant network/telecom standards (e.g. TIA/EIA-568 for cabling)
Diagram: ALCMS/SCADA Network Topology Diagram
Case Study: Division 20 — ALCMS/SCADA Troubleshooting
Symptom — A recurring pattern where the same fault reappears shortly after a maintenance work order is closed as "resolved," indicating the maintenance action itself — rather than the underlying equipment — is a contributing factor to the repeat pattern.
The maintenance process itself — work order records, PM checklists, technician assignment history, and spares/parts records — cross-referenced against the equipment fault history it is meant to resolve.
After the process gap is corrected (checklist update, training, parts stocking, or closure-verification requirement), monitor the specific fault type's recurrence rate for at least two PM cycles and confirm it has dropped to the expected baseline before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-QA-01 (Work Order Closure and Verification Procedure)
Standards: ISO 9001:2015 Cl. 10.2 (corrective action), ISO 55001 (asset management)
Diagram: Work Order Process Flow Diagram
Case Study: Division 21 — Preventive Maintenance Troubleshooting
Symptom — An investigation traces a fault, near-miss, or nonconformance to an action or omission by a person (technician, operator, or engineer) rather than to a purely equipment, material, or design cause, and the finding needs to be developed into a defensible, non-punitive root cause rather than left as a generic "human error" label.
Not equipment-specific — applies across CCR, cable, fixture, and sign work; relevant records are the specific work order, procedure/SOP in force at the time, and training records for the individual(s) involved.
After the systemic contributing factor is corrected (procedure revision, training, workload adjustment, or design/error-proofing change), monitor for recurrence of the same error type across the team, not just the individual, over the following review period before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-HR-01 (Just Culture and Non-Punitive Investigation Procedure)
Standards: ISO 9001:2015 Cl. 10.2, ICAO Doc 9859 (Safety Management Manual — human factors principles)
Diagram: HFACS or Equivalent Human-Factors Classification Chart
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A fault is traced back to how a component was installed (wrong torque, wrong orientation, wrong depth, incorrect wiring) rather than to the component itself or a maintenance action, and the finding needs to be developed into a defensible installation-stage root cause, distinguishing it from a later maintenance-caused error.
Applies across newly installed or recently reworked fixtures, cable, transformers, CCRs, and signs; relevant records are the installation work package, inspection/test records (ITP), and as-built documentation from the original installation.
After rework to the correct specification and, where a systemic pattern is found, re-inspection of the full affected batch, confirm compliance across the sample and monitor for recurrence of the same defect type on any subsequent installation work before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-QA-02 (Inspection and Test Plan Procedure), SOP-DESIGN-02 (Design Change Control)
Standards: ISO 9001:2015 Cl. 8.5/8.7, ICAO Annex 14 Vol I, applicable FAA AC/IS installation standards for the component type
Diagram: Original Installation Work Package and As-Built Drawing
Case Study: Division 25 — Field Case Study Troubleshooting
Symptom — A recurring or systemic fault across multiple otherwise-correctly installed and maintained units is traced back to the original design — an undersized component, an incorrect calculation, or a specification that does not match actual operating conditions — rather than to installation or maintenance practice.
Applies at the system/design level — circuit design calculations, component specification selection, and design drawings — rather than to any single physical unit; relevant records are the original design calculation package and any design change history.
After the design is corrected and the affected population is identified and remediated (or a phased remediation plan is in place), verify a sample of remediated units against the corrected design and confirm the defect does not recur on any new installation using the corrected design before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-DESIGN-01 (Design Calculation and Review Procedure)
Standards: ICAO Annex 14 Vol I, FAA AC 150/5340-30, applicable IS/IEC design standards for the component
Diagram: Original Design Calculation Package and Corrected Design Drawing
Case Study: Division 24 — Complete Runway Lighting Failure
Symptom — A component fails in a way inconsistent with normal wear, thermal, or electrical stress, and physical/metallurgical or polymer evidence points to the material itself — composition, contamination, or intrinsic defect — rather than to how the component was installed, operated, or maintained.
Applies to the specific material/component in question (cable insulation compound, transformer potting, connector polymer, fixture housing alloy, LED encapsulant) and the batch/supplier record for that material.
After replacement with verified-conforming material and, where a batch defect is confirmed, removal or monitoring of the remaining affected population, track failure incidence in that population over the following review period and confirm it returns to the expected baseline rate before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-QA-03 (Incoming Material Inspection Procedure)
Standards: ISO 9001:2015 Cl. 8.4/8.7, relevant material standards (e.g. IEC/IS cable and polymer standards) for the component
Diagram: Material Specification and Batch Traceability Record
Case Study: Division 05 — Runway Centreline Light Troubleshooting
Symptom — A component fails in a manner traced to how it was built by the manufacturer — an assembly, process control, or quality-escape issue — distinct from a raw material defect, an installation error, or normal operational wear, typically confirmed by teardown showing a consistent defect signature across a specific batch or production date range.
Applies to the specific manufactured component (transformer, CCR module, connector, fixture, LED driver) and its manufacturing/quality record — production batch, factory acceptance test (FAT) data, and quality escape history.
After replacement with a unit confirmed from an unaffected batch or corrected production, and any manufacturer corrective action (process fix, expanded FAT coverage) is confirmed in place, track failure incidence in the remaining installed population for the following review period before closing the RCA.
SOP: SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-QA-03 (Incoming Material Inspection Procedure), SOP-QA-04 (Supplier Quality Management)
Standards: ISO 9001:2015 Cl. 8.4/8.7/10.2, applicable FAA AC/IS product standards for the component
Diagram: Manufacturer Teardown Report and Batch Traceability Record
Case Study: Division 05 — Runway Centreline Light Troubleshooting
Quick answers about Division 23 — Root Cause Analysis / Failure Investigation Troubleshooting in the AGL Troubleshooting Atlas.
Division 23 is the Root Cause Analysis / Failure Investigation Troubleshooting reference. It publishes 20 diagnostic topics, RCA-546 to RCA-565, in a single subsection.
Every topic follows the same diagnostic record: the symptom, equipment/system, possible causes ranked by likelihood (high, medium or low), required tools, safety precautions, diagnostic procedure, test points, root cause verification, corrective action, preventive action and related references (SOPs, standards, diagrams and case studies).
The 20 topics are RCA-546 to RCA-565: Repeated Transformer Failure RCA; Repeated CCR Trip RCA; Repeated Cable Failure RCA; Repeated Connector Failure RCA; Repeated Fixture Failure RCA; Repeated LED Failure RCA; Repeated Sign Failure RCA; Repeated Earth Fault RCA; Repeated Water Ingress RCA; Repeated Insulation Failure RCA; Repeated Photometry Failure RCA; Repeated Alignment Failure RCA; Repeated Circuit Failure RCA; Repeated Communication Failure RCA; Repeated Maintenance Failure RCA; Human Error Root Cause; Installation Error Root Cause; Design Error Root Cause; Material Failure Root Cause; Manufacturing Defect Root Cause.
Each procedure starts with observation before any intervention. For example, RCA-546 (Repeated Transformer Failure RCA) begins: Pull the full failure history for the position/circuit/batch in question spanning at least the last 12–24 months from the CMMS or maintenance log.
Each topic lists its own precautions. For example, RCA-546 (Repeated Transformer Failure RCA) starts with: LOTO the circuit before removing any transformer for forensic inspection.
Related references in the topics include SOP-RCA-01 (Root Cause Analysis and FRACAS Procedure), SOP-RCL-12 (Transformer Test and Replacement Procedure), SOP-CCR-04 (CCR LOTO Procedure), SOP-CCR-07 (Protection Relay Verification), SOP-RCL-02 (Series Circuit Fault Location Procedure), SOP-RCL-03 (Fixture Replacement Procedure), SOP-PHM-01 (Photometric Survey Procedure) and SOP-SGN-01 (Illuminated Sign Maintenance Procedure), and 12 more.
Where a standard applies, it appears in the topic's Related References. Those cited in this division include FAA AC 150/5345-26, IEEE C57.12.91, ISO 9001:2015 Cl. 10.2, ICAO Annex 14 Vol I, FAA AC 150/5345-10, IEC 61439, IEC 60364, FAA AC 150/5340-30, FAA AC 150/5345-46 and ISO 9001:2015 Cl. 8.7, among others.
Use the search box at the top of the page to filter the 20 published topics by code, fault name or keyword; matching topics open automatically. Each diagnostic record can also be downloaded as a Word (.doc) file.
A repaired fault without a root cause is a fault waiting to recur.
Build the technical knowledge to understand structured failure investigation, the 5-whys and fishbone methods applied to AGL systems, and how to turn a single fault into a system-wide reliability improvement.