What is switchover time on a generator changeover?

How long the lights are interrupted when the load moves from the primary supply to the standby generator, and the limit that interruption must stay under.

CHANGEOVER AND SWITCHOVER TIME · HOW LONG THE LIGHTS ARE INTERRUPTED the switch is the fast part — starting the generator and restarting the regulators take the time 15 s CLASS · GENERATOR ROUTE DETECT 1 GENERATOR START AND RUN-UP longest part of the break 2 TRANSFER 3 CCR RESTART 4 MARGIN keep it — do not spend it 5 LIGHTS INTERRUPTED · THIS IS THE SWITCHOVER TIME t = 0 15 s LIMIT mains fails 1 s CLASS · NEEDS A NO-BREAK ARRANGEMENT 1 s LIMIT A GENERATOR CANNOT START IN 1 s — THE LOAD MUST BE CARRIED BY A SOURCE ALREADY RUNNING second independent feed with fast transfer · no-break power system · as the design and the authority require 1 DETECT the loss or poor quality of the supply is sensed, usually with a short deliberate delay 2 GENERATOR START AND RUN-UP cranks, starts and reaches rated voltage and frequency — usually the longest part 3 TRANSFER the changeover switch moves the load to the generator 4 CCR RESTART the regulators re-establish the series-circuit current and the lights come back 5 MARGIN what is left under the limit — absorbs a slow start or an ageing switch TIMED ON TEST WITHIN THE LIMIT, PROVEN A recorded interruption on load shows the whole chain meets its class NEVER TIMED DARK LONGER THAN ALLOWED A slow start or a sticky switch is found only in a real outage SCHEMATIC · NOT TO SCALE · FOLLOW ICAO ANNEX 14 VOL. I, THE AUTHORITY AND THE EQUIPMENT MANUALS
generator start and transfer
margin and no-break source
detection and regulator restart
The Fact Secondary power

Changeover is the act of moving the load from the primary supply to the standby generator, normally through a changeover or transfer switch. Switchover time is the length of the interruption the lights actually see. ICAO Annex 14 defines it for a light as the time for the intensity to fall to 50 percent and recover to 50 percent during a power supply changeover, with the light running at 25 percent intensity or above. It is a measure of what the pilot sees, not of how fast the switch operates.

Annex 14 Volume I gives each facility a maximum switchover time in its secondary power supply table. Most facilities are given 15 seconds, the most critical elements of Category II and III runways are given 1 second, and a 1 second limit also applies to some other facilities where the table notes require it, for example where approaches are over hazardous or precipitous terrain. A generator can serve the 15 second class, but it cannot start in 1 second, so the 1 second class needs a source that is already running. A slow start, a sticky switch or regulators that restart slowly can push the interruption past the limit, and this is often found only in a real outage.

  1. Know the class. Find which facilities are on the circuit and which limit applies to each in the current Annex 14 table and the authority’s requirement.
  2. Budget the chain. Add detection, generator start and run-up, transfer and regulator restart, and compare the total with the limit.
  3. Arrange the source. A generator for the 15 second class; a source that is already running for the 1 second class.
  4. Time it. Simulate loss of the primary supply on load and record the interruption, ideally with a light sensor and a recorder.
  5. Transfer back. Return to the primary supply in a controlled way once it is stable. This is a second interruption, so plan it with air traffic control.
  6. Record & repeat. Log the result against the limit and repeat the test on a regular schedule and after any change.
Changeover The act of moving the load to the standby source
Switchover time How long the lights are interrupted, from 50% intensity down and back up
Typical limits 15 s for most facilities; 1 s for the most critical Cat II/III elements, and where the table notes require it
Longest part Generator start and run-up, then regulator restart
Weak point Slow start, sticky switch, never timed on load
Reference ICAO Annex 14 Vol. I · ICAO Doc 9157 Part 5 · FAA AC 150/5340-30 (standby power guidance) · NFPA 110
Schematic — simplified and not to scale; the segment lengths are illustrative, not measured. The limits shown are typical values; which one applies depends on the facility, the runway category and the authority. Check the secondary power supply table in the current edition of ICAO Annex 14 Vol. I, the equipment manuals and your site’s isolation and permit-to-work procedure.
Entry 32 · Standby power and UPS Entry 34 · Airfield substation single-line diagram

Frequently Asked Questions

Q1What is the difference between changeover and switchover time?

Changeover is the act of moving the load from the primary supply to the standby source, usually by a changeover or transfer switch. Switchover time is the length of the interruption the lights actually see. It includes detecting the failure, starting the generator, the transfer itself and the regulators restarting, so it is much longer than the switch operation alone.

Q2What switchover time does airfield lighting have to meet?

ICAO Annex 14 Volume I sets a maximum switchover time for each facility in its secondary power supply table. Most facilities are given 15 seconds, the most critical elements of Category II and III runways are given 1 second, and a 1 second limit also applies to some other facilities where the table notes require it, for example where approaches are over hazardous or precipitous terrain. Always check the table in the current edition and the authority's requirement for your runway.

Q3How is switchover time defined?

Annex 14 defines it for a light as the time for the intensity in a given direction to fall to 50 percent and recover to 50 percent during a power supply changeover, with the light operating at 25 percent intensity or above. It is a measure of what the pilot sees, not of how fast the switch moves. Check the exact wording in the current edition.

Q4Can a standby generator meet a 1 second requirement?

No. A generator needs several seconds to start and reach rated voltage and frequency, so a 1 second limit needs a source that is already running, such as a second independent utility feed with a fast transfer or a no-break power system. Which arrangement is used depends on the design and the authority.

Q5How is switchover time tested?

By simulating a loss of the primary supply with the system on load, then recording how long the lights are interrupted, ideally with a light sensor and a recorder rather than a stopwatch. Repeat the test at the intensity steps in use, test the transfer back to the primary supply as well, and log the results against the required limit.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.