What is SCADA?

SCADA is the supervisory layer that collects status and alarms from the field controllers, shows them to operators, keeps the history and passes supervisory commands down.

SCADA · COLLECT, SHOW, LOG, COMMANDHMI CLIENTStower, maintenanceview and commandPLCs · CCRscontrollers, I/Ostatus contacts backSCADA SERVERACQUIREpoll the PLCsstatus, readingsALARMSraise, display,acknowledgeHISTORIANevents, trends,reports1 POLL2 UPDATE3 LOG4 COMMANDREPEATS CONTINUOUSLYCMDSTATUSCMDSTATUSSTANDBY SERVER · OFTEN REDUNDANTAIRFIELD LIGHTSSUPERVISORY LAYERPLCs still run thereal-time control logicDATA AND HISTORYalarms, events and trendskept with time stampsLINK OR SERVER LOSSscreen may be out of date;check CCR and field statusSCHEMATIC · NOT TO SCALE · ARCHITECTURE, POLLING AND REDUNDANCY ARE SET BY THE PROJECT DESIGN
command / history
status back
alarms / link loss
The Fact Supervisory layer

SCADA — supervisory control and data acquisition — is the layer that watches the whole airfield lighting system at once. A SCADA server polls the PLCs and CCRs for status and readings, raises and lists alarms, and keeps a historian of events, operator actions and trends. The HMI clients at the tower and maintenance station are its screens, and a supervisory command from an operator is passed down through the server to the field controllers.

SCADA supervises; the PLCs still run the real-time logic and drive the equipment, so a SCADA failure does not by itself switch the lights off. The ALCMS is commonly built on SCADA software, and servers are often redundant with a standby. If the server or network fails, the screen can be out of date and the real status is checked at the CCR or in the field. Because it is networked, access control and security are part of the design.

PurposeSupervise and record
CollectsStatus, alarms, readings
ShowsOn the HMI clients
StoresEvents, trends, history
CommandsSupervisory, via PLCs
ServersOften redundant
NetworkLinks to the controllers
ReferenceFAA AC 150/5345-56 (L-890 ALCMS); ICAO Doc 9157 Part 5 (electrical systems); IEC 62443 (industrial control system security); project design documents
Awareness schematic only, not an operating procedure. Architecture, polling, alarm handling, redundancy, cyber security and failure behaviour are set by the manufacturer, the project design and the airport’s own procedures. Only trained and authorised personnel configure or change a SCADA system, under change control.
Entry 8 · PLC Entry 10 · Communication network

Frequently Asked Questions

Q1What does SCADA stand for and what does it do?

SCADA means supervisory control and data acquisition. In an airfield lighting control system it is the supervisory layer that collects status, alarms and readings from the PLCs and CCRs, shows them to operators on the HMI, keeps a record of events and trends, and passes supervisory commands down to the field controllers.

Q2How is SCADA different from a PLC?

A PLC runs the real-time control logic close to the equipment, repeating its scan cycle continuously. SCADA sits above it: it gathers data from many PLCs, presents the whole airfield on one system, stores the history and sends supervisory commands, but it does not replace the controllers that drive the equipment.

Q3How do SCADA, ALCMS and the HMI relate?

The ALCMS is commonly built on SCADA software. The SCADA server holds the data and logic for supervision, the HMI is the screen operators use to see it and send commands, and the PLCs and CCRs do the work in the field. The exact split depends on the manufacturer and the project.

Q4What does the SCADA record, and why does it matter?

It normally logs alarms, events, operator commands and readings with time stamps. That history helps find the cause of a fault, shows trends such as a circuit slowly degrading, and supports review after an incident or a maintenance visit.

Q5What happens if the SCADA server or network fails?

That depends on the design. Servers are often redundant, and the PLCs and local control at the CCR remain available, but the screen can become out of date. Check the real status at the CCR or in the field, tell ATC as the procedure requires and follow the failure flow.

Q6Why does SCADA security matter?

Because it is networked, access control, user levels and network protection are part of the design, and only authorised personnel should change settings or commands. Software changes follow the airport's change-control procedure, with the lights verified afterwards.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.