Division 10 of 22 · SOP-204 → SOP-218 Series

Approach Lighting System SOPs

Controlled procedures for the planning interface, installation, structures, fixtures, cabling, transformers, connectors, inspection, testing and photometric verification of approach lighting systems — applicable to ALS, SALS, SSALR, MALSR, MALSF, ALSF-type systems, PALS and other approved approach lighting configurations.

15 / 15
Topics Published
SOP-204 → SOP-218
SOP ID Range
Rev 0
Initial Issue

Important — The exact approach lighting configuration, length, bar geometry, fixture spacing, elevations, aiming, colors, intensity, structure dimensions, frangibility, obstruction requirements and photometric criteria shall always be taken from the approved aerodrome lighting drawings, applicable ICAO/FAA/DGCA requirements, approved obstacle/approach-lighting study, manufacturer instructions and project specification.

Division 10 · Approach Lighting SOPs

15 of 15 topics published
SOP-204 Approach Lighting Installation
Purpose

To establish a controlled procedure for installing an approach lighting system in accordance with the approved design and aerodrome requirements.

Pre-Installation Verification

Verify:

  • Approved approach lighting layout.
  • Runway centreline reference.
  • Threshold reference.
  • Approach lighting system type.
  • Fixture schedule.
  • Light-bar locations.
  • Crossbar locations.
  • Pole/structure locations.
  • Fixture elevations.
  • Cable routes.
  • Transformer locations.
  • Connector arrangement.
  • Obstacle/frangibility requirements.
  • Access and airside safety controls.
Procedure
  1. Review approved approach lighting drawings.
  2. Establish runway centreline and threshold reference.
  3. Verify all structure locations.
  4. Verify fixture positions and elevations.
  5. Inspect foundations/supports.
  6. Install poles/structures.
  7. Install fixtures.
  8. Install primary/secondary cabling as applicable.
  9. Install transformers.
  10. Install connectors.
  11. Verify fixture orientation.
  12. Verify elevation.
  13. Verify alignment.
  14. Inspect mechanical installation.
  15. Perform electrical tests.
  16. Conduct functional testing.
  17. Conduct photometric verification where required.
  18. Complete documentation.
Acceptance

The system shall match the approved:

Geometry + Elevation + Alignment + Optical Configuration + Electrical Configuration + Control Configuration.

SOP-205 Approach Light Alignment

Critical Principle — Approach lighting alignment must be assessed as a complete visual guidance pattern, not merely as individual fixture alignment.

Purpose

To ensure approach light fixtures are correctly aligned with the approved approach lighting geometry.

Reference

Alignment shall be established from the approved:

  • Runway centreline.
  • Threshold reference.
  • Approach lighting centreline.
  • Crossbar geometry.
  • Fixture aiming requirements.
Procedure
  1. Establish runway centreline reference.
  2. Establish threshold reference.
  3. Verify each approach-light station.
  4. Check lateral position.
  5. Check longitudinal position.
  6. Check fixture orientation.
  7. Check optical axis.
  8. Check adjacent fixtures.
  9. Correct deviations.
  10. Record measurements.
SOP-206 Approach Light Height Verification
Purpose

To verify that approach light fixtures and structures are installed at the approved elevations.

Procedure
  1. Obtain approved elevation data.
  2. Establish survey reference.
  3. Verify ground level.
  4. Measure pole/fixture elevation.
  5. Compare with approved design.
  6. Verify crossbar elevation.
  7. Verify consistency between stations.
  8. Identify settlement or foundation movement.
  9. Correct unacceptable deviations.
  10. Record measurements.
Check

Verify:

  • Fixture height.
  • Crossbar height.
  • Pole height.
  • Ground clearance.
  • Structural settlement.
  • Fixture-to-centreline relationship.
SOP-207 Approach Light Orientation

Important — Do not assume all approach light fixtures use identical aiming requirements. Follow the fixture manufacturer's approved aiming procedure.

Purpose

To ensure fixtures are oriented correctly toward the intended approach direction.

Procedure
  1. Identify approach direction.
  2. Verify fixture optical orientation.
  3. Confirm horizontal aiming.
  4. Confirm vertical aiming where applicable.
  5. Check fixture housing orientation.
  6. Check optical assembly.
  7. Compare neighboring fixtures.
  8. Correct deviations.
  9. Record orientation verification.
SOP-208 Approach Light Pole Installation
Purpose

To establish a safe and controlled procedure for installing approach light poles/support structures.

Pre-Installation

Verify:

  • Approved pole location.
  • Pole type.
  • Pole height.
  • Foundation.
  • Structural details.
  • Frangibility requirement.
  • Wind/environmental design.
  • Cable route.
  • Access arrangements.
Procedure
  1. Inspect delivered pole.
  2. Verify identification.
  3. Inspect foundation.
  4. Verify anchor arrangement where applicable.
  5. Position pole.
  6. Install according to approved structural design.
  7. Verify verticality.
  8. Install fixtures/support arms.
  9. Install cable.
  10. Verify mechanical security.
  11. Verify frangible arrangement where required.
  12. Complete structural inspection.
SOP-209 Approach Light Structure Inspection

Escalation — Any suspected structural instability, significant deformation or impact damage shall be treated as a safety-critical defect and assessed before continued service.

Purpose

To identify structural conditions that may affect the safety, alignment or reliability of the approach lighting system.

Inspection

Check:

  • Pole verticality.
  • Foundation condition.
  • Anchor hardware.
  • Structural members.
  • Crossbars.
  • Support arms.
  • Corrosion.
  • Cracks.
  • Deformation.
  • Loose fasteners.
  • Cable supports.
  • Frangible components.
  • Evidence of impact.
  • Settlement.
Procedure
  1. Conduct visual inspection.
  2. Check structural condition.
  3. Verify fixture support.
  4. Verify alignment.
  5. Inspect fasteners.
  6. Check foundation.
  7. Record defects.
  8. Initiate corrective action where required.
SOP-210 Approach Light Fixture Installation
Purpose

To ensure approach light fixtures are correctly installed on their approved structures/supports.

Procedure
  1. Verify fixture model.
  2. Inspect fixture.
  3. Confirm mounting location.
  4. Install mounting hardware.
  5. Position fixture.
  6. Align optical system.
  7. Apply specified torque.
  8. Connect secondary cable.
  9. Verify connector.
  10. Check sealing.
  11. Verify fixture height.
  12. Verify orientation.
  13. Conduct inspection.
SOP-211 Approach Light Cable Installation

Critical Check — Cable installation shall not compromise fixture alignment, frangible structure, drainage, mechanical safety or electrical integrity.

Purpose

To ensure approach-lighting cables are installed, protected and identified according to the approved design.

Procedure
  1. Review cable schedule.
  2. Confirm cable route.
  3. Verify cable type.
  4. Inspect cable before installation.
  5. Install cable using approved method.
  6. Avoid excessive bending.
  7. Maintain required bend radius.
  8. Protect cable against mechanical damage.
  9. Secure cable to structures where required.
  10. Install identification.
  11. Complete cable entry/sealing.
  12. Perform continuity/insulation testing where applicable.
  13. Record cable route.
SOP-212 Approach Light Transformer Installation

Important — Transformer rating shall be matched to the approved fixture/load and manufacturer requirements.

Purpose

To establish controlled installation requirements for isolating transformers associated with approach lighting fixtures.

Procedure
  1. Verify transformer model and rating.
  2. Inspect transformer.
  3. Confirm location.
  4. Verify transformer mounting/protection.
  5. Connect primary.
  6. Connect secondary.
  7. Inspect connectors.
  8. Verify cable sealing.
  9. Verify identification.
  10. Conduct applicable electrical tests.
  11. Verify fixture connection.
  12. Document installation.
SOP-213 Approach Light Connector Installation

Critical Rule — The connector shall be protected against moisture ingress and mechanical damage in accordance with the approved installation method.

Purpose

To ensure approach-lighting connectors are correctly installed, sealed and identified.

Procedure
  1. Identify cable and fixture.
  2. Verify connector type.
  3. Inspect connector.
  4. Verify contact condition.
  5. Prepare cable according to approved procedure.
  6. Complete termination/assembly.
  7. Verify contact engagement.
  8. Complete sealing.
  9. Apply identification.
  10. Perform continuity check.
  11. Inspect mechanical security.
  12. Record completion.
SOP-214 Approach Light Replacement
Purpose

To establish a safe method for replacing defective approach lighting equipment.

Procedure
  1. Obtain work authorization.
  2. Coordinate with Airport Operations/ATC as required.
  3. Identify defective fixture.
  4. Isolate circuit.
  5. Apply LOTO where applicable.
  6. Verify safe electrical condition.
  7. Inspect surrounding structure.
  8. Disconnect connector.
  9. Remove defective fixture.
  10. Inspect mounting arrangement.
  11. Install approved replacement.
  12. Connect secondary cable.
  13. Verify orientation.
  14. Verify height/alignment.
  15. Apply specified torque.
  16. Conduct electrical testing.
  17. Conduct functional testing.
  18. Perform photometric verification where required.
  19. Complete work-clearance process.
SOP-215 Approach Light Cleaning
Purpose

To maintain optical performance through controlled cleaning of approach-lighting fixtures.

Contamination

Inspect for:

  • Dust.
  • Dirt.
  • Mud.
  • Insects.
  • Salt.
  • Oil.
  • Atmospheric deposits.
  • Bird contamination.
  • Moisture.
Procedure
  1. Obtain maintenance authorization.
  2. Isolate equipment where required.
  3. Inspect fixture.
  4. Clean lens/prism using approved materials.
  5. Avoid abrasive materials.
  6. Remove residue.
  7. Inspect optical surface.
  8. Check for damage.
  9. Verify sealing.
  10. Restore equipment.
  11. Conduct functional verification where required.
SOP-216 Approach Light Inspection
Purpose

To provide a systematic inspection of the complete approach lighting installation.

Inspection Categories

A. Structural

  • Poles.
  • Crossbars.
  • Foundations.
  • Supports.
  • Fasteners.
  • Frangible components.

B. Mechanical

  • Fixture mounting.
  • Alignment.
  • Height.
  • Housing.
  • Couplings.
  • Cable supports.

C. Optical

  • Lens.
  • Prism.
  • LED module/lamp.
  • Color.
  • Contamination.
  • Optical orientation.

D. Electrical

  • Primary circuit.
  • Transformer.
  • Secondary cable.
  • Connector.
  • Insulation.
  • Continuity.
  • Circuit identification.

E. Environmental

  • Water ingress.
  • Corrosion.
  • Weather damage.
  • Vegetation.
  • Wildlife/bird contamination.
  • Debris.
Procedure
  1. Conduct system-level inspection.
  2. Inspect each station.
  3. Record defects.
  4. Classify defects by severity.
  5. Correct or initiate corrective action.
  6. Conduct reinspection.
  7. Update maintenance records.
SOP-217 Approach Light Functional Testing

System-Level Principle — Do not accept the system solely because every fixture illuminates. Verify that the complete approach lighting pattern functions correctly.

Purpose

To verify correct operation of the approach lighting system following installation, repair or maintenance.

Pre-Test

Confirm:

  • Work area clear.
  • Personnel clear.
  • Tools removed.
  • FOD inspection complete.
  • Electrical connections complete.
  • Circuit correctly configured.
  • Control system available.
  • ATC/Operations coordination complete where required.
Procedure
  1. Obtain permission to energize.
  2. Energize the approach lighting system.
  3. Operate through applicable intensity levels.
  4. Inspect the complete lighting pattern.
  5. Verify correct ON/OFF operation, color, intensity, sequence and fixture response.
  6. Confirm no flickering, no intermittent operation and no abnormal illumination.
  7. Check control-system response where applicable.
  8. Record defects.
  9. Restore required operating configuration.
  10. Complete documentation.
SOP-218 Approach Light Photometric Verification

Critical Rule — Photometric acceptance values must come from the applicable standard, approved project specification or equipment/system requirement. Do not insert generic acceptance limits into the SOP.

Purpose

To verify the photometric performance of the approach lighting system against the applicable approved requirements.

Scope

Photometric verification may include, as applicable:

  • Light intensity.
  • Distribution.
  • Uniformity.
  • Color.
  • Horizontal aiming.
  • Vertical aiming.
  • Intensity steps.
  • Individual fixture output.
  • System-level pattern.
Pre-Test Requirements

Verify:

  • Approved photometric criteria available.
  • Correct runway/approach lighting configuration.
  • Test equipment suitable for the application.
  • Test equipment calibration status valid.
  • Test reference coordinates established.
  • Weather/visibility conditions recorded where relevant.
  • Lighting intensity setting identified.
  • Test area controlled.
Procedure
  1. Review approved photometric test procedure.
  2. Establish test reference.
  3. Verify system configuration.
  4. Set required intensity level.
  5. Measure required points/angles.
  6. Record individual fixture results.
  7. Record system-level results.
  8. Compare measurements against applicable criteria.
  9. Identify deficient fixtures.
  10. Correct alignment/fixture defects.
  11. Repeat measurements where required.
  12. Prepare final photometric report.
Report Should Include
  • Airport/project.
  • Runway designation.
  • Approach lighting system type.
  • Date/time.
  • Weather conditions.
  • Test equipment.
  • Calibration details.
  • Test methodology.
  • Fixture identification.
  • Test locations.
  • Measured values.
  • Applicable acceptance criteria.
  • Pass/fail status.
  • Deficiencies.
  • Corrective actions.
  • Retest results.
  • Engineer/tester's signature or authorization.
No SOPs match your search. Try a different term.

Division-Wide Requirements

The master workflow, quality hold points, common failure modes and inspection checklist that apply across all 15 Division 10 procedures.

A. Master Workflow

The following sequence should be applied end-to-end for every approach lighting installation:

APPROVED DESIGN CENTRELINE/THRESHOLD REF STRUCTURE LOCATION FOUNDATION INSPECTION POLE/STRUCTURE INSTALL ALIGNMENT/HEIGHT CHECK FIXTURE INSTALL FIXTURE ALIGNMENT/ORIENTATION CABLE INSTALL TRANSFORMER INSTALL CONNECTOR INSTALL ELECTRICAL TESTING MECHANICAL INSPECTION OPTICAL INSPECTION FOD/AREA INSPECTION CONTROLLED ENERGIZATION FUNCTIONAL TESTING PHOTOMETRIC VERIFICATION DEFECT RECTIFICATION RETEST FINAL ACCEPTANCE

B. Quality Hold Points

  • HP-01 — Survey ReferenceRunway centreline and threshold reference verified.
  • HP-02 — Structure LocationPole/crossbar locations verified against approved drawings.
  • HP-03 — FoundationFoundation condition and structural interface accepted.
  • HP-04 — Pole/StructureVerticality, height, mechanical condition and frangibility verified.
  • HP-05 — FixtureCorrect fixture and optical configuration verified.
  • HP-06 — AlignmentHorizontal/vertical orientation and system geometry verified.
  • HP-07 — CablingCable routing, protection, identification and connections verified.
  • HP-08 — TransformerTransformer rating, installation and connections verified.
  • HP-09 — ConnectorConnector assembly and sealing verified.
  • HP-10 — Functional TestComplete approach lighting pattern verified.
  • HP-11 — PhotometryRequired photometric testing completed.
  • HP-12 — Final ReleaseAll defects closed and documentation approved.

C. Common Failure Modes

  • Incorrect Centreline PositionCan distort the intended approach guidance pattern.
  • Incorrect Fixture ElevationCan change the geometry and visual presentation of the approach system.
  • Pole SettlementCan gradually alter fixture elevation and alignment.
  • Fixture MisalignmentA fixture can illuminate normally while directing light incorrectly.
  • Structural DamageImpact, corrosion or loose supports can compromise system alignment and safety.
  • Connector/Transformer FailureCan cause individual fixture failure or intermittent operation.
  • Optical ContaminationDirt or moisture can reduce useful optical output.
  • Incorrect Fixture ConfigurationAn incorrect optical/color configuration can result in a non-compliant system even when the fixture operates.
  • Cable DamageImproper routing or mechanical damage can cause intermittent or permanent circuit failure.
  • Photometric DegradationA visually illuminated system may still fail objective photometric requirements.

D. Master Inspection Checklist

The inspection/commissioning team should confirm:

  • Approved approach lighting drawing available
  • Correct approach system type
  • Runway centreline verified
  • Threshold reference verified
  • Structure locations verified
  • Foundation condition verified
  • Pole condition verified
  • Pole verticality verified
  • Pole height verified
  • Crossbar position verified
  • Frangibility verified
  • Fixture type verified
  • Fixture condition verified
  • Fixture location verified
  • Fixture height verified
  • Fixture alignment verified
  • Fixture orientation verified
  • Optical surface clean
  • Prism/lens inspected
  • Transformer verified
  • Primary connection verified
  • Secondary connection verified
  • Connector condition verified
  • Cable route inspected
  • Cable identification complete
  • Cable protection verified
  • Sealing verified
  • Electrical testing completed
  • Mechanical inspection completed
  • Optical inspection completed
  • FOD inspection completed
  • Functional test completed
  • Intensity operation verified
  • Control response verified where applicable
  • Photometric verification completed where required
  • Defects closed
  • Retest completed
  • Final report prepared
  • System released

“Approach lighting is a precision visual guidance system. Successful installation is not simply the installation of poles and lights; the complete system must maintain the approved geometry, elevation, alignment, optical performance, structural integrity, electrical reliability and photometric performance from the approach end through the runway threshold.”

Division 10 — Approach Lighting Golden Rule

Division 10 — SOP Approval Principle

Each project should adapt these SOPs to its own approved aerodrome lighting drawings, applicable ICAO/FAA/DGCA requirements, approved obstacle/approach-lighting study, fixture and transformer manufacturer's instructions, and applicable photometric acceptance criteria.

Approved project drawings, the applicable regulatory requirements and manufacturer's instructions shall take precedence wherever they impose more restrictive requirements.

Reference Basis

Technical references behind the procedures in this division:

  • ICAO Annex 14, Vol. I — Aerodrome Design and Operations, Chapter 5 (approach lighting systems) and Appendices 1 and 2 — simple and precision approach lighting, sequenced flashing lights, colours and characteristics.
  • ICAO Doc 9157, Aerodrome Design Manual, Part 4 — approach lighting design and photometric guidance.
  • FAA AC 150/5340-30 — approach lighting system layouts and installation details.
  • FAA AC 150/5345-45 and AC 150/5345-46 — low-impact resistant structures and fixture specifications.
  • FAA AC 150/5345-51 — discharge-type flasher equipment for sequenced flashing.
  • ICAO Annex 14, Vol. I — Aerodrome Design and Operations, Chapter 8 — secondary power and switch-over requirements for approach lights.
  • FAA AC 150/5340-26 and UK CAA CAP 637 — maintenance and supplementary practice.

References are given at document or chapter level for technical orientation. Confirm the current edition, amendments and national adoption (for example DGCA CAR Section 4, FAA Advisory Circulars or EASA material) for each project. Approved project specifications, manufacturer instructions and the airport's own procedures take precedence, as stated in the precedence note above.

Quick Reference

A short answer on approach lighting replacement, taken from SOP-214 in Division 10. Confirm all criteria against the approved design and the current standard.

Approach lighting replacement

Approach lighting replacement follows SOP-214. Obtain work authorization and coordinate with Airport Operations/ATC as required. Identify the defective fixture, isolate the circuit, apply LOTO where applicable and verify a safe electrical condition. Inspect the surrounding structure, disconnect the connector, remove the defective fixture and inspect the mounting arrangement. Install the approved replacement, connect the secondary cable, then verify orientation, height and alignment and apply the specified torque. Finish with electrical testing, functional testing, photometric verification where required and the work-clearance process.

Frequently Asked Questions

Quick answers about Approach Lighting SOPs in the AGL SOP Library.

Q1What is Division 10 — Approach Lighting SOPs?

Division 10 is a set of 15 procedures (SOP-204 to SOP-218, Rev 0) for approach lighting systems. It covers the planning interface, installation, structures, fixtures, cabling, transformers, connectors, inspection, testing and photometric verification for ALS, SALS, SSALR, MALSR, MALSF, ALSF-type systems, PALS and other approved configurations.

Q2Where do approach lighting geometry and photometric criteria come from?

From the approved aerodrome lighting drawings, applicable ICAO, FAA and DGCA requirements, the approved obstacle/approach-lighting study, manufacturer instructions and the project specification. This includes configuration, length, bar geometry, spacing, elevations, aiming, colors, intensity, structure dimensions and frangibility.

Q3Is an approach lighting system accepted when every fixture lights up?

No. The system-level principle in SOP-217 says the complete approach lighting pattern must be verified as functioning correctly, including operation through the applicable intensity levels, not just individual fixtures illuminating.

Q4Can generic photometric limits be used?

No. Photometric acceptance values must come from the applicable standard, approved project specification or equipment/system requirement (SOP-218). Verification may cover intensity, distribution, uniformity, color, horizontal and vertical aiming, intensity steps, individual fixture output and the system-level pattern.

Q5What is the approach lighting installation workflow?

Approved design, centreline and threshold reference, structure location, foundation inspection, pole or structure installation, alignment and height check, fixture installation and alignment, cable, transformer and connector installation. Then electrical, mechanical and optical inspection, FOD/area inspection, controlled energization, functional testing, photometric verification, defect rectification, retest and final acceptance.

Q6What must be verified before installing approach light poles?

The approved pole location, type and height, foundation, structural details, frangibility requirement, wind and environmental design, cable route and access arrangements (SOP-208). After installation, verticality, mechanical security and the frangible arrangement where required are checked.

Q7How is approach light height verified?

SOP-206 uses approved elevation data and a survey reference to measure pole, fixture and crossbar elevation and compare it with the approved design. It checks consistency between stations, ground clearance, structural settlement and the fixture-to-centreline relationship.

Q8How is approach lighting replacement carried out?

Approach lighting replacement (SOP-214) covers work authorization, isolation and LOTO, structure and mounting inspection, installation of the approved replacement and secondary cable connection, then orientation, height, alignment and torque checks, electrical and functional testing, photometric verification where required, and work clearance.

Precision AGL Academy

Turn SOP Knowledge Into AGL Engineering Competence.

Knowing the maintenance procedure is essential. Understanding how approach lighting sequencing, circuits and structures work together takes deeper technical knowledge.

Build Practical AGL Expertise

Learn through structured training covering:

AGL Fundamentals Airside Safety Electrical Systems Installation Testing Commissioning Photometry Troubleshooting Maintenance

Develop the technical foundation to work with AGL systems systematically, safely and confidently.

Learn the system. Follow the procedure. Apply the engineering.

Talk to Precision AGL Academy

Follow the Academy