Testing, Maintenance & Troubleshooting Comparison

SAT VS COMMISSIONING

Site Acceptance Test (SAT) verifies that the installed equipment/system meets the agreed acceptance criteria at site. Commissioning verifies that the complete installed system has been correctly installed, adjusted, energized, integrated, and made ready for safe operation. In many AGL contracts the two activities overlap or are combined — always follow the project's approved test procedures.

At a Glance

Feature SAT Commissioning Test
Full formSite Acceptance TestCommissioning Test
Main purposeFormal site acceptancePrepare and prove system for operation
TimingAfter installationDuring/after installation, before operation
Main focusContractual acceptance criteriaInstallation, configuration, adjustment, operation
Equipment scopeInstalled equipment/systemComplete installed system
Site interfacesTestedFully integrated
Functional testingYesYes
Calibration/adjustmentAs requiredImportant
Client witnessCommonMay be required
Final handoverOften linked to acceptanceSupports readiness for operation
Acceptance
SAT Core Question
Readiness
Commissioning Core Question

SAT

SAT is the formal test performed at the project site, run against a predefined acceptance procedure.

INSTALLATION
     │
     ▼
SITE PRE-CHECKS
     │
     ▼
    SAT
     │
     ▼
   PASS?
  ↙     ↘
NO       YES
 │         │
 ▼         ▼
RECTIFY   ACCEPTANCE

The SAT procedure normally defines exactly what must be demonstrated for formal acceptance.

Commissioning Test

Commissioning is broader than a single acceptance test — it is the technical process of getting the system into a correctly operating condition.

INSTALL → INSPECT → TEST → ENERGIZE
   → CONFIGURE → ADJUST → INTEGRATE
   → FUNCTIONAL TEST → READY FOR OPERATION

The objective is to make the system operate correctly, not simply to demonstrate compliance.

Meet Acceptance vs Prove Readiness

SAT
APPROVED PROCEDURE
       │
       ▼
  DEMONSTRATE
       │
       ▼
 FORMAL ACCEPTANCE
COMMISSIONING
INSTALLED SYSTEM
       │
       ▼
CHECK / ADJUST / INTEGRATE
       │
       ▼
 READY FOR OPERATION

Easy memory: SAT asks "does it meet the requirements?" Commissioning asks "does it work correctly?"

What Each Activity Covers

SAT Scope

For an AGL system, this could include:

  • CCR operation
  • Current-step operation
  • AGL lighting operation
  • Control functions
  • Remote control
  • Monitoring
  • Alarm functions
  • Communication, interlocking and protection functions

Commissioning Scope

Commissioning may include:

  • Installation verification & cable testing
  • Equipment checks & energization
  • Parameter configuration & protection setting verification
  • Functional testing & control-system integration
  • Monitoring & alarm testing
  • Operational checks
  • Rectification and retesting

New CCR Connected to a Runway Circuit

Consider a new AGL CCR connected to a runway circuit. Commissioning progressively verifies the chain, then SAT formally demonstrates the operating result.

Commissioning: Progressive Verification

CCR
 ├─ Installation ✓
 ├─ Power supply ✓
 ├─ Earthing ✓
 ├─ Control wiring ✓
 ├─ Settings ✓
 └─ Protection ✓
   │
   ▼
SERIES CIRCUIT
 ├─ Continuity ✓
 ├─ Insulation ✓
 └─ Circuit checks ✓
   │
   ▼
ISOLATION TRANSFORMERS
   │
   ▼
RUNWAY LIGHTS
   │
   ▼
CONTROL + MONITORING

SAT: Formal Demonstration

CCR STEP 1       ✓
CCR STEP 2       ✓
CCR STEP 3       ✓
CCR STEP 4       ✓
REMOTE ON/OFF    ✓
ALARM            ✓
MONITORING       ✓
LIGHT OPERATION  ✓

Results are recorded against the approved SAT procedure.

Where Each Stage Sits

A typical sequence places commissioning before a final SAT — but this is not universal.

FAT → DELIVERY → INSTALLATION → PRE-COMMISSIONING
   → COMMISSIONING → SAT → FINAL ACCEPTANCE

Some project specifications combine the two into a single site testing stage instead:

INSTALLATION
      │
      ▼
COMMISSIONING + SAT
      │
      ▼
  ACCEPTANCE

Always follow the project's approved ITP, commissioning procedure and SAT procedure — the contract specification controls the actual sequence, not general convention.

Pre-Commissioning vs Commissioning vs SAT

Stage Main Question
Pre-commissioningIs everything installed and ready to energize?
CommissioningDoes the system operate correctly after energization/configuration?
SATDoes the installed system satisfy the formal acceptance requirements?
PRE-COMMISSIONING → "Cables and equipment are installed correctly."
COMMISSIONING     → "System operates correctly."
SAT               → "System meets the contractual acceptance criteria."

Iterative Adjustment vs Predefined Procedure

Commissioning

Can be detailed and iterative — the purpose is to make the system work correctly.

TEST → ADJUST → RETEST
   → CONFIGURE → RETEST

SAT

Normally follows a predefined acceptance procedure — the objective is to formally demonstrate compliance.

TEST ITEM → ACCEPTANCE CRITERION
   → RESULT → PASS / FAIL

How a Failed Test Is Treated

SAT FAILURE
SAT
 │
 ▼
FAIL
 │
 ▼
NCR / PUNCH ITEM
 │
 ▼
RECTIFICATION
 │
 ▼
RETEST → ACCEPTANCE
COMMISSIONING FAILURE
TEST
 │
 ▼
FAIL
 │
 ▼
ADJUST / REPAIR
 │
 ▼
RETEST → PASS

A commissioning failure is expected as part of getting the system operational. A failed SAT item, by contrast, can affect formal project acceptance.

Activity-by-Activity Breakdown

AGL Activity Commissioning SAT
Verify installationYesMay be verified
Cable testingYesAs specified
CCR energizationYesYes
CCR configurationYesVerify
Current-step operationYesYes
Isolation transformer checksYesAs specified
Lighting operationYesYes
Remote controlYesYes
MonitoringYesYes
Alarm simulationYesYes
System integrationYesYes
Adjustment/optimizationYesUsually limited
Formal contractual acceptanceNot necessarilyYes

Myths vs Facts

Myth: SAT and commissioning are always two completely separate stages
Fact

SAT and commissioning are not universally defined as fully separate activities. Many project specifications combine them, or run SAT as an activity that includes commissioning tests — the contract specification and approved test procedures control the actual scope.

Myth: Commissioning is just a rehearsal for SAT
Fact

Commissioning is the technical process of installing, energizing, configuring, adjusting and integrating the system so it actually works. SAT then formally demonstrates that the working system meets the agreed acceptance criteria — the two have different objectives, not just different levels of formality.

Myth: A commissioning failure and a SAT failure are handled the same way
Fact

Commissioning failures are expected and are resolved through adjustment and retest as part of getting the system operational. A failed SAT item is typically logged as an NCR or punch item and can affect formal project acceptance.

Myth: SAT tests different things than commissioning
Fact

The two activities often test many of the same functions — CCR steps, lighting operation, remote control, monitoring and alarms. What differs is the purpose: commissioning proves the system works, SAT formally records that it meets the acceptance criteria.

How Projects Structure the Two Activities

OPTION A                OPTION B                  OPTION C

COMMISSIONING           COMMISSIONING             SAT
      │                       +                 includes
      ▼                     SAT                COMMISSIONING TESTS
     SAT                     │
                              ▼
                         ACCEPTANCE

Therefore, don't define SAT and commissioning solely by terminology. The contract specification and approved test procedures control the actual scope on a given project.

SAT vs Commissioning Test

Engineering Verdict

Commissioning is the technical process of checking, energizing, configuring, adjusting, integrating and proving the installed system is ready for operation.

SAT is the formal site acceptance test used to demonstrate that the installed equipment/system meets the project-specific acceptance requirements. There is project-specific overlap between the two, and in many AGL contracts commissioning activities are performed within or alongside SAT.

SATPredefined procedure → demonstrate → formal acceptance.
CommissioningInstall → energize → configure → adjust → ready for operation.

A typical AGL sequence runs FAT → Installation → Pre-commissioning → Commissioning → SAT → Handover. But if the project specification combines commissioning and SAT, they may be performed as one integrated site testing stage — always follow the governing procedure, not a general rule of thumb.

Engineering & Expert Notes

Do Not Merge the Two Records
Records

Keep acceptance evidence and commissioning data separate and clear.

Agree Acceptance Criteria Before Starting
Preparation

Settle the test list and values in advance.

Define Retest Rules
Retests

Agree what to repeat after rectification.

Hand Over a Complete Baseline
Handover

Provide settings, results and photographs.

Frequently Asked Questions

What is the fundamental difference between SAT and commissioning?

SAT formally verifies that the installed equipment/system meets the agreed acceptance criteria. Commissioning verifies that the complete system has been correctly installed, adjusted, energized, integrated and made ready for safe operation.

Does commissioning always happen before SAT?

A typical sequence places commissioning before SAT, but this is not universal. Some project specifications combine commissioning and SAT into a single integrated stage, or run SAT as an activity that includes commissioning tests.

Is a commissioning failure the same as a SAT failure?

No. A commissioning failure is expected as part of getting the system operational and is resolved through adjustment and retest. A failed SAT item is typically raised as an NCR or punch item and can affect formal project acceptance.

What does pre-commissioning check that commissioning does not?

Pre-commissioning asks whether everything is installed and ready to energize. Commissioning then asks whether the system operates correctly once it is energized and configured.

Who typically witnesses SAT versus commissioning?

Client witness is common during SAT since it is the formal acceptance step. Commissioning may also require client presence, but its main purpose is technical readiness rather than formal sign-off.

Can SAT and commissioning test the same AGL functions?

Yes. Functions such as CCR step operation, lighting operation, remote control, monitoring and alarms are commonly checked in both — the difference lies in the purpose and formality of the test, not necessarily the function tested.

Governing Documents

For an actual project, always verify the current edition of the applicable documents and the project's own ITP, commissioning procedure and SAT procedure.

Project ITP

The Inspection and Test Plan defines which activities are classified as pre-commissioning, commissioning and SAT, and the hold/witness points for each.

ICAO Annex 14, Volume I

Aerodrome Design and Operations — general basis for AGL system performance that commissioning and SAT are ultimately verifying against.

DGCA / AAI Requirements

For Indian airport projects, also verify applicable DGCA requirements, AAI requirements, airport-specific technical specifications, and contract-specific commissioning/SAT procedures.

Final Engineering Note

Do not assume SAT and commissioning are always separate stages. The contract specification and approved test procedures — not general terminology — define the actual scope and sequence on a given project.

Commissioning proves the system works; SAT formally records that it meets the agreed acceptance requirements — on many AGL projects, the two are performed together.

Precision AGL Academy

Compare the Systems. Then Learn How to Engineer Them.

Understanding the difference between AGL systems is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how AGL systems work as part of a complete airport lighting system, not just as individual components or configurations.

Compare. Understand. Apply. Engineer.

Continue Exploring