Earth Pit
A dedicated excavation or enclosure containing one or more earth electrodes, used to establish a reliable low‑impedance connection to the general mass of earth. Earth pits are fundamental to the earthing system of Airfield Ground Lighting (AGL) infrastructure, providing a safe path for fault currents, lightning strikes, and static discharge, ensuring personnel safety and equipment protection.
Image disclaimer: For identification and illustration only. It may show a product by another manufacturer and may not depict the exact item described; it is not a statement of any product’s quality, approval or performance. Third-party image and trademark rights belong to their owners. See full notice.
What Is It?
An Earth Pit (also known as an earthing pit or grounding pit) is a physical structure that houses the earth electrode and its associated connections, providing a point of access for testing, inspection, and maintenance of the earthing system. The key components of an earth pit include:
- Earth Electrode: The conductive element that makes contact with the soil. Common types include:
- Copper‑bonded steel rods: Most common, with a copper coating for corrosion resistance and steel core for mechanical strength.
- Copper plates: Used in areas with high resistivity or for large‑current installations.
- Chemical (maintenance‑free) electrodes: Filled with conductive compounds (e.g., bentonite) to reduce resistance.
- Pipe electrodes: Galvanised iron or copper pipes, driven vertically.
- Pit Enclosure: A robust, weatherproof chamber (typically made of brick, concrete, or heavy‑duty plastic) that protects the electrode and connections from mechanical damage, moisture, and corrosion. It includes a removable cover for access.
- Connection Lugs: Heavy‑duty copper or aluminium lugs for connecting the earth conductor (from the equipment or lightning protection system) to the electrode.
- Backfill Material: The soil or conductive material (e.g., bentonite, charcoal, salt) used to surround the electrode and enhance conductivity.
- Test Terminal: A removable link or terminal that allows the earth resistance to be measured without disturbing the permanent connections.
Earth pits are strategically located throughout the AGL infrastructure, including near CCR rooms, ALCMS shelters, lighting control panels, and at the base of tall structures (masts, towers).
Purpose & Function
The earth pit's purpose is to make the earth electrode buried beneath it a permanently testable, maintainable part of the earthing system rather than an inaccessible connection lost underground. Because an earthing system's effectiveness depends on its resistance staying below a specified threshold over years of soil movement, moisture change, and corrosion, the pit's accessible test terminal is what allows that resistance to actually be measured periodically rather than assumed — turning an invisible safety-critical connection into one that can be verified and, if necessary, remediated before it fails during an actual fault or lightning event.
Where Is It Used?
Earth pits are essential in every part of the AGL earthing network:
- CCR Rooms and Substations: Providing a low‑resistance earth connection for the main switchgear, transformers, and CCR panels.
- ALCMS and Communication Shelters: Earthing for sensitive electronic equipment and lightning protection systems.
- Lighting Control Panels (LCPs): Local earthing for outdoor panels and their internal surge protection devices.
- Airfield Lighting Circuits: Earthing of cable trays, junction boxes, and metal enclosures along the series lighting circuits.
- Obstruction Lighting Structures: Earthing of masts, towers, and poles supporting obstruction lights.
- Apron Floodlight Masts: Earthing for tall floodlight structures and their associated power supplies.
- Equipment Shelters: Earthing of remote equipment huts housing RTUs, modems, and power supplies.
- Lightning Protection Systems: The final termination point for down conductors from air terminals.
Installation & Location
Earth pits are installed directly above the buried electrode at every earthing point in the network — CCR rooms, substations, lighting control panels, junction boxes along the series circuits, and the base of masts and poles — with the chamber's cover set flush with finished grade or paving so it doesn't create a trip or mowing hazard while remaining findable for testing. The pit is sized to give a technician room to access the electrode connection, test link, and any maintenance-free earthing compound or backfill, and is positioned clear of building foundations, buried services, and heavy vehicle loading where practical. Its location is recorded on the site earthing drawing so each pit can be located, opened, and tested as part of the periodic resistance-testing programme without needing to trace cabling first.
How Does It Work?
An earth pit works by providing a low‑impedance path for electrical current to flow into the earth, thereby dissipating fault currents and lightning surges safely. The key principles are:
- Low Resistance Path: The earth electrode, buried in conductive soil (or backfill), offers a resistance typically less than 10Ω (and often below 5Ω for critical systems). This ensures that fault currents are rapidly diverted to ground, preventing dangerous touch voltages.
- Dissipation of Lightning Current: During a lightning strike, the high‑frequency surge current is conducted through the down conductors to the earth pit, where it spreads into the surrounding earth without causing damage.
- Equipotential Bonding: All metallic parts connected to the earth pit are brought to the same potential, eliminating dangerous voltage differences that could cause sparking or electric shock.
- Testing and Maintenance: The test terminal allows periodic measurement of earth resistance using a 3‑point or 4‑point earth tester, ensuring the earthing system remains effective over time.
- Corrosion Protection: The electrode material and backfill are chosen to resist corrosion, ensuring long‑term stability. Copper‑bonded steel rods, for example, provide excellent corrosion resistance while maintaining mechanical strength.
System Architecture & Control Logic
The earth pit does not exert active control, but it is the architectural access point for managing the electrode buried beneath it: the test terminal inside the pit lets the electrode be electrically isolated from the rest of the bonded system for a clean four-point resistance measurement, without disturbing any permanent connection. In this sense the "control logic" of an earth pit is procedural rather than electronic — a maintenance schedule dictates how often the link is opened and the resistance measured, and the result is compared against a threshold (commonly below 5–10Ω depending on the installation) to decide whether remedial work such as additional electrodes or chemical backfill is required. On more heavily instrumented sites, a continuous earth-monitoring relay can be wired across the test link to watch loop impedance in real time and report a fault condition to a central panel, but the earth pit's core role remains giving inspectors physical, testable access to a component that would otherwise be inaccessible once buried.
Testable Dissipation Assembly
Unlike a bare electrode, the earth pit houses an accessible test link inside an inspection chamber — letting the resistance path be measured and maintained without excavation.
Fault Current / Lightning Surge
Down Conductor
Test Link / Terminal
Accessible via cover, removable joint
Earth Electrode
Inside backfilled pit
Soil Mass
Dissipated, resistance ≤10Ω target
Annual Inspection
Cover lifted, test link opened, resistance measured with a 3- or 4-point earth tester — without disturbing the electrode
Physical Construction
The pit is a below-grade chamber built around the driven earth electrode, formed from precast concrete rings, brick masonry, or a heavy-duty PVC housing set into an excavated hole with the electrode's connection point sitting near the base or mid-height of the chamber. Conductive backfill — bentonite, charcoal, or a proprietary compound — is packed around the electrode inside the pit to keep contact resistance low and stable through seasonal changes in soil moisture. A cast-iron, steel, or heavy-duty plastic cover plate with lockable bolts sits flush with the surrounding grade, protecting the chamber from surface water ingress and unauthorised access while still allowing periodic opening for inspection. Inside, a removable test link or bolted joint isolates the electrode from the rest of the earthing system so its individual resistance can be measured without disturbing the wider bonding network, and the connection lug is sized in electrolytic copper to carry full fault current without overheating.
Technical Parameters
| Parameter | Typical Value |
|---|---|
| Electrode Material | Copper‑bonded steel, solid copper, galvanised steel, stainless steel |
| Electrode Diameter | 12.7 mm, 14.2 mm, 17.2 mm (common sizes) |
| Electrode Length | 2.4 m, 3.0 m, 6.0 m (driven in sections) |
| Earth Resistance Target | ≤ 10Ω (general), ≤ 5Ω (critical systems), ≤ 1Ω (special installations) |
| Copper Coating Thickness | ≥ 250 µm (for copper‑bonded rods) |
| Connection Lug Material | Electrolytic copper (≥ 25 mm² cross‑section) |
| Pit Enclosure | Precast concrete, brick masonry, or heavy‑duty PVC |
| Pit Dimensions | 300 mm x 300 mm to 600 mm x 600 mm (typical) |
| Cover Plate | Cast iron, steel, or heavy‑duty plastic with lockable bolts |
| Backfill Material | Bentonite, charcoal, salt, or native soil with additives |
| Test Terminal | Removable link or bolted joint |
| Inspection Interval | Annual visual inspection, earthing resistance test every 1‑2 years |
| Standards Compliance | IEEE 80, IEC 62305, IS 3043, BS 7430, FAA AC 150/5340‑30 |
Applicable Standards
IEEE 80
Guide for Safety in AC Substation Grounding – Earthing design and resistance criteria
IEC 62305
Protection against lightning – Earthing and bonding requirements
IS 3043
Indian Standard for Code of Practice for Earthing
BS 7430
Code of Practice for Protective Earthing of Electrical Installations
FAA AC 150/5340‑30
Design and Installation Details for Airport Visual Aids – grounding and bonding requirements
Installation Requirements
Pit Positioning Above Electrode
SiteInstall the pit directly above the buried electrode at every earthing point — CCR rooms, substations, panels, junction boxes, and mast or pole bases.
Flush Cover Setting
CivilSet the chamber cover flush with finished grade or paving so it doesn't create a trip or mowing hazard while remaining findable for testing.
Foundation/Service Clearance
CivilPosition the pit clear of building foundations, buried services, and heavy vehicle loading where practical.
Access Sizing for Test Link
MechanicalSize the pit to give a technician room to access the electrode connection, test link, and any maintenance-free earthing compound or backfill.
Backfill/Earthing Compound Placement
ElectricalPlace bentonite, charcoal, salt, or native soil with additives per the earthing design.
Site Earthing Drawing Record
DocumentationRecord the pit's location on the site earthing drawing so it can be located, opened, and tested without needing to trace cabling first.
Pre-Energisation Sign-off
DocumentationRecord pit position, cover type, and test link details as-built before the site is closed.
Testing & Commissioning
Soil Resistivity Survey
Pre-EnergisationCarry out a Wenner four-pin soil resistivity survey at the pit location to confirm the electrode configuration will achieve the design earth resistance target.
Earth Resistance (Fall-of-Potential) Test
Pre-EnergisationMeasure electrode resistance to earth using the fall-of-potential method via the test terminal before the pit is finally sealed.
Test Terminal / Link Function Verification
EnergisationOperate the removable link or bolted joint to confirm the electrode can be isolated from the bonded system for periodic testing without excavation.
Connection & Lug Verification
EnergisationConfirm the electrolytic copper connection lug and cable termination are correctly sized, torqued, and free of corrosion before the pit is closed.
Enclosure & Cover Verification
Final AcceptanceCheck the precast concrete, brick, or PVC enclosure and lockable cover plate are correctly seated, load-rated for the location, and free from cracking or damage.
Backfill Material Verification
Final AcceptanceConfirm bentonite, charcoal, salt, or additive backfill has been placed and compacted correctly around the electrode to support the measured resistance value long-term.
Documentation & As-Built Sign-off
Final AcceptanceRecord soil resistivity, earth resistance readings, pit dimensions, and electrode position in the commissioning dossier for handover.
Inspection & Maintenance
Earth Resistance Test
AnnualMeasure resistance to ground and compare against baseline and required threshold.
Pit Cover & Lid Inspection
AnnualCheck the pit cover and lid for cracking, water pooling, or mechanical damage.
Connection & Corrosion Check
AnnualOpen the pit and inspect the electrode and connections for corrosion or looseness.
System Adequacy Review
Every few years, or after site changesConfirm the number and layout of pits still meets the required overall earthing resistance.
Common Field Issues
High Earth Resistance
Dry soil conditions, soil resistivity changes, or electrode corrosion can increase earth resistance above acceptable limits. Regular testing and corrective measures (e.g., adding more electrodes, using chemical backfill, or installing additional pits) are necessary.
Corrosion of Electrode and Connections
Copper‑bonded rods can corrode over time, especially in aggressive soils (high salinity, acidic). Use of stainless steel or solid copper electrodes, and ensuring proper backfill, can mitigate this. Regular inspection and replacement are recommended.
Loose or Poor Connections
Connection lugs and test terminals can become loose due to vibration or thermal cycling, increasing resistance and potentially causing arcing. Torque‑tighten connections and use lock washers or anti‑vibration compounds.
Water Ingress and Mechanical Damage
Earth pits can be flooded or suffer mechanical damage (cracks in the cover or enclosure). Ensure proper drainage, use water‑tight covers, and protect pits from vehicle traffic or heavy equipment.
Inadequate Number of Pits
For large AGL installations, a single earth pit may not provide sufficiently low resistance. Multiple pits interconnected by a ring earth conductor are often required to achieve the desired resistance.
Troubleshooting Guide
Measured Resistance Above Acceptable Limit
Loose or Corroded Test Terminal
Water Ingress or Flooding in the Pit
Cover Cracked or Pit Damaged by Traffic
Failure Modes & Root Causes
Elevated Pit Resistance
Loose or Corroded Test Terminal
Water Ingress or Flooding
Cover or Pit Structural Damage
Safety & Operational Notes
Assume Fault or Lightning Current May Be Present
Electrical SafetyTreat the electrode and its connections inside the pit as potentially carrying fault or lightning current at any time; do not disconnect a bonding link without first confirming the associated system is isolated or that the disconnection is planned and safe.
Confined Space & Pit Access
OperationalCheck for water, gas accumulation, or unstable fill before entering a deep earth pit, and follow the aerodrome's confined-space and lone-working procedures for below-grade access.
Water Ingress in the Pit
Electrical SafetyTreat standing water in an earth pit as a potential conduction path during a fault or lightning event; avoid reaching into a flooded pit and pump it out before working on the electrode or test link.
Test Before Relying on a Connection
Electrical SafetyMeasure earth resistance at the test link and verify continuity to the main earthing system after any work in the pit, and do not treat a reinstated connection as effective protection until it has been tested.
Cover & Frame Manual Handling
Personnel SafetyUse correct lifting technique or lifting tools for heavy pit covers and frames, and never leave a cover partially raised or unsecured over an open pit on the movement area.
Secure the Test Link After Testing
ComplianceReinstate and torque the removable test link correctly after taking a resistance reading; a test link left open disconnects the electrode from the system it is meant to protect.
FOD Control at the Open Pit
OperationalKeep tools, fasteners, and covers accounted for at all times when the pit is open, and secure or remove any loose material before reinstating the cover, to prevent foreign object debris on the movement area.
Restore to Compliant State
ComplianceDo not leave a pit cover unseated or a test link disconnected after maintenance; verify a compliant, secure closure and a tested connection before closing out the work.
Engineering & Expert Notes
Seasonal Drift Is Normal, Sudden Jumps Are Not
DiagnosticsEarth pit resistance naturally rises and falls with soil moisture across wet and dry seasons, so judge a reading against the pit's own seasonal history rather than a single fixed number. A sudden jump outside that seasonal band, rather than the slow seasonal swing itself, is the signal worth chasing.
A Corroded Test Link Reads Like a Bad Electrode
TroubleshootingBefore condemning an earth electrode over a high reading, check the test link connection itself; a corroded or loose test link joint adds resistance that has nothing to do with the electrode or soil, and cleaning the joint alone can resolve an apparent failure.
Salt/Chemical Backfill Wears Out Over Years
MaintenanceConductive backfill compounds used to lower resistance in poor soil leach out gradually over years of rainfall. A pit that met spec at commissioning can drift out of tolerance purely from backfill depletion, so factor replenishment into the long-term maintenance plan, not just electrode inspection.
Isolate the Pit From the Grid Before Testing
TechniqueTesting an earth pit while it is still bonded into the wider earthing grid can mask a genuinely poor individual electrode, since parallel paths through other pits carry the test current. Disconnect the bonding link before a fall-of-potential test to get a true reading for that pit alone.
Probe Spacing Errors Distort Fall-of-Potential Results
TechniquePlacing the potential probe too close to the electrode under test, rather than out near the theoretical 62% distance, is a common source of an artificially low or unstable reading. Where results look implausibly good, verify probe placement before trusting the number.
Log Readings Against the Same Pit Every Cycle
ProcessKeep resistance readings tied to a fixed pit ID rather than a general area, since pits a few metres apart in different soil strata can behave very differently. A per-pit history is what actually reveals a genuine degrading trend versus normal site-to-site variation.
Frequently Asked Questions
Short answers about the Earth Pit: what it is, how it works, typical specifications, standards, maintenance and common faults.
Q1What is an Earth Pit?
An Earth Pit (also known as an earthing pit or grounding pit) is a physical structure that houses the earth electrode and its associated connections, providing a point of access for testing, inspection, and maintenance of the earthing system. The key components of an earth pit include: Earth Electrode: The conductive element that makes contact with the soil. Common types include: Copper‑bonded steel rods: Most common, with a copper coating for corrosion resistance and steel core for mechanical strength.
Q2What is the purpose of an Earth Pit?
The earth pit's purpose is to make the earth electrode buried beneath it a permanently testable, maintainable part of the earthing system rather than an inaccessible connection lost underground. Because an earthing system's effectiveness depends on its resistance staying below a specified threshold over years of soil movement, moisture change, and corrosion, the pit's accessible test terminal is what allows that resistance to actually be measured periodically rather than assumed — turning an invisible safety-critical connection into one that can be verified and, if necessary, remediated before it fails during an actual fault or lightning event.
Q3Where is an Earth Pit used and installed?
Earth pits are essential in every part of the AGL earthing network: CCR Rooms and Substations: Providing a low‑resistance earth connection for the main switchgear, transformers, and CCR panels. ALCMS and Communication Shelters: Earthing for sensitive electronic equipment and lightning protection systems. Lighting Control Panels (LCPs): Local earthing for outdoor panels and their internal surge protection devices. Airfield Lighting Circuits: Earthing of cable trays, junction boxes, and metal enclosures along the series lighting circuits.
Q4How does an Earth Pit work?
An earth pit works by providing a low‑impedance path for electrical current to flow into the earth, thereby dissipating fault currents and lightning surges safely. The key principles are: Low Resistance Path: The earth electrode, buried in conductive soil (or backfill), offers a resistance typically less than 10Ω (and often below 5Ω for critical systems). This ensures that fault currents are rapidly diverted to ground, preventing dangerous touch voltages.
Q5What are the typical technical parameters of an Earth Pit?
Typical values are — Electrode Material: Copper‑bonded steel, solid copper, galvanised steel, stainless steel; Electrode Diameter: 12.7 mm, 14.2 mm, 17.2 mm (common sizes); Electrode Length: 2.4 m, 3.0 m, 6.0 m (driven in sections); Earth Resistance Target: ≤ 10Ω (general), ≤ 5Ω (critical systems), ≤ 1Ω (special installations); Copper Coating Thickness: ≥ 250 µm (for copper‑bonded rods); Connection Lug Material: Electrolytic copper (≥ 25 mm² cross‑section); Pit Enclosure: Precast concrete, brick masonry, or heavy‑duty PVC; Pit Dimensions: 300 mm x 300 mm to 600 mm x 600 mm (typical); Cover Plate: Cast iron, steel, or heavy‑duty plastic with lockable bolts.
Q6Which standards apply to an Earth Pit?
The main references are IEEE 80 — Guide for Safety in AC Substation Grounding – Earthing design and resistance criteria; IEC 62305 — Protection against lightning – Earthing and bonding requirements; IS 3043 — Indian Standard for Code of Practice for Earthing; BS 7430 — Code of Practice for Protective Earthing of Electrical Installations; FAA AC 150/5340‑30 — Design and Installation Details for Airport Visual Aids – grounding and bonding requirements. Always verify the current edition and your aerodrome's approved requirements.
Q7How often should an Earth Pit be inspected and maintained?
Typical maintenance tasks and intervals are: Earth Resistance Test (annual); Pit Cover & Lid Inspection (annual); Connection & Corrosion Check (annual); System Adequacy Review (every few years, or after site changes). Your airport's approved maintenance programme takes precedence.
Q8How do I troubleshoot common Earth Pit faults?
Common symptoms covered are: Measured Resistance Above Acceptable Limit; Loose or Corroded Test Terminal; Water Ingress or Flooding in the Pit; Cover Cracked or Pit Damaged by Traffic. For example, for "Measured Resistance Above Acceptable Limit": Likely Cause: Dry soil conditions, electrode corrosion, or an insufficient number of pits for the installation. Diagnostic Steps: Test resistance at the pit using a fall-of-potential method; inspect the electrode and connections through the open pit; review the ring-earth interconnection to nearby pits. Corrective Action: Add chemical backfill, install additional interconnected pits, or replace the electrode, then re-test to confirm resistance is within limits.
Related Components
Go Beyond the Component. Understand the Complete AGL System.
You have explored the component. Now understand how it works within the complete Airfield Ground Lighting system.
Learn AGL from fundamentals to design, installation, testing, photometry, commissioning, maintenance and troubleshooting through structured technical training at Precision AGL Academy.
Build practical knowledge. Understand the circuit. Read the standards. Troubleshoot with confidence.
Your next step in AGL starts here.
Need expert guidance on earth pit design, installation, or testing?
Precision AGL Academy provides advice on earthing resistance optimization, electrode selection, and compliance with international standards for AGL earthing systems.
Follow the Academy
Important Notice, Disclaimer & Limitation of Liability
Please read before relying on any content on this page.
- Purpose and intended users. This page on Earth Pit is an independent educational and informational reference for competent, suitably trained and authorised airfield ground lighting (AGL) and aerodrome electrical personnel. It is not professional engineering, legal or regulatory advice, and using it does not create any professional or client relationship.
- Safety. Work on series circuits, constant current regulators (CCRs), isolating transformers, cables, connectors and lighting equipment can be fatal. Always apply the aerodrome’s permit-to-work and isolation/LOTO procedures, prove dead, use correctly rated instruments and PPE, and follow the manufacturer’s instructions. Nothing here authorises work on live equipment or the bypassing of any safety device or interlock.
- Aviation operations. Nothing here authorises installation, modification, energisation, adjustment, return to service, a change of operating category (CAT I/II/III), a NOTAM or any aerodrome certification or approval decision. These rest with the aerodrome operator, the air navigation service provider and the competent regulator.
- Specifications, ratings and typical values. Descriptions, parameters, ratings, dimensions, photometric values, wattages, service lives, maintenance tasks and intervals, failure modes, certifications (for example CE, FCC, UL or IEC marks) and part or type designations are general, typical and indicative. They may not match any particular product, make, model or version, and they are not a datasheet, design, specification, selection, sizing, procurement or acceptance criterion. The manufacturer’s current documents, the approved design and the project specification prevail.
- Standards and regulations. References to ICAO, FAA, IEC, IEEE, ISO, BIS, DGCA and other standards are paraphrased summaries for orientation only. They may be incomplete or out of date, and standards are revised from time to time. Consult the current official editions. Following this content does not guarantee compliance with any law, standard or regulatory approval, and the regulator’s requirements always prevail.
- No warranty. Content is provided “as is” and “as available”, without warranty of any kind, express or implied, including accuracy, completeness, currency or fitness for a particular purpose. Real installations differ in design, equipment make and model, age and condition.
- Limitation of liability. To the fullest extent permitted by applicable law, Precision AGL Academy, Precision AGL Solutions and their owners, authors and contributors are not liable for any injury, death, loss, damage, downtime, penalty or regulatory consequence, whether direct or indirect, arising from the use of, reliance on, or inability to use this content. Nothing in this notice excludes or limits any liability that cannot lawfully be excluded or limited.
- Independence, brands and no endorsement. This is an independent publication. It is not affiliated with, sponsored by or endorsed by ICAO, the FAA, the IEC, DGCA, AAI, any airport, regulator, supplier or equipment manufacturer. Third-party names, product designations, standard designations and trademarks (including Megger®, Siemens, Eaton, Crouse-Hinds, ADB SAFEGATE, Fluke, ABB and Honeywell) belong to their respective owners and are used only for identification and description. Mention of a brand, product or supplier is not a recommendation, and we do not sell, supply or quote for any component described.
- Images and third-party content. Images and illustrations are shown to help identify the type of component. They may show products of various manufacturers, may not depict the exact item described, and are not a statement about any product’s quality, approval or performance. Copyright and trademarks in third-party images, logos and photographs belong to their respective owners and are not claimed as ours. If you are a rights holder and want an image removed, replaced or credited, email precisionaglsolutions@gmail.com with the page address and we will act promptly.
- Training and services. Mentions of training, courses, consultation, advice, selection, installation, calibration or other support, including the “Learn…Certify” pathway, describe learning stages and are not an offer, quotation, tender or promise of any result. Contacting us or our replying creates no engagement or duty of care; an engagement exists only under a written agreement. We are not a regulator or certification body, and completing any course or reading this content is not a certification, accreditation or authorisation to work on any aerodrome.
- Copyright, privacy and corrections. © 2026 Precision AGL Academy. All rights reserved. Text, structure, compilations and diagrams may be viewed for personal reference and internal training only; any other copying, republication or commercial use needs our written permission. If you email, telephone or message us, we use your details only to respond and handle your matter, in line with applicable Indian law including the Digital Personal Data Protection Act, 2023; please do not send confidential or security-sensitive information. To display this page your browser requests fonts, icons and images from third-party servers, which receive your IP address and browser details under their own policies. Content is reviewed periodically with no obligation to update. To report an error, safety concern or rights issue, write to precisionaglsolutions@gmail.com.