Division 04 of 25 · INST Series

Installation Forms

The 25 forms that turn approved design and approved materials into a traceable field record — every installed cable, base can, fixture, transformer, connector, earth, sign, PAPI, approach light, CCR and ALCMS unit made physically identifiable, location-traceable, technically verifiable, and linked to its inspection and test records. Grouped into Installation Records and Installation Verification, this division is the field installation evidence layer that bridges Design/Procurement (Divisions 02–03) and Testing, Commissioning & Maintenance.

25 / 25
Forms Scoped
INST-01 → INST-25
Form ID Range
2
Categories
Rev 0
Initial Issue

Where this fits — Division 02 designs the AGL system and Division 03 approves the materials for it; this division proves what actually went into the ground and how it was verified. Every asset record here should trace back to an approved drawing and forward into the Installation Completion Certificate and Handover Record that release the work to Testing & Commissioning.

A · Installation Records

15 of 15 forms
INST-01 Installation Checklist Checklist
Purpose

The master checklist confirming that an AGL installation activity has been performed according to the approved design, drawings, specifications, and approved installation procedure.

Key Fields
  • Approved drawing available and latest revision verified
  • Approved material available and inspected
  • Method statement / risk assessment approved
  • Work permit and site access available
  • Tools, test equipment, and valid calibration in place
  • Correct location, orientation, elevation, and mounting
  • Cable connection, identification, and earthing completed
  • Visual inspection, snags, and corrective actions closed
Feeds every asset-specific installation record below.
INST-02 Site Installation Record Record
Purpose

A detailed record of installation activities carried out at a specific site or location, on a given date and shift.

Key Fields
  • Site Installation Record No.
  • Location / work area
  • Date, shift, weather
  • Contractor / supervisor / installation team
  • Activity performed, equipment installed, quantity
  • Tools and test equipment used
  • Inspection completed / installation accepted
  • Defects, snags, photographs, remarks
INST-03 Cable Laying Record Record
Purpose

Creates a traceable record of primary and other AGL cable installation, from drum to installed route.

Key Fields
  • Cable Record No. / Circuit ID / Cable ID
  • Cable type, manufacturer, size, voltage rating
  • Drum number, drum length, starting/end point, total installed length
  • Route, trench/duct, pulling method and tension
  • Bend, joint, and crossing locations
  • Correct cable, route, and identification verified
  • Continuity and insulation test completed
  • Traceability: drum → cable ID → circuit → route → location → test record
Feeds INST-04 Cable Route Record and INST-21 Cable Identification Record.
INST-04 Cable Route Record Record
Purpose

Documents the actual installed cable route and makes it traceable for future maintenance, against the designed route.

Key Fields
  • Cable ID / Circuit ID / Cable type
  • Start location / end location / route description
  • Drawing reference / trench or duct identification
  • Crossing, junction, and joint points
  • Coordinates / reference points / installed length
  • Designed route vs actual route
  • Deviation and reason for deviation / approval reference
  • As-built drawing / asset database reference
Feeds the as-built drawing and asset/cable database.
INST-05 Base Can Installation Record Record
Purpose

Documents installation of inset/elevated fixture base cans and associated mounting arrangements.

Key Fields
  • Base Can ID / Location / Runway-Taxiway / chainage
  • Drawing reference / base-can type / manufacturer / model
  • Dimensions, elevation, orientation, foundation details
  • Level verified / foundation satisfactory / drainage provision
  • Cable entry and cable protection verified
  • Earthing provision and mounting arrangement verified
  • Fixture ID linked / installation date / inspector
  • Photographs and remarks
INST-06 Fixture Installation Record Record
Purpose

Documents installation of individual AGL lighting fixtures, linked back to base can, transformer, and circuit.

Key Fields
  • Fixture ID / Circuit ID / Location / Runway-Taxiway
  • Fixture type, manufacturer, model, serial number, part number
  • Transformer ID / Base Can ID
  • Mounting arrangement, orientation, elevation, alignment
  • Connector, cable connection, torque
  • Earthing/bonding and sealing
  • Correct fixture, location, orientation, elevation, transformer, connector, circuit verified
  • No physical damage / identification complete
Feeds INST-16 Fixture Alignment Record and INST-17 Fixture Elevation Record.
INST-07 Transformer Installation Record Record
Purpose

Documents installation of AGL isolation transformers, including rating, connections, and protection.

Key Fields
  • Transformer ID / Circuit ID / Location
  • Manufacturer, model, serial number, VA rating
  • Primary rating / secondary rating / batch number / certificate reference
  • Primary and secondary connection, connector, cable
  • Mounting/location, earthing, identification, protection, sealing
  • Correct transformer, rating, and circuit verified
  • Installation visually satisfactory
  • Test record linked
Feeds INST-18 Transformer Connection Record.
INST-08 Connector Installation Record Record
Purpose

Documents installation of AGL connectors and ensures proper electrical and mechanical connection.

Key Fields
  • Connector ID / Circuit ID / Cable ID / Equipment ID
  • Connector type, manufacturer, part number, serial/batch number
  • Installation location
  • Correct connector, cable, termination, and polarity
  • Correct mechanical connection and sealing
  • Torque verified / identification complete / no damage
  • Installer / inspector / date
  • Test reference and remarks
Feeds INST-19 Connector Torque Record.
INST-09 Earthing Installation Record Record
Purpose

Documents installation and connection of equipment earthing/bonding arrangements.

Key Fields
  • Earthing record number / equipment / equipment ID / location
  • Earth conductor and conductor size
  • Earth electrode/reference / connection point / bonding arrangement
  • Correct conductor and connection verified
  • Connection mechanically secure / corrosion protection completed
  • Identification completed / continuity verified
  • Earth resistance test reference available
  • Test instrument, calibration reference, inspector
Feeds INST-20 Earthing Connection Record.
INST-10 Sign Installation Record Record
Purpose

Documents installation of airfield signs — foundation, mounting, illumination, and identification.

Key Fields
  • Sign ID / sign type / location / Runway-Taxiway
  • Manufacturer, model, serial number, legend, size
  • Circuit ID / Transformer ID
  • Foundation, mounting, orientation, elevation, alignment
  • Cable, connector, earthing, identification
  • Correct sign, legend, location, and orientation verified
  • Correct electrical connection and illumination
  • Structural condition / no damage
INST-11 PAPI Installation Record Record
Purpose

Documents physical and electrical installation of PAPI/APAPI units, including alignment and elevation.

Key Fields
  • PAPI ID / Runway / Location / unit number
  • Manufacturer, model, serial number, optical configuration
  • Power supply / Circuit / transformer or control equipment
  • Correct location, elevation, alignment, azimuth, unit spacing
  • Foundation satisfactory / electrical connection correct
  • Earthing completed / mechanical adjustment available
  • Identification complete
  • Installation, alignment, elevation survey and functional test reference
INST-12 Approach Light Installation Record Record
Purpose

Documents installation of approach lighting equipment relative to centreline and crossbar references.

Key Fields
  • Runway / runway end / approach system
  • Light ID / location / centreline reference / crossbar reference
  • Fixture type / Transformer ID / Circuit ID
  • Correct position, spacing, elevation, orientation, alignment
  • Correct circuit and transformer
  • Correct mounting
  • Structural condition verified
INST-13 CCR Installation Record Record
Purpose

Documents installation of Constant Current Regulators, including rating, wiring, and control interface.

Key Fields
  • CCR ID / manufacturer / model / serial number
  • Rated current, rated power, number of steps, input voltage
  • Output configuration / circuit assignment / control interface
  • Location / foundation-mounting / ventilation-clearance
  • Input, output, and control connection
  • Earthing and communication
  • Correct CCR, rating, and circuit verified
  • Input, output, control wiring and earthing verified
INST-14 ALCMS Installation Record Record
Purpose

Documents installation of AGL control and monitoring equipment — cabinet, PLC, HMI, and interface modules.

Key Fields
  • Equipment ID (cabinet / PLC / HMI / control panel / comms / network / interface / monitoring modules)
  • Manufacturer, model, serial number
  • Panel location / power supply
  • Communication connection, I/O connection, network connection
  • Earthing
  • Equipment installed and wiring completed / labels installed
  • Communication and network connections verified
  • Software/configuration reference recorded
INST-15 Cable Joint Record Record
Purpose

Documents each AGL cable joint and provides permanent traceability of the jointing process and test results.

Key Fields
  • Joint ID / Circuit ID / Cable IDs / location
  • Joint type, manufacturer, joint kit, batch number, installation date, installer
  • Cable and connector preparation / jointing procedure
  • Insulation, sealing, mechanical protection, identification
  • Continuity and insulation resistance test / test voltage and result
  • Test instrument and calibration reference
  • Accepted / rework required / rejected

B · Installation Verification

10 of 10 forms
INST-16 Fixture Alignment Record Verification Record
Purpose

Verifies that installed AGL fixtures are correctly aligned with the approved design.

Key Fields
  • Fixture ID / Location / Runway-Taxiway / fixture type
  • Design orientation vs actual orientation
  • Alignment reference / measurement method / measurement equipment
  • Result vs tolerance / acceptance criterion
  • Corrective adjustment and final result
  • Alignment correct / beam direction correct
  • Fixture secured, no movement
  • Final alignment recorded
INST-17 Fixture Elevation Record Verification Record
Purpose

Verifies the installed fixture elevation against the approved design and reference datum.

Key Fields
  • Fixture ID / Location
  • Design elevation vs actual elevation / reference datum
  • Measurement method / survey equipment / survey date
  • Difference and acceptance status
  • Within requirement / adjustment required / reinspection required
INST-18 Transformer Connection Record Verification Record
Purpose

Verifies correct connection of isolation transformers on both the primary and secondary side.

Key Fields
  • Transformer ID / Circuit ID / Fixture ID
  • Primary: cable ID, connector, polarity, connection
  • Secondary: fixture cable, connector, polarity, connection
  • Identification complete
  • Correct transformer, primary, secondary, and polarity
  • Correct connector / connection secure
INST-19 Connector Torque Record Verification Record
Purpose

Provides evidence that specified connector/terminal torque requirements have been correctly applied.

Key Fields
  • Connector ID / Equipment ID / connection point
  • Required torque vs actual torque / torque unit
  • Torque wrench ID / calibration certificate
  • Date / technician / inspector
  • Required torque met / torque tool calibrated
  • Connection inspected and record accepted
INST-20 Earthing Connection Record Verification Record
Purpose

Verifies individual equipment earthing and bonding connections against the required condition.

Key Fields
  • Equipment ID / Location / earth connection ID
  • Conductor size / connection type
  • Earth point / bonding point
  • Required condition vs actual condition
  • Connection secure / conductor and termination correct
  • Corrosion protection completed
  • Continuity verified / test record referenced
INST-21 Cable Identification Record Verification Record
Purpose

Ensures that every installed cable can be identified and traced throughout the AGL system.

Key Fields
  • Cable ID / Circuit ID / cable type / size / manufacturer
  • Drum number / start point / end point / route
  • Identification tag / label location
  • Joint references / equipment connections / as-built reference
  • Cable label installed / circuit identification correct
  • Start/end identification correct
  • Drawing updated / asset register updated
INST-22 Installation Quality Checklist Checklist
Purpose

The formal quality-control inspection of completed AGL installation, covering materials, installation, cable, and equipment.

Key Fields
  • Approved material used / correct manufacturer-model / traceability available
  • Correct location, orientation, elevation, mounting
  • Correct cable connection, connector, torque
  • Earthing complete / identification complete
  • Correct route / cable protected / ends sealed / joints identified
  • Equipment checked: fixture, transformer, CCR, PAPI, sign, approach lighting, ALCMS
  • Installation, test, and inspection records complete / photographs available
  • Snags recorded and closed
INST-23 Installation Snag List Register
Purpose

Identifies, assigns, and tracks installation deficiencies through to closure.

Key Fields
  • Snag ID / Location / Equipment / deficiency
  • Category (civil, electrical, mechanical, alignment, elevation, cable, connector, earthing, identification, material, documentation, safety, quality)
  • Priority / responsible party / target date
  • Status (open, assigned, in progress, ready for inspection, closed, rejected/rework)
  • Closure evidence
INST-24 Installation Completion Certificate Certificate
Purpose

Formally certifies that the defined installation scope has been completed and is ready for subsequent inspection, testing, and commissioning.

Key Fields
  • Project / work package / location / drawing references
  • Installation scope / start date / completion date / contractor
  • Approved materials used / installation inspections completed
  • Cable, equipment, and earthing records completed
  • Alignment / elevation verified / snags closed
  • Outstanding items identified
  • Certification statement
  • Signatures: Installation Engineer, QA/QC Engineer, AGL Engineer, Project Manager, Consultant/Client
Gates the Installation Handover Record below.
INST-25 Installation Handover Record Handover Record
Purpose

Transfers the completed installation package from the installation team to testing/commissioning, operations, or the next project-control stage.

Key Fields
  • Project / work package / location / handover date
  • Handing-over party / receiving party / installation completion certificate reference
  • Physical handover: fixtures, transformers, cables, connectors, CCRs, signs, PAPI, approach lighting, ALCMS, earthing
  • Documentation handover: checklists, site and cable records, alignment/elevation/torque records, quality and snag closure records, as-built information
  • Outstanding items: item, responsible party, target date, status
  • Handover status: accepted / accepted with outstanding items / rejected / reinspection required

How Division 04 Connects

These 25 forms build a traceable engineering history for every asset, circuit, cable, transformer, fixture, and connection installed on the airfield — not just proof that equipment was installed.

Installation Control Flow

The two categories in this division follow the field sequence from approved design to handover:

APPROVED DESIGN APPROVED MATERIALS INSTALLATION RECORDS VERIFICATION SNAG CLOSURE COMPLETION HANDOVER

Related Divisions

  • Division 02 — Design & Engineering Forms (calculations and drawings every installation record traces back to)
  • Division 03 — Material & Procurement Forms (approved materials that installation records confirm were used)
  • Division 05 — Testing & Commissioning Forms (receives the completed package via INST-25 Handover Record)
  • Division 20 — Documentation & Records Control (as-built drawings and asset/cable database)

Frequently Asked Questions

Quick answers about the 25 Division 04 Installation forms, how they are grouped, and how they connect to the rest of the library.

Q1What is Division 04 — Installation Forms in the AGL Engineering Forms & Templates library?

Division 04 is a set of 25 installation forms (INST-01 to INST-25) in the AGL Engineering Forms & Templates library. It turns approved design and approved materials into a traceable field record, so that every installed cable, base can, fixture, transformer, connector, earth, sign, PAPI, approach light, CCR and ALCMS unit is identifiable, location-traceable and technically verifiable. The forms are grouped into 2 categories: Installation Records and Installation Verification.

Q2Which forms are included in Installation Records?

Installation Records (15 forms): INST-01 Installation Checklist, INST-02 Site Installation Record, INST-03 Cable Laying Record, INST-04 Cable Route Record, INST-05 Base Can Installation Record, INST-06 Fixture Installation Record, INST-07 Transformer Installation Record, INST-08 Connector Installation Record, INST-09 Earthing Installation Record, INST-10 Sign Installation Record, INST-11 PAPI Installation Record, INST-12 Approach Light Installation Record, INST-13 CCR Installation Record, INST-14 ALCMS Installation Record, INST-15 Cable Joint Record.

Q3Which forms are included in Installation Verification?

Installation Verification (10 forms): INST-16 Fixture Alignment Record, INST-17 Fixture Elevation Record, INST-18 Transformer Connection Record, INST-19 Connector Torque Record, INST-20 Earthing Connection Record, INST-21 Cable Identification Record, INST-22 Installation Quality Checklist, INST-23 Installation Snag List, INST-24 Installation Completion Certificate, INST-25 Installation Handover Record.

Q4What is the difference between the Installation Records and the Installation Verification forms?

The 15 Installation Records (INST-01 to INST-15) document what was installed and where, such as cable laying and route, base cans, fixtures, transformers, connectors, earthing, signs, PAPI, approach lights, CCRs, ALCMS equipment and cable joints. The 10 Installation Verification forms (INST-16 to INST-25) verify the work through alignment, elevation, connection, torque, earthing and cable identification records, then close it out through quality checking, snagging, completion certification and handover.

Q5What forms close out an AGL installation and hand it on?

The Installation Quality Checklist (INST-22) is the formal quality-control inspection of the completed installation. The Installation Snag List (INST-23) identifies, assigns and tracks deficiencies through to closure. The Installation Completion Certificate (INST-24) certifies that the defined scope is complete and ready for inspection and testing, and the Installation Handover Record (INST-25) transfers the completed package to testing and commissioning, operations or the next stage.

Q6Can the forms in Division 04 be downloaded and filled in?

Yes. Each form has a Download as Word button that produces an uncontrolled sample Word template with letterhead, a document-control block, ruled entry fields and a three-tier approval table, ready to print or fill on-screen. Checklist-format forms such as Installation Checklist (INST-01) download with a checkbox and a verified-by line for each item. The forms can also be searched by keyword or form ID.

Q7How does Division 04 connect to design, materials and testing?

Division 02 designs the AGL system and Division 03 approves the materials, while Division 04 proves what actually went into the ground and how it was verified. Every asset record here should trace back to an approved drawing and forward into the Installation Completion Certificate and Handover Record that release the work to testing and commissioning.

Beyond the Paperwork

INSTALL IT RIGHT. KNOW WHY IT’S RIGHT.

Installation forms record what was done — but real field competence means understanding series-circuit architecture, isolating transformer connections, cable routing and depth requirements behind every entry.

Take your knowledge further with Precision AGL Academy.

Build Complete AGL Project Capability

Learn how technical AGL work connects with:

Project Planning Design Procurement Installation Testing Commissioning Safety Documentation Handover Maintenance

Develop the knowledge to not only record the work, but understand the engineering and project-management principles behind it.

Plan the project. Understand the engineering. Deliver with confidence.