Division 07 of 25 · COM Series

Commissioning & Handover Forms

The 25 forms that carry an installed, inspected, and tested AGL system through readiness verification, controlled energization, functional and system-specific commissioning, integrated testing, punch/snag closure, performance verification, and final acceptance — into a complete, signed-off handover package. Grouped into Commissioning Forms, System-Specific Commissioning, Punch & Snag Management, Performance & Acceptance, and Handover Documentation, this division is the operational transition and acceptance layer that bridges Installation/Testing (Divisions 04–06) and safe operational use by the client or airport operator.

25 / 25
Forms Scoped
COM-01 → COM-25
Form ID Range
5
Categories
Rev 0
Initial Issue

Where this fits — Divisions 04–06 install, inspect, and test the physical AGL system; this division proves it was safely energized, that it performs its intended function individually and as an integrated system, and that every outstanding item was closed before the client or operator formally accepted and took delivery of it. Every record here should trace back to an installation, inspection, or test reference and forward into the Final Acceptance Certificate, Taking-Over Certificate, and Handover Certificate that release the project into operational service and Project Closeout.

A · Commissioning Forms

8 of 25 forms
COM-01 Pre-Commissioning Checklist Checklist
Purpose

Verify that all installation, inspection, testing and safety requirements have been completed before energization.

Key Fields
  • Project name / project ID / airport / location / system / circuit-equipment / date
  • Installation complete
  • Drawings available
  • Approved materials confirmed
  • Inspection completed
  • Electrical testing completed
  • Earthing verified
  • Cable identification completed
  • Connections checked
  • Torque verification completed
  • Test equipment calibrated
  • Defects reviewed
  • Safety controls in place
Status: Ready / Ready with observations / Not ready
COM-02 Commissioning Checklist Checklist
Purpose

Provide the master checklist for the complete commissioning process.

Sections
  • Pre-commissioning
  • Installation verification
  • Electrical testing
  • Energization
  • Functional testing
  • Control testing
  • Monitoring
  • Integration
  • Performance verification
  • Documentation
  • Acceptance
Output: Commissioning Completion Percentage
COM-03 Equipment Readiness Certificate Certificate
Purpose

Certify that individual equipment is ready for commissioning.

Key Fields
  • Equipment ID / manufacturer / model / serial number / location
  • Applicable to: CCR, isolation transformer, AGL fixture, PAPI, airfield sign, ALCMS equipment, panel, PLC, communication equipment
  • Installation verification
  • Inspection status
  • Test status
  • Safety status
  • Outstanding defects
  • Readiness status
  • Engineer approval
Decision: Ready for energization / Not ready
COM-04 Circuit Readiness Certificate Certificate
Purpose

Verify that the complete AGL electrical circuit is ready for energization.

Verification
  • Cable installation
  • Cable identification
  • Circuit continuity
  • Insulation resistance
  • Earth continuity
  • Connector installation
  • Transformer connection
  • Fixture connection
  • Circuit drawings
  • CCR output connection
  • Isolation status
  • Test completion
Status: Ready / Not ready
COM-05 Energization Record Record
Purpose

Provide controlled evidence for initial energization.

Key Fields
  • Energization ID / date-time / circuit-system
  • Responsible engineer
  • Permit reference
  • Isolation removal
  • Pre-energization inspection
  • Voltage / current
  • Initial observation
  • Abnormal condition
  • Result
  • Authorization
Result: Successful / Abnormal / Failed
COM-06 CCR Energization Record Record
Purpose

Control energization of the Constant Current Regulator.

Verification
  • Input supply
  • Earthing
  • CCR configuration
  • Output circuit
  • Intensity steps
  • Protection settings
  • Alarm condition
  • Remote control
  • Local control
  • Emergency stop
  • Monitoring
Test Record

Records Input Supply, Output Current, Intensity Steps, and Protection against required values, with actual measurements and a Pass/Fail result for each parameter.

Precedes COM-07 Series Circuit Energization Record.
COM-07 Series Circuit Energization Record Record
Purpose

Control first energization of the AGL series circuit.

Verification
  • Circuit identification
  • Isolation transformer connections
  • Fixture connections
  • Connector condition
  • Cable testing
  • Insulation resistance
  • Continuity
  • CCR connection
  • Initial current
  • Load condition
Record
  • Circuit number / CCR
  • Number of transformers
  • Number of fixtures
  • Initial current
  • Abnormal observations
  • Final result
COM-08 Functional Commissioning Record Record
Purpose

Verify that the AGL equipment performs its intended operational function.

Tests
  • Switching ON/OFF
  • Intensity control
  • Local control
  • Remote control
  • Alarm indication
  • Monitoring
  • Fail-safe operation
  • Restoration
  • Emergency operation
Result: Functional / Not functional

B · System-Specific Commissioning

5 of 25 forms
COM-09 PAPI Commissioning Record Record
Purpose

Verify operational readiness of the PAPI/APAPI system.

Verification
  • Installation
  • Position
  • Elevation
  • Alignment
  • Azimuth
  • Electrical connection
  • Intensity
  • Colour transition
  • Functional operation
  • Switching
  • Control interface
Final Status: Commissioned / Not commissioned
COM-10 Sign Commissioning Record Record
Purpose

Verify operational readiness of an illuminated airfield sign.

Verification
  • Sign identification
  • Location
  • Orientation
  • Electrical connection
  • Illumination
  • Brightness/intensity selection
  • Visibility
  • Circuit operation
  • Control operation
  • Earthing
Result: Accepted / Requires correction
COM-11 ALCMS Commissioning Record Record
Purpose

Verify operation of the Airfield Lighting Control and Monitoring System.

Tests
  • System configuration
  • PLC operation
  • HMI operation
  • Communication
  • CCR interface
  • Local control
  • Remote control
  • Alarm
  • Monitoring
  • Interlocks
  • Fail-safe operation
  • Backup
  • Restoration
Key Result: All commands and feedback should be verified end-to-end.
COM-12 Approach Lighting Commissioning Record Record
Applicable Systems
  • Approach lighting
  • Threshold lighting
  • Runway end lighting
  • Sequenced flashing lights, where applicable
  • Visual approach aids associated with the system
Verification
  • Circuit operation
  • Correct sequence
  • Intensity
  • Fixture operation
  • Control
  • Synchronization
  • Visibility
COM-13 Integrated System Test Test
Purpose

Verify that individual AGL systems operate together as an integrated airport lighting system.

Typical Interfaces
  • CCR ↔ ALCMS
  • ALCMS ↔ PLC
  • PLC ↔ HMI
  • Remote command ↔ CCR
  • CCR ↔ Series circuit
  • Circuit ↔ Fixtures
  • Alarms ↔ Monitoring
Test Sequence

Command → Communication → Control Logic → CCR Response → Circuit Energization → Fixture Response → Feedback → Alarm/Monitoring.

Result: Pass / Fail / Partial

C · Punch & Snag Management

4 of 25 forms
COM-14 Punch List List
Purpose

Record outstanding work preventing full completion.

Key Fields
  • Punch number
  • Description
  • Location
  • System
  • Category
  • Responsible party
  • Target date
  • Status
Priority: Critical / Major / Minor
COM-15 Snag List List
Purpose

Record defects, deficiencies or incomplete work identified during commissioning.

Key Fields
  • Snag ID
  • Description
  • Equipment
  • Location
  • Photograph
  • Date
  • Responsible person
  • Priority
  • Target closure date
  • Status
COM-16 Punch List Closure Closure Record
Purpose

Verify completion of punch-list items.

Closure Process

Punch Raised → Correction → Inspection → Verification → Closed.

Evidence
  • Corrective action
  • Photograph
  • Retest result
  • Inspector
  • Closure date
Closes items opened on COM-14 Punch List.
COM-17 Defect Closure Certificate Certificate
Purpose

Formally certify closure of identified defects.

Key Fields
  • Defect ID
  • Original defect
  • Root cause
  • Corrective action
  • Retest
  • Verification
  • Approved by
  • Closure date
Final Status: Closed / Not closed

D · Performance & Acceptance

3 of 25 forms
COM-18 Performance Verification Verification
Purpose

Verify that the commissioned AGL system meets approved technical and operational requirements.

Verification Areas
  • Electrical performance
  • Functional performance
  • Control performance
  • Monitoring performance
  • Optical performance
  • Reliability observations
  • Safety systems
  • Applicable compliance requirements
Evidence
  • Test reports
  • Commissioning records
  • Inspection records
  • Photometric records, where applicable
  • Control-system records
COM-19 Final Acceptance Certificate Certificate
Purpose

Confirm that the system has satisfied the defined acceptance requirements.

Acceptance Criteria
  • Installation complete
  • Testing complete
  • Commissioning complete
  • Defects closed
  • Punch items closed or formally accepted
  • Documentation complete
  • Compliance verified
Certification: Accepted / Conditionally accepted / Not accepted
COM-20 Taking-Over Certificate Certificate
Purpose

Formally record transfer of responsibility from the contractor/project organization to the client or designated operator.

Information
  • Project / scope
  • Completion date
  • System covered
  • Outstanding items
  • Warranty start
  • Taking-over date
  • Authorized signatures
Gates Division E — Handover Documentation below.

E · Handover Documentation

5 of 25 forms
COM-21 Handover Certificate Certificate
Purpose

Confirm formal delivery of the completed AGL system and required records.

Handover Items
  • Physical system
  • Documentation
  • Drawings
  • O&M manuals
  • Test records
  • Commissioning records
  • Asset records
  • Spare parts
  • Warranty documents
  • Training records
COM-22 As-Built Document Checklist Checklist
Purpose

Verify completeness and approval of final as-built documentation.

Checklist
  • Approved as-built drawings
  • Cable routes
  • Circuit diagrams
  • Equipment locations
  • CCR configuration
  • PAPI location data
  • Sign locations
  • ALCMS architecture
  • Asset identification
Status: Available / Pending / Not applicable
COM-23 O&M Document Handover Handover Record
Purpose

Control handover of operation and maintenance information.

Contents
  • O&M manuals
  • Maintenance schedules
  • Equipment manuals
  • Manufacturer documents
  • Troubleshooting guides
  • Spare-parts lists
  • Calibration requirements
  • Safety instructions
COM-24 Spare Parts Handover Handover Record
Purpose

Record transfer of contractual and recommended spare parts.

Key Fields
  • Spare ID
  • Description
  • Manufacturer
  • Part number
  • Quantity
  • Equipment compatibility
  • Warranty
  • Storage location
  • Condition
  • Handover acknowledgment
Updates Division 12 — Spare Parts Register.
COM-25 Final Project Closeout Closeout Record
Purpose

Provide final administrative and technical closure of the project.

Closeout Verification
  • Technical: installation complete, testing complete, commissioning complete, performance accepted
  • Quality: NCR closed, punch list closed, snags closed
  • Documentation: as-built complete, O&M complete, certificates issued, registers handed over
  • Commercial/contractual: deliverables completed, warranty transferred, outstanding obligations identified
  • Knowledge: lessons learned, major technical issues, failure records, improvement opportunities
Final Status: PROJECT CLOSED

How Division 07 Connects

These 25 forms build a complete and traceable chain proving the AGL system was installed, inspected, tested, made ready, safely energized, commissioned, integrated, verified, accepted, and handed over — not just proof that lights turn on.

Commissioning & Handover Flow

The five categories in this division follow the operational transition sequence from installed hardware to project closure:

INSTALLED / INSPECTED / TESTED PRE-COMMISSIONING & READINESS ENERGIZATION FUNCTIONAL & SYSTEM-SPECIFIC COMMISSIONING INTEGRATED SYSTEM TEST PUNCH & SNAG CLOSURE PERFORMANCE VERIFICATION FINAL ACCEPTANCE TAKING-OVER HANDOVER PROJECT CLOSEOUT

Related Divisions

  • Division 04 — Installation Forms (the field installation records this division's readiness certificates verify)
  • Division 05 — Inspection Forms (inspection completion gates pre-commissioning)
  • Division 06 — Testing Forms (electrical test results feed circuit and equipment readiness)
  • Division 10 — QA/QC Forms (NCR closure required for final project closeout)
  • Division 13 — Safety & Permit Forms (work permits referenced on every energization record)
  • Division 19 — ALCMS & Control System Forms (detailed control-system commissioning evidence)
  • Division 23 — Project Handover & Closeout Forms (receives the completed package via COM-25 Final Project Closeout)
  • Division 25 — Master Forms Library & Document Packages
  • Division 12 — Spare Parts Register (updated by COM-24 Spare Parts Handover)

Frequently Asked Questions

Quick answers about the 25 Division 07 Commissioning & Handover forms, how they are grouped, and how they connect to the rest of the library.

Q1What is Division 07 — Commissioning & Handover Forms in the AGL Engineering Forms & Templates library?

Division 07 is a set of 25 commissioning & handover forms (COM-01 to COM-25) in the AGL Engineering Forms & Templates library. It carries an installed, inspected and tested AGL system through readiness verification, controlled energization, functional and system-specific commissioning, integrated testing, punch and snag closure, performance verification and final acceptance into a signed-off handover package. The forms are grouped into 5 categories: Commissioning Forms, System-Specific Commissioning, Punch & Snag Management, Performance & Acceptance and Handover Documentation.

Q2Which forms are included in Commissioning Forms and System-Specific Commissioning?

Commissioning Forms (8 forms): COM-01 Pre-Commissioning Checklist, COM-02 Commissioning Checklist, COM-03 Equipment Readiness Certificate, COM-04 Circuit Readiness Certificate, COM-05 Energization Record, COM-06 CCR Energization Record, COM-07 Series Circuit Energization Record, COM-08 Functional Commissioning Record; System-Specific Commissioning (5 forms): COM-09 PAPI Commissioning Record, COM-10 Sign Commissioning Record, COM-11 ALCMS Commissioning Record, COM-12 Approach Lighting Commissioning Record, COM-13 Integrated System Test.

Q3Which forms are included in Punch & Snag Management, Performance & Acceptance and Handover Documentation?

Punch & Snag Management (4 forms): COM-14 Punch List, COM-15 Snag List, COM-16 Punch List Closure, COM-17 Defect Closure Certificate; Performance & Acceptance (3 forms): COM-18 Performance Verification, COM-19 Final Acceptance Certificate, COM-20 Taking-Over Certificate; Handover Documentation (5 forms): COM-21 Handover Certificate, COM-22 As-Built Document Checklist, COM-23 O&M Document Handover, COM-24 Spare Parts Handover, COM-25 Final Project Closeout.

Q4What is the difference between the Equipment Readiness Certificate, the Circuit Readiness Certificate and the energization records?

The Equipment Readiness Certificate (COM-03) certifies that individual equipment is ready for commissioning. The Circuit Readiness Certificate (COM-04) verifies that the complete AGL electrical circuit is ready for energization. The Energization Record (COM-05) provides controlled evidence of initial energization, and COM-06 and COM-07 control the energization of the CCR and the first energization of the series circuit.

Q5What is the difference between a Punch List and a Snag List?

The Punch List (COM-14) records outstanding work that prevents full completion. The Snag List (COM-15) records defects, deficiencies or incomplete work identified during commissioning. Closure is verified through the Punch List Closure (COM-16), and the Defect Closure Certificate (COM-17) formally certifies closure of identified defects.

Q6What is the difference between the Final Acceptance Certificate, the Taking-Over Certificate and the Handover Certificate?

The Final Acceptance Certificate (COM-19) confirms that the system has satisfied the defined acceptance requirements. The Taking-Over Certificate (COM-20) formally records the transfer of responsibility from the contractor or project organization to the client or designated operator. The Handover Certificate (COM-21) confirms formal delivery of the completed AGL system and required records, and Final Project Closeout (COM-25) provides the final administrative and technical closure.

Q7Can the forms in Division 07 be downloaded and filled in?

Yes. Each form has a Download as Word button that produces an uncontrolled sample Word template with letterhead, a document-control block, ruled entry fields and a three-tier approval table, ready to print or fill on-screen. Checklist-format forms such as Pre-Commissioning Checklist (COM-01) download with a checkbox and a verified-by line for each item. The forms can also be searched by keyword or form ID.

Q8How does Division 07 connect to installation, inspection and testing?

The earlier divisions install, inspect and test the physical AGL system. This division proves it was safely energized, that it performs its intended function individually and as an integrated system, and that every outstanding item was closed before the client or operator formally accepted delivery. Every record should trace back to an installation, inspection or test reference.

Beyond the Signature

COMMISSION THE SYSTEM. OWN THE HANDOVER.

A commissioning form captures the final sign-off — but delivering a system that performs on day one means understanding integration, interface testing and CAT I/II/III operational requirements behind every checkpoint.

Take your knowledge further with Precision AGL Academy.

Build Complete AGL Project Capability

Learn how technical AGL work connects with:

Project Planning Design Procurement Installation Testing Commissioning Safety Documentation Handover Maintenance

Develop the knowledge to not only record the work, but understand the engineering and project-management principles behind it.

Plan the project. Understand the engineering. Deliver with confidence.