Division 16 of 25 · CIR Series

Cable, Connector & Circuit Records

The 25 forms that establish complete electrical-circuit traceability for the AGL system — from cable procurement, drum and identification through route, installation, jointing, termination, connector control, testing, series-circuit topology, energization, fault history, modification, isolation, restoration and final circuit history. This is the master traceability and lifecycle-record layer for every AGL series circuit, because a single fault on one primary cable, joint, connector or transformer can affect an entire operational section. It integrates strongly with Divisions 02, 04, 06, 08, 09, 11, 12, 13 and 14.

25 / 25
Forms Scoped
CIR-01 → CIR-25
Form ID Range
9
Categories
Rev 0
Initial Issue

Where this fits — Division 16 is the electrical backbone of the AGL documentation system: cable schedule and drum register feed installation and route records, which feed jointing, termination and connector control, which feed testing and series-circuit topology, which feed energization, fault management, modification, isolation/restoration, and ultimately the master Circuit History Register — the single lifecycle record for every runway, taxiway or apron series circuit.

A · Cable Master Records

5 of 5 forms
CIR-01 Cable Schedule Schedule
Purpose

Maintains the master schedule of all AGL primary and secondary cables associated with a project or installation.

Key Fields
  • Project/Airport / drawing reference / circuit reference / cable schedule revision
  • Cable ID, cable type, size, conductor material, insulation type, voltage rating
  • Manufacturer, part number, cable drum number, cable length
  • From / to / route / circuit ID / installation date
  • Installed length / remaining length / joint and termination locations
  • Status: planned, procured, delivered, installed, tested, energized, modified, abandoned
  • Prepared by / checked by / approved by
CIR-02 Cable Drum Register Register
Purpose

Provides complete traceability of cable from delivery through installation.

Key Fields
  • Drum ID, manufacturer, cable type, size, length, batch/lot number
  • Manufacturing date, supplier, certificate reference
  • Delivery date, PO number, inspection status, drum and cable-end condition
  • Test certificate reference
  • Cable used, project/circuit, start/end location, length installed, balance length
  • Final status: fully used / partially used / returned / damaged / rejected
CIR-03 Cable Identification Record Record
Purpose

Establishes unique identification of every installed cable.

Key Fields
  • Cable ID / circuit ID / cable type / size
  • From / to / route / drum ID / installation date
  • Cable marker, cable tag, phase/polarity where applicable
  • Circuit number and directional identification
  • Identification installed / drawing updated / cable correctly traced
Feeds CIR-13 Circuit Identification.
CIR-04 Cable Laying Record Record
Purpose

Documents actual installation of AGL cable.

Key Fields
  • Cable ID, drum ID, circuit, route, start point, end point, date, installation team
  • Trench/duct readiness, cable handling, minimum bending radius, pulling method
  • Cable protection, separation requirements, route condition
  • Warning/identification system
  • Planned length vs actual length, installation status, remarks
Feeds CIR-05 Cable Route Record.
CIR-05 Cable Route Record Record
Purpose

Establishes the physical route and location of each cable.

Key Fields
  • Cable ID / circuit ID / start / intermediate points / end
  • Duct/trench, crossing points, manholes/pits, base cans, joint locations
  • Drawing reference, as-built reference, GPS/coordinate information
  • Route photographs and revision
  • Route verified / requires correction
Feeds the as-built drawing and asset/cable database.

B · Cable Joints & Terminations

2 of 2 forms
CIR-06 Cable Joint Record Record
Purpose

Documents every cable joint installed on the AGL circuit.

Key Fields
  • Joint ID, cable ID, circuit ID, location, joint type
  • Manufacturer, kit/model, batch/lot number
  • Date, technician, jointing procedure, environmental conditions
  • Cable preparation and connection method
  • Joint condition, sealing, mechanical protection, identification, torque
  • Continuity, insulation resistance and other applicable tests
  • Accepted / rejected
Feeds CIR-08 Cable Test Record.
CIR-07 Cable Termination Record Record
Purpose

Documents termination of cables at equipment or circuit endpoints.

Key Fields
  • Cable ID, circuit ID, from, to, equipment, terminal/connector, termination method
  • Cable identification, polarity, connection, torque
  • Insulation, mechanical security, environmental sealing
  • Continuity, insulation resistance, functional test
  • Installer / inspector / QA-QC approval

C · Cable Testing

3 of 3 forms
CIR-08 Cable Test Record Test Record
Purpose

Provides the master record of electrical tests performed on installed cables.

Key Fields
  • Cable ID, circuit ID, cable size, length, from/to, test date
  • Test equipment ID, calibration status, operator
  • Insulation resistance, continuity, earth/ground-related tests
  • Test voltage, test duration, measured result, acceptance criterion, pass/fail
  • Test procedure and test report number
Feeds CIR-09 Cable Insulation Record and CIR-10 Cable Continuity Record.
CIR-09 Cable Insulation Record Test Record
Purpose

Records insulation-resistance measurements for cable sections and series circuits.

Key Fields
  • Cable ID, circuit ID, test section, test voltage, test duration
  • Instrument ID, temperature/environmental conditions
  • Measured insulation resistance vs minimum acceptance requirement
  • Pass/fail and remarks
  • Trend: previous value → current value → change → trend
CIR-10 Cable Continuity Record Test Record
Purpose

Confirms electrical continuity of installed cable conductors and circuit paths.

Key Fields
  • Cable ID, circuit ID, from, to, test method, instrument ID
  • Expected continuity vs measured condition
  • Polarity where applicable, connection condition
  • Pass/fail

D · Series Circuit Records

3 of 3 forms
CIR-11 Series Circuit Record Master Record
Purpose

Establishes the complete topology of an AGL series circuit — one of the most important records in this division.

Key Fields
  • Circuit ID, CCR ID, runway/taxiway/system, circuit length
  • Cable type/size, number of transformers, number of fixtures
  • CCR, primary cable, isolating transformers, connectors, fixtures, joints
  • Return/earth arrangements as applicable
  • Circuit sequence: CCR → cable → transformer → fixture → transformer → fixture …
  • Component sequence, component ID, location, status
Feeds CIR-25 Circuit History Register.
CIR-12 Circuit Schedule Schedule
Purpose

Maintains the master operational schedule of AGL circuits.

Key Fields
  • Circuit ID, system, runway/taxiway, CCR ID, circuit rating
  • Number of fixtures, number of transformers, cable length
  • Normal operating condition, intensity steps
  • Status: operational, isolated, under maintenance, faulted, out of service
CIR-13 Circuit Identification Verification Record
Purpose

Verifies physical identification of every AGL circuit.

Key Fields
  • Circuit ID, CCR identification, cable identification
  • Equipment identification, transformer identification, fixture identification
  • Circuit direction
  • Labels installed / labels legible / drawing matches field
  • Circuit correctly identified

E · Circuit Operation & Faults

2 of 2 forms
CIR-14 Circuit Energization Record Record
Purpose

Records every controlled energization of an AGL circuit after installation, maintenance, isolation or testing.

Key Fields
  • Circuit ID, CCR ID, isolation status, cable/insulation test completed, continuity verified
  • Equipment connected, safety clearance obtained, permit/LOTO clearance completed
  • Date/time, CCR setting, initial current/voltage, load condition, number of operating fixtures
  • Result: normal / abnormal
  • Authorized by / performed by / witnessed by
Directly linked with Division 13 — Safety & Permit Forms.
CIR-15 Circuit Fault Record Record
Purpose

Records faults occurring on AGL circuits.

Key Fields
  • Fault ID, circuit ID, date/time, location, operational condition, CCR alarm, symptoms
  • Fault type: open circuit, earth fault, insulation deterioration, short circuit, connector fault, transformer fault, fixture fault, cable damage, intermittent fault
  • Initial measurements, fault location, test equipment, investigation reference
  • Temporary restoration, repair, replacement, retest
Feeds CIR-25 Circuit History Register and Division 09 failure investigation.

F · Connector Control

5 of 5 forms
CIR-16 Connector Installation Record
Purpose

Documents installation of AGL connectors, including applicable L-823-type connector assemblies.

Key Fields
  • Connector ID, connector type, manufacturer, model, part number
  • Cable ID, transformer/fixture ID
  • Date, installer, connection method, environmental sealing, mechanical protection
  • Correct connector, correct cable, correct connection, physical condition, identification
Feeds CIR-17 Connector Torque Record.
CIR-17 Connector Torque Record Verification Record
Purpose

Documents controlled torque application where the connector/connection design requires torque control.

Key Fields
  • Connector ID, equipment, connection point
  • Required torque vs applied torque, torque tool ID, calibration status
  • Date, technician
  • Result: within requirement / not acceptable
CIR-18 Connector Inspection Inspection Record
Purpose

Inspects installed connectors for physical and electrical condition.

Key Fields
  • Connector body, contact condition, cable interface, sealing
  • Mechanical security, contamination, moisture, damage, identification
  • Continuity and insulation-related checks where applicable
  • Classification: good / attention required / defective / replace
CIR-19 Connector Replacement Record
Purpose

Documents replacement of defective connectors.

Key Fields
  • Existing connector ID, cable ID, circuit, failure reason, condition
  • New connector ID, manufacturer, model, batch/lot, installation date, installer
  • Continuity, insulation, functional circuit test
  • Replacement accepted / retest required
Feeds CIR-20 Connector Failure Record.
CIR-20 Connector Failure Record Failure Record
Purpose

Establishes a failure history for connectors.

Key Fields
  • Failure ID, connector ID, circuit, location, date, symptoms
  • Failure type: open connection, poor contact, insulation failure, moisture ingress, mechanical damage, overheating, incorrect installation, corrosion, other
  • RCA reference: fault investigation, 5-Why, fishbone, corrective action

G · Circuit Modification & Extension

2 of 2 forms
CIR-21 Circuit Modification Record Record
Purpose

Documents any approved modification to an existing AGL circuit.

Key Fields
  • Circuit ID, existing configuration, drawing reference, reason for modification
  • Components affected: cable, transformer, fixture, connector changes
  • Design review, approval, risk assessment, method statement
  • Continuity, insulation resistance, functional testing, photometry where applicable
  • As-built drawing / circuit schedule / asset register updated
CIR-22 Circuit Extension Record Record
Purpose

Documents extension of an existing circuit.

Key Fields
  • Circuit ID, existing length, existing load, existing fixtures
  • New cable, new fixtures, new transformers, new connectors, new joints
  • Load, voltage/current, circuit capability, CCR capability, insulation, continuity
  • Extension accepted / rejected

H · Circuit Isolation & Restoration

2 of 2 forms
CIR-23 Circuit Isolation Record Record
Purpose

Establishes controlled isolation of an AGL circuit before maintenance, modification or emergency work.

Key Fields
  • Circuit ID, CCR, location, reason for isolation
  • Date/time, CCR isolated, electrical isolation completed, LOTO reference
  • Isolation verification, warning/identification
  • Zero-energy verification, test-before-touch requirements completed, work permit reference
  • Authorized by / isolated by / verified by
Directly linked with Division 13 — Safety & Permit Forms.
CIR-24 Circuit Restoration Record Record
Purpose

Documents safe return of an isolated circuit to service.

Key Fields
  • Work completed, tools removed, personnel clear, covers/guards restored
  • Connections checked, testing completed, defects closed
  • Continuity, insulation resistance, circuit condition, equipment connections
  • CCR energized, current recorded, voltage recorded, fixture operation verified
  • Restored to service / not restored
  • Technician / engineer / operations-ATC coordination where applicable

I · Master Circuit History

1 of 1 forms
CIR-25 Circuit History Register Master Register
Purpose

The master historical record of every AGL series circuit.

Key Fields
  • Circuit ID, airport, runway/taxiway, system, CCR ID
  • Original installation date, circuit length, number of fixtures/transformers, cable type/size
  • Lifecycle history: installation, testing, energization, maintenance, faults, repairs, connector replacements, cable joints, modifications, extensions, isolation events, restorations, photometric tests
  • Reliability information: number of failures, failure frequency, MTBF, MTTR, repeated faults, insulation-resistance trend, major modifications
  • Current status: operational, degraded, under maintenance, isolated, out of service, decommissioned

How Division 16 Connects

These 25 forms build one-to-one traceability at cable, connector and circuit level — from procurement to final decommissioning — so that virtually every AGL failure, maintenance event, commissioning activity and performance issue can be traced back to a specific circuit, cable, joint, connector, transformer or fixture location.

Division 16 Control Flow

The nine categories in this division follow the electrical lifecycle from procurement to decommissioning:

PROCUREMENT INSTALLATION TESTING COMMISSIONING OPERATION FAILURE RESTORATION LIFECYCLE

Related Divisions

  • Division 02 — Design & Engineering Forms (circuit and cable calculations every schedule traces back to)
  • Division 04 — Installation Forms (field cable, base can, fixture and transformer installation records)
  • Division 06 — Testing & Commissioning Forms (shares insulation, continuity and functional test data)
  • Division 08 / 09 — Maintenance & Failure Investigation (fault, RCA and connector failure history)
  • Division 11 — Asset Management (circuit master record and condition/status tracking)
  • Division 12 / 14 — Photometry & Measurement Traceability (linked test and calibration references)
  • Division 13 — Safety & Permit Forms (isolation, LOTO and energization clearance)

Frequently Asked Questions

Quick answers about the 25 Division 16 Cable, Connector & Electrical Circuit forms, how they are grouped, and how they connect to the rest of the library.

Q1What is Division 16 — Cable, Connector & Electrical Circuit Records in the AGL Engineering Forms & Templates library?

Division 16 is a set of 25 cable, connector & electrical circuit records (CIR-01 to CIR-25) in the AGL Engineering Forms & Templates library. It establishes complete electrical-circuit traceability for the AGL system, from cable procurement, drum and identification through route, installation, jointing, termination, connector control, testing, series-circuit topology, energization, faults, modification, isolation, restoration and final circuit history. The forms are grouped into 9 categories: Cable Master Records, Cable Joints & Terminations, Cable Testing, Series Circuit Records, Circuit Operation & Faults, Connector Control, Circuit Modification & Extension, Circuit Isolation & Restoration and Master Circuit History.

Q2Which forms are included in Cable Master Records, Cable Joints & Terminations and Cable Testing?

Cable Master Records (5 forms): CIR-01 Cable Schedule, CIR-02 Cable Drum Register, CIR-03 Cable Identification Record, CIR-04 Cable Laying Record, CIR-05 Cable Route Record; Cable Joints & Terminations (2 forms): CIR-06 Cable Joint Record, CIR-07 Cable Termination Record; Cable Testing (3 forms): CIR-08 Cable Test Record, CIR-09 Cable Insulation Record, CIR-10 Cable Continuity Record.

Q3Which forms are included in Series Circuit Records, Circuit Operation & Faults and Connector Control?

Series Circuit Records (3 forms): CIR-11 Series Circuit Record, CIR-12 Circuit Schedule, CIR-13 Circuit Identification; Circuit Operation & Faults (2 forms): CIR-14 Circuit Energization Record, CIR-15 Circuit Fault Record; Connector Control (5 forms): CIR-16 Connector Installation, CIR-17 Connector Torque Record, CIR-18 Connector Inspection, CIR-19 Connector Replacement, CIR-20 Connector Failure Record.

Q4Which forms are included in Circuit Modification & Extension, Circuit Isolation & Restoration and Master Circuit History?

Circuit Modification & Extension (2 forms): CIR-21 Circuit Modification Record, CIR-22 Circuit Extension Record; Circuit Isolation & Restoration (2 forms): CIR-23 Circuit Isolation Record, CIR-24 Circuit Restoration Record; Master Circuit History (1 form): CIR-25 Circuit History Register.

Q5What is the Series Circuit Record and the Circuit History Register?

The Series Circuit Record (CIR-11) establishes the complete topology of an AGL series circuit and is described on the page as one of the most important records in the division. The Circuit History Register (CIR-25) is the master historical record of every AGL series circuit.

Q6What is the difference between the Cable Schedule, Cable Drum Register, Cable Identification, Cable Laying and Cable Route records?

The Cable Schedule (CIR-01) is the master schedule of primary and secondary cables. The Cable Drum Register (CIR-02) gives traceability from delivery through installation, and the Cable Identification Record (CIR-03) establishes unique identification of each installed cable. The Cable Laying Record (CIR-04) documents actual installation, and the Cable Route Record (CIR-05) establishes each cable's physical route and location.

Q7Which forms control circuit isolation, restoration and energization?

The Circuit Isolation Record (CIR-23) establishes controlled isolation of a circuit before maintenance, modification or emergency work, and the Circuit Restoration Record (CIR-24) documents its safe return to service. The Circuit Energization Record (CIR-14) records every controlled energization after installation, maintenance, isolation or testing.

Q8Can the forms in Division 16 be downloaded and filled in?

Yes. Each form has a Download as Word button that produces an uncontrolled sample Word template with letterhead, a document-control block, ruled entry fields and a three-tier approval table, ready to print or fill on-screen. The forms can also be searched by keyword or form ID.

Q9How does Division 16 connect to the rest of the AGL documentation system?

Division 16 is the electrical backbone of the documentation system. The cable schedule and drum register feed installation and route records, which feed jointing, termination and connector control, then testing and series-circuit topology, then energization, fault management, modification and isolation records. It lets virtually every failure, maintenance event and commissioning activity be traced back to a specific circuit, cable, joint, connector, transformer or fixture location.

Beyond the Cable Schedule

RECORD THE CIRCUIT. UNDERSTAND THE ARCHITECTURE.

A cable and connector record tells you what's connected — but real competence means understanding series-circuit architecture, loop resistance, L-823 connector integrity and how a single bad joint can take down an entire circuit.

Take your knowledge further with Precision AGL Academy.

Build Complete AGL Project Capability

Learn how technical AGL work connects with:

Project Planning Design Procurement Installation Testing Commissioning Safety Documentation Handover Maintenance

Develop the knowledge to not only record the work, but understand the engineering and project-management principles behind it.

Plan the project. Understand the engineering. Deliver with confidence.