Division 16 · EBM · Protective-Electrical Integrity

Earthing & Bonding Maintenance

The protective-electrical-integrity backbone of the handbook. This division maintains a reliable low-impedance path for fault current, equipment bonding, electrical safety, lightning-related currents, and surge protection — keeping AGL equipment and personnel protected.

Core principle: earthing provides the path — bonding connects the assets — surge protection limits transient overvoltage.

Philosophy: a visually intact earth conductor does not automatically mean the earthing system is electrically satisfactory. The maintenance program combines visual, mechanical, and connection inspection with continuity and earth-resistance verification before any corrective action is closed out.

31
Topics in Division
04
Asset Groups (A–D)
05
Condition Classes
08
Step Core Principle

EBM Philosophy

Every earthing and bonding maintenance task in this division follows the same underlying sequence, regardless of asset type.

Visual Inspection
Mechanical Inspection
Connection Inspection
Continuity Verification
Earth-Resistance Verification
Corrective Action
Retest
Record
Earthing — connection to the earth electrode/system Bonding — continuity between conductive equipment/structures Lightning Protection — controlled path for lightning current Surge Protection — limits transient overvoltage

Earthing Condition Classification

A generic five-class condition scale for the earthing and bonding system.

ConditionDescriptionAction
GoodEarth / bonding system intactRoutine PM
AcceptableMinor deterioration with no significant impactMonitor
DeterioratingDeveloping corrosion / mechanical issuePlanned maintenance
DefectiveContinuity or physical integrity compromisedCorrective maintenance
CriticalMajor loss of protective path or significant lightning/surge concernPriority / emergency response

Maintenance Decision Matrix

The standard finding-to-action mapping used across the earthing and bonding system.

FindingTypical Maintenance Action
Dirty earth pitClean
Damaged pit coverRepair / replace
Loose earth terminalTighten
Corroded connectionClean / treat / replace
Damaged earth conductorRepair / replace
Damaged earth clampReplace
Earth continuity failureLocate and correct
Abnormal earth resistanceInvestigate and correct
Loose bonding connectionTighten
Damaged bonding conductorReplace
Missing bonding connectionRestore
Damaged lightning conductorRepair / replace
Failed SPDReplace
Lightning-event damageInspect / test / restore
Corroded bonding connectionTreat / replace
Damaged cable-tray bondingRestore

The 31 Topics

Grouped by protective system — click any topic to expand its inspection points and acceptance condition.

A

Earthing System

10 topics
MNT-EBM-001Earth Electrode Inspection
Inspect Accessible Electrode For
  • Physical damage
  • Corrosion
  • Loose connections
  • Mechanical deterioration
  • Evidence of disturbance
  • Condition of associated conductor
Acceptance / Record

Where not accessible: inspect the accessible connection and associated earth-pit arrangement instead.

MNT-EBM-002Earth Pit Cleaning
Keep Free From
  • Excessive dirt
  • Debris
  • Foreign material
  • Standing water where drainage is required
  • Obstructions to inspection
Acceptance / Record

Objective: cleaning should allow safe access to the earth connection.

MNT-EBM-003Earth Pit Restoration
Check
  • Cover condition
  • Accessibility
  • Structural condition
  • Drainage
  • Identification
  • Protection of earth connections
Acceptance / Record

Outcome: the restored pit should permit future inspection and testing.

MNT-EBM-004Earth Conductor Inspection
Inspect For
  • Physical damage
  • Corrosion
  • Broken strands
  • Loose connections
  • Poor routing
  • Mechanical stress
  • Inadequate protection
Acceptance / Record

Focus: particular attention should be given to exposed portions.

MNT-EBM-005Earth Conductor Replacement
After Replacement
  • Verify connections
  • Verify mechanical security
  • Verify continuity
  • Complete applicable earth testing
Acceptance / Record

Standard: replace damaged or severely deteriorated conductors using the approved conductor specification.

MNT-EBM-006Earth Connection Cleaning
Perform
  • Clean accessible earth connections where contamination or corrosion is present
  • Inspect the connection after cleaning
Acceptance / Record

Determine: whether the connection remains serviceable after cleaning.

MNT-EBM-007Earth Terminal Tightening
Particular Attention
  • CCR earth terminals
  • Panel earth terminals
  • Transformer earth connections
  • Sign earth connections
  • Structural bonding terminals
Acceptance / Record

Standard: use the applicable manufacturer / installation requirements for tightening.

MNT-EBM-008Earth Clamp Inspection
Inspect For
  • Corrosion
  • Looseness
  • Mechanical damage
  • Poor contact
  • Deterioration
Risk / Attention

Defective clamps should be repaired or replaced.

MNT-EBM-009Earth Corrosion Treatment
Sequence
  • Assess severity
  • Clean / treat where appropriate
  • Inspect remaining material
  • Replace severely deteriorated components
  • Restore connection integrity
  • Perform electrical verification
MNT-EBM-010Earth Connection Continuity Check
Record
  • Equipment
  • Earth point
  • Test date
  • Test instrument
  • Result
  • Acceptance criterion
  • Technician
Acceptance / Record

Objective: confirm that the intended earth connection remains electrically continuous.

B

Equipment Bonding

10 topics
MNT-EBM-011Fixture Bonding Inspection
Inspect
  • Bonding conductor condition
  • Connection security
  • Corrosion
  • Mechanical damage
  • Continuity
Acceptance / Record

Where bonding is by equipment design: verify it remains intact after maintenance.

MNT-EBM-012Base-Can Bonding Inspection
Check
  • Bonding conductor
  • Connection
  • Corrosion
  • Mechanical integrity
  • Continuity
Risk / Attention

Focus: particular attention after civil or fixture replacement work.

MNT-EBM-013Transformer Bonding Inspection
Inspect
  • Conductor condition
  • Terminal condition
  • Connection security
  • Corrosion
  • Continuity
MNT-EBM-014Sign Bonding Inspection
Check
  • Bonding conductor
  • Connection
  • Mechanical security
  • Corrosion
  • Continuity
MNT-EBM-015CCR Bonding Inspection
Inspect
  • Earth terminal condition
  • Bonding conductor
  • Cabinet connection
  • Corrosion
  • Mechanical security
  • Continuity
MNT-EBM-016Panel Bonding Inspection
Inspect
  • Earth / bonding conductors
  • Door bonding where applicable
  • Panel bonding
  • Terminal security
  • Corrosion
MNT-EBM-017Cable-Tray Bonding Where Applicable
Inspect
  • Bonding jumpers
  • Connections
  • Continuity
  • Corrosion
  • Mechanical integrity
Acceptance / Record

Applies: where metallic cable trays are used and bonding is required.

MNT-EBM-018Structural Bonding Inspection
Look For
  • Missing bonding conductors
  • Loose connections
  • Corrosion
  • Mechanical damage
  • Discontinuity
MNT-EBM-019Bonding Conductor Replacement
After Replacement
  • Secure the conductor
  • Verify connections
  • Check routing
  • Verify continuity
MNT-EBM-020Bonding Connection Tightening
Where Tightening Is Required
  • Use the approved tightening requirement
  • Avoid damaging terminals
  • Verify continuity after maintenance where applicable
C

Lightning / Surge Protection

6 topics
MNT-EBM-021Lightning Protection Inspection
Inspect For
  • Physical damage
  • Corrosion
  • Loose connections
  • Discontinuity
  • Damaged conductors
  • Mechanical deterioration
  • Counterpoise conductor and its connections, where installed
MNT-EBM-022Lightning Conductor Inspection
Inspect For
  • Physical damage
  • Corrosion
  • Loose connections
  • Mechanical displacement
  • Damaged supports
MNT-EBM-023SPD Condition Inspection
Inspect For
  • Physical damage
  • Status indication
  • Abnormal condition
  • Loose connections
  • Signs of thermal stress
Acceptance / Record

Where fitted: verify the SPD's visual status indicator condition.

MNT-EBM-024SPD Replacement
Verify
  • Correct device
  • Correct rating
  • Correct connection
  • Correct installation
  • Status indication
Risk / Attention

Replace when: the status indication or condition shows failure or end of life, or when inspection / testing after a surge or lightning event shows the device is degraded.

MNT-EBM-025Surge Protection Connection Inspection
Inspect For
  • Loose terminals
  • Damaged conductors
  • Incorrect connections
  • Corrosion
  • Physical damage
MNT-EBM-026Post-Lightning-Event Earthing Inspection
Inspect
  • Earth conductors
  • Earth connections
  • Bonding conductors
  • Lightning conductors
  • Counterpoise conductor, where installed
  • SPDs
  • Associated electrical equipment
Risk / Attention

Look for: both visible damage and abnormal electrical / test conditions.

D

Testing

5 topics
MNT-EBM-027Earth Resistance Verification
Record
  • Earth point
  • Test method
  • Test instrument
  • Test date
  • Measured value
  • Applicable acceptance criterion
  • Environmental conditions where relevant
Risk / Attention

Important: acceptance limits should come from the applicable project specification, airport standard, equipment requirement, or governing standard — not from an arbitrary universal value. Safety: apply the site isolation / permit procedure before disconnecting any earth link for testing, and do not carry out earth testing or work on lightning-protection conductors during thunderstorm activity.

MNT-EBM-028Earth Continuity Verification
Verify
  • Continuity of applicable earth conductors
  • Continuity of applicable connections
Acceptance / Record

Objective: confirm the intended conductive path has not been interrupted.

MNT-EBM-029Bonding Continuity Verification
Particularly Important After
  • Equipment replacement
  • Fixture replacement
  • Sign replacement
  • Panel work
  • Transformer work
  • Civil work
  • Cable-tray modification
MNT-EBM-030Corrective Action After Failed Earth Test
Investigation Covers
  • Test setup and instrument verification
  • Repeat / confirm test
  • Earth connection and conductor inspection
  • Electrode / pit and bonding-path inspection
  • Cause identification and defect correction
  • Retest and record
Risk / Attention

Trigger: a failed or abnormal earth test should initiate a controlled investigation — see the full sequence below.

MNT-EBM-031Earthing Maintenance Record
Should Include
  • Asset info, airport, location, equipment
  • Earth point ID, bonding point ID
  • Inspection: electrode, pit, conductor, clamp, terminal, bonding
  • Testing: type, instrument, method, result, criterion
  • Maintenance: cleaning, tightening, repair, replacement, corrosion treatment
  • Closure: retest result, final condition, technician, supervisor, date, work-order, remarks

Corrective Action After Failed Earth Test

The controlled investigation sequence triggered by an abnormal or failed earth test result.

1
Abnormal Result

Failed or unexpected earth-test value.

2
Verify Setup

Confirm the test was correctly configured.

3
Verify Instrument

Confirm calibration and correct operation.

4
Repeat Test

Confirm the result is genuine.

5
Inspect Connection

Check the earth connection point.

6
Inspect Conductor

Check for damage or corrosion.

7
Inspect Electrode/Pit

Check the earth electrode and pit.

8
Inspect Bonding Path

Check the associated bonding path.

9
Identify Cause

Determine the root cause of the deviation.

10
Correct Defect

Repair, clean, treat, or replace as required.

11
Repeat Test

Confirm the correction restored acceptable values.

12
Record Result

Close out with the final measured value.

Special Inspection Triggers & Post-Maintenance Verification

Earthing and bonding work does not stand alone — it should be triggered by wider events and verified after other maintenance disturbs it.

Special Inspection Triggers

  • Lightning event
  • Major electrical fault
  • Flooding
  • Civil works
  • Cable, fixture, sign, or transformer replacement
  • CCR maintenance or panel modification
  • Earthing-test failure or repeated equipment failures

Post-Maintenance Verification

  • Connection security
  • Conductor condition
  • Mechanical protection
  • Corrosion treatment
  • Earth continuity and bonding continuity
  • Earth resistance
  • SPD condition and lightning-protection condition

Why it matters: maintenance work elsewhere on the asset can unintentionally disturb an otherwise satisfactory bonding path — the exact testing requirement should correspond to the work performed.

The Protection Chain

Division 16 reduces to a single protective chain, reinforced by lightning and surge protection.

Electrical Equipment
Bonding
Earth Conductor
Earth Electrode / System
Lightning Protection Surge Protection

Frequently Asked Questions

Quick answers about earthing & bonding maintenance, based on the topics in this division.

8 QUESTIONS
Q1What is earthing and bonding maintenance in the AGL Maintenance Handbook?

It is the protective-electrical-integrity division, maintaining a reliable low-impedance path for fault current, equipment bonding, electrical safety and lightning-related currents. In short, earthing provides the path, bonding connects the assets and surge protection limits transient overvoltage.

Q2What does Division 16 of the AGL Maintenance Handbook cover?

Division 16 (Earthing & Bonding Maintenance) contains 31 topics in four groups: Group A Earthing System (10 topics), Group B Equipment Bonding (10 topics), Group C Lightning / Surge Protection (6 topics) and Group D Testing (5 topics).

Q3Does a visually intact earth conductor mean the earthing system is satisfactory?

No. A visually intact conductor is not automatically electrically satisfactory, so the maintenance sequence goes beyond inspection to continuity verification and earth-resistance verification.

Q4What is the earthing and bonding maintenance sequence?

Visual Inspection, Mechanical Inspection, Connection Inspection, Continuity Verification, Earth-Resistance Verification, Corrective Action, Retest and Record.

Q5What should be done after a failed or abnormal earth test?

A controlled twelve-step investigation: verify the test setup and the instrument, repeat the test to confirm the result, inspect the connection, conductor, electrode and pit and the bonding path, identify the cause, correct the defect, repeat the test to confirm acceptable values, and record the final measured value.

Q6What events should trigger a special earthing inspection?

A lightning event, a major electrical fault, flooding, civil works, replacement of a cable, fixture, sign or transformer, and CCR maintenance or panel modification. Earthing and bonding should also be verified after other maintenance disturbs it.

Q7How are earthing conditions classified?

Five classes: Good (routine PM), Acceptable (monitor), Deteriorating (planned maintenance), Defective (continuity or physical integrity compromised, corrective maintenance) and Critical (major loss of the protective path or a significant lightning or surge concern, priority or emergency response).

Q8What does the earthing and bonding decision matrix recommend?

A loose earth terminal or bonding connection is tightened, a corroded connection is cleaned, treated or replaced, an earth continuity failure is located and corrected, abnormal earth resistance is investigated and corrected, a failed SPD is replaced, and lightning-event damage is inspected, tested and restored.

Go Further

Don't Just Test the Earth. Understand the Protection It Provides.

Earthing and bonding maintenance is more than an annual resistance reading.

Build the technical knowledge to understand fault current paths, bonding continuity, soil resistivity effects, and how a degraded earth system compromises personnel and equipment safety.

Maintain the earth. Protect the fault path. Understand the risk.