The core electrical-testing division of the AGL Testing & Commissioning Manual. Division 02 verifies the electrical integrity, continuity, insulation, resistance, polarity, voltage, current, power, circuit connections, transformer circuits, connectors, control circuits, and auxiliary supplies of the installed AGL system — before any functional or system-level commissioning begins.
Sequence: Prepare → Isolate → Verify Safe → Test → Record → Evaluate → Accept/Reject → Report. Test methods, test voltages, permissible limits, discharge requirements, and acceptance values are always taken from the applicable project specification, approved test procedure, equipment manufacturer requirements, and applicable standards — this division defines the testing scope, not the numerical acceptance limits.
Every topic in this division follows the same underlying sequence, whatever the circuit or equipment under test — and every result is carried through to a formal evaluation and acceptance decision, never accepted on the strength of a recorded number alone.
Division 02 is worked as a staged sequence rather than a single pass — each group below builds on the one before it, and the division closes only once evaluation and acceptance are complete.
| Group | What It Confirms |
|---|---|
| A — Insulation & Continuity | Cable and equipment insulation is intact, and the intended electrical path exists without an unintended open circuit |
| B — Earthing | The installed earthing system, earth electrodes, and protective bonding paths meet resistance and continuity requirements |
| C — Polarity & Resistance | Connections are correctly oriented, and circuit/cable resistance is consistent with design expectations |
| D — Electrical Measurements | Required supply voltage, current, power, and phase configuration are present and correct at specified test points |
| E — Cable & Termination Testing | Installed cables, joints, and terminations are electrically and mechanically sound |
| F — Circuit & Equipment Verification | Primary and secondary circuits, transformers, and connectors are electrically verified before energization |
| G — Control & Auxiliary | Control circuits and auxiliary supplies are electrically sound ahead of functional testing |
| H — Evaluation, Acceptance & Reporting | Every result is evaluated against an approved criterion, formally accepted or rejected, and traceable to a test report |
Two requirement groups should be closed out before the Division 02 team starts working through the topic list.
Grouped by test focus, in the order the division is normally worked — click any topic to expand its verification checks and acceptance criteria.
Acceptance Criteria: measured insulation resistance meets the value specified in the project specification/approved test procedure, with the circuit safely discharged and restored only after confirming safe conditions.
Acceptance Criteria: result is recorded as continuity satisfactory for every test point; any "not satisfactory" result is investigated and corrected before proceeding.
Acceptance Criteria: measured earth resistance meets the project acceptance criterion. Earth resistance and earth continuity are also revisited under the dedicated Earthing & Bonding Testing division.
Acceptance Criteria: protective earth and bonding paths are confirmed electrically continuous at every typical point, with no broken or loose bonding conductor outstanding.
Acceptance Criteria: measured cable resistance is consistent with calculated/design resistance and manufacturer data, with any significant deviation investigated and closed out.
Acceptance Criteria: measured voltage at every specified test point is within the nominal/design range, recorded with instrument ID and operating condition.
Acceptance Criteria: measured current is consistent with expected current and stable across operating conditions. Detailed CCR output-current and regulation testing is addressed subsequently under CCR Testing & Commissioning.
Acceptance Criteria: measured power, and power factor/frequency where applicable, is consistent with the applicable design and equipment requirements.
Acceptance Criteria: phase sequence, identification, and connection are confirmed correct at every applicable AC supply point.
Acceptance Criteria: measured insulation resistance for each installed AGL cable meets the applicable acceptance value, with discharge completed after every test.
Acceptance Criteria: every cable joint present is uniquely identified, tests satisfactory for continuity and insulation, and is mechanically sound and sealed.
Acceptance Criteria: every secondary-side component — transformer secondary, secondary cable, connector, and fixture — is confirmed continuous, correctly connected, and free of open or short circuits.
Acceptance Criteria: the electrical test requirement for each isolation transformer is satisfied here; the dedicated Division 04 — Isolation Transformer Testing & Commissioning provides the full transformer testing and commissioning procedure.
Acceptance Criteria: every connector in the circuit is correctly identified, mated, locked, and continuous; connector testing is later expanded to identification, continuity, contact, mating, locking, sealing, cable-lead, and electrical verification.
Acceptance Criteria: control-circuit electrical integrity is confirmed here; whether the control system actually performs the required operational sequence is verified later under the ALCMS and System Integration divisions.
Acceptance Criteria: every auxiliary and project-specific supply feeding control and supporting equipment is confirmed correct for voltage, continuity, protection, and earthing.
Acceptance Criteria: every electrical test is traceable to a formal test record following the recommended report structure, complete with acceptance sign-off before the division closes.
Division 02 sits between installation readiness and the specialized commissioning divisions — no result proceeds forward without evaluation, and no division closes without acceptance.
Installation readiness verified and energization authorized.
Division 02 confirms insulation, continuity, resistance, polarity, voltage, current, power, and circuit connections.
Division 03 builds on verified electrical integrity for CCR-specific testing.
Division 04 provides the dedicated transformer testing and commissioning procedure.
Division 05 onward proceeds into fixture, runway, taxiway, control, and photometric commissioning.
Every result passes through the evaluation sequence before any PASS is recorded.
Failed or abnormal results are corrected and retested before proceeding.
The Master Electrical Test Report closes the division and hands the system forward.
Quick answers about Division 02 — Electrical Testing in the AGL Testing & Commissioning Manual.
Division 02 of the AGL Testing & Commissioning Manual covers Electrical Testing. It is the core electrical-testing division of the AGL Testing & Commissioning Manual. Division 02 verifies the electrical integrity, continuity, insulation, resistance, polarity, voltage, current, power, circuit connections, transformer circuits, connectors, control circuits, and auxiliary supplies of the installed AGL system — before any functional or system-level commissioning begins. It contains 23 topics (TC-ELE-001 to TC-ELE-023) organised into 8 groups (A–H), each topic with its own verification checks.
Prepare → Isolate → Verify Safe → Test → Record → Evaluate → Accept/Reject → Report. Test methods, test voltages, permissible limits, discharge requirements, and acceptance values are always taken from the applicable project specification, approved test procedure, equipment manufacturer requirements, and applicable standards — this division defines the testing scope, not the numerical acceptance limits.
Every topic in this division follows the same underlying sequence, whatever the circuit or equipment under test — and every result is carried through to a formal evaluation and acceptance decision, never accepted on the strength of a recorded number alone. Steps: Prepare → Isolate → Verify Safe → Test → Record → Evaluate → Accept/Reject → Report. Focus areas: Primary circuit integrity; Secondary & transformer integrity; Control & auxiliary integrity; Result evaluation & acceptance.
Division 02 has 23 topics in 8 groups. A — Insulation & Continuity: Insulation Resistance Testing, Continuity Testing. B — Earthing: Earth Resistance Testing, Earth Continuity Testing. C — Polarity & Resistance: Polarity Verification, Circuit Resistance Measurement, Cable Resistance Measurement. D — Electrical Measurements: Voltage Measurement, Current Measurement, Power Measurement, Phase Verification Where Applicable. E — Cable & Termination Testing: Cable Insulation Testing, Cable Joint Testing, Cable Termination Testing. F — Circuit & Equipment Verification: Secondary Circuit Verification, Primary Circuit Verification, Transformer Electrical Testing, Connector Continuity Verification. G — Control & Auxiliary: Control-Circuit Testing, Auxiliary-Supply Testing. H — Evaluation, Acceptance & Reporting: Electrical Test-Result Evaluation, Electrical Acceptance Assessment, Electrical Test Report Preparation.
Division 02 is worked as a staged sequence rather than a single pass — each group below builds on the one before it, and the division closes only once evaluation and acceptance are complete. A — Insulation & Continuity: Cable and equipment insulation is intact, and the intended electrical path exists without an unintended open circuit; B — Earthing: The installed earthing system, earth electrodes, and protective bonding paths meet resistance and continuity requirements; C — Polarity & Resistance: Connections are correctly oriented, and circuit/cable resistance is consistent with design expectations; D — Electrical Measurements: Required supply voltage, current, power, and phase configuration are present and correct at specified test points; E — Cable & Termination Testing: Installed cables, joints, and terminations are electrically and mechanically sound; F — Circuit & Equipment Verification: Primary and secondary circuits, transformers, and connectors are electrically verified before energization; G — Control & Auxiliary: Control circuits and auxiliary supplies are electrically sound ahead of functional testing; H — Evaluation, Acceptance & Reporting: Every result is evaluated against an approved criterion, formally accepted or rejected, and traceable to a test report.
Two requirement groups should be closed out before the Division 02 team starts working through the topic list. Reference Package: Project specification, approved test procedure, and applicable standards; Test voltages, permissible limits, and discharge requirements for each test type; Circuit, cable, transformer, and connector schedules; Equipment manufacturer requirements for winding resistance, ratio, and rated values; Division 01 pre-commissioning verification record and energization authorization. Safety & Instrument Readiness: Confirm the circuit under test is identified and correctly isolated; Confirm absence of voltage before connecting any test instrument; Disconnect sensitive electronic equipment where the test procedure requires it; Confirm the correct instrument, test range, and valid calibration status; Confirm discharge procedure is understood and applied after every insulation test.
Division 02 sits between installation readiness and the specialized commissioning divisions — no result proceeds forward without evaluation, and no division closes without acceptance. (1) Division 01 Complete — Installation readiness verified and energization authorized; (2) Electrical Integrity Verified — Division 02 confirms insulation, continuity, resistance, polarity, voltage, current, power, and circuit connections; (3) CCR Testing & Commissioning — Division 03 builds on verified electrical integrity for CCR-specific testing; (4) Isolation Transformer Testing — Division 04 provides the dedicated transformer testing and commissioning procedure; (5) Component/System Commissioning — Division 05 onward proceeds into fixture, runway, taxiway, control, and photometric commissioning; (6) Evaluation Before Acceptance — Every result passes through the evaluation sequence before any PASS is recorded; (7) Corrective Action — Failed or abnormal results are corrected and retested before proceeding; (8) Formal Sign-Off — The Master Electrical Test Report closes the division and hands the system forward.
Electrical testing is the point where installation integrity becomes proven, measurable fact.
Build the technical knowledge to understand what insulation resistance, continuity, polarity, voltage, current, and power readings actually confirm, how each result ties back to circuit design, and how electrical integrity underpins every division of AGL commissioning that follows.
Measure with precision. Interpret with confidence. Commission with certainty.