Division 23 · HFA · Final Acceptance Gate

Handover & Final Acceptance

The final gate of the entire AGL commissioning process. Division 23 does not generate new field evidence — it converts the technical evidence produced across Divisions 01–22 into a formal handover and project-closure decision: the installed system, test evidence, photometric results, documentation, assets, spares, training, regulatory requirements and outstanding actions are reviewed, and the system is either accepted, conditionally accepted, or held pending closure.

Philosophy: final acceptance is not based on a single successful test. It is based on demonstrated completion of the installation, successful testing and performance verification, closure of deficiencies, completion of documentation, verification of assets and spares, completion of training, satisfaction of applicable regulatory requirements, and formal acceptance by the authorized parties.

20
Topics in Division
09
Review Groups (A–I)
23
Final Division of 23
08
Step Handover Flow

Review Philosophy

Every topic in this division follows the same underlying sequence, whatever the evidence being reviewed — and is checked against the same four acceptance domains before the project is signed off.

Compile Evidence
Review Against Requirement
Identify Gap or Deviation
Close or Disposition
Re-Verify
Record & Sign Off
Installation & test completeness Documentation & asset readiness People & compliance readiness Formal acceptance & closure

Review Sequence

Division 23 runs as a staged gate rather than a single pass — each stage below builds on the one before it, and the division closes only once every stage is signed off.

StageWhat It Confirms
Physical & Test ReviewFinal installation, testing, and photometric evidence generated across Divisions 01–22 are complete and accepted
Deficiency ClosureOutstanding punch-list and snag items are closed or formally dispositioned
Documentation ReviewTest reports, calibration records, as-built drawings, and O&M documentation are complete and correspond to the actual installation
Assets & SparesThe asset register is verified and project-supplied spare parts are formally handed over
People ReadinessRequired operator/maintenance training and client witness points are complete
Compliance & Final TestingApplicable regulatory requirements are satisfied and final acceptance testing is completed
Operational AcceptanceA formal decision is made on readiness for operational use
Handover PackageThe handover package, certificate, and final commissioning report are compiled and issued
ClosureEvery technical and administrative condition is satisfied and the project is formally closed

Before Final Review Begins

Two requirement groups should be closed out before the division-23 team starts working through the topic list.

Evidence Package

  • Complete Division 01–22 test reports, results, and calibration references
  • Approved as-built drawings and equipment/cable schedules
  • O&M manuals, asset register, and spare-parts documentation
  • Training records, attendance registers, and competency assessments
  • Applicable regulatory/authority requirements for this specific project

Review Team & Access

  • Confirm client, consultant, and airport-authority representation is available for witnessing
  • Confirm access to the completed installation for the final physical inspection
  • Confirm outstanding NCRs and corrective actions from earlier divisions are visible to the review team
  • Do not begin formal final acceptance review until Divisions 01–22 evidence is substantially complete

The 20 Topics

Grouped by acceptance focus, in the order the gate is normally worked — click any topic to expand its verification checks and acceptance criteria.

A

Physical & Test Review

3 topics
TC-HFA-001Final Installation Inspection
Verification Checks
  • Walk the complete AGL installation against the approved design and approved changes
  • Verify runway, taxiway, approach, PAPI/APAPI, sign, and stop-bar systems are physically complete
  • Inspect CCRs, isolation transformers, primary and secondary cables, and connectors for condition
  • Verify control panels, ALCMS, and equipment rooms are complete and clean
  • Confirm earthing and bonding, civil works, and base cans are in finished condition
  • Check for physical damage, water/moisture ingress, and safety hazards
  • Confirm mounting, alignment, and labelling of all inspected equipment
Acceptance / Record

Acceptance Criteria: the final installation matches the approved design, approved changes, and actual as-built condition, with no unresolved safety condition.

TC-HFA-002Final Testing Review
Verification Checks
  • Review pre-commissioning, electrical, CCR, transformer, fixture, cable, connector, and earthing test records
  • Review ALCMS, functional, integration, and performance test records
  • Confirm every applicable test was completed and results formally recorded
  • Confirm acceptance criteria were identified for each test and results checked against them
  • Confirm failed tests were retested and the retest result accepted
  • Compile the master test-division review table (report available / results accepted / retest closed / final status)
  • Identify any test division still open and escalate before proceeding
Acceptance / Record

Acceptance Criteria: every applicable commissioning test across Divisions 01–22 is reported, accepted, and closed, with no open retest.

TC-HFA-003Final Photometry Review
Verification Checks
  • Review runway, taxiway, approach-light, PAPI, and sign-illumination photometric records
  • Verify light intensity, colour, uniformity, distribution, and beam-alignment results
  • Confirm the measurement equipment used was in valid calibration at the time of test
  • Confirm each result was checked against the applicable photometric requirement
  • Identify any failed location, the corrective action taken, and the retest result
  • Confirm the final photometric compliance decision is documented
Acceptance / Record

Acceptance Criteria: measured photometric results are checked against the applicable requirement for every location, with full compliance or formally dispositioned exceptions.

B

Deficiency Closure

2 topics
TC-HFA-004Outstanding Punch-List Review
Verification Checks
  • Compile the consolidated punch-list from all commissioning divisions
  • Confirm each item records description, location, responsibility, and corrective action
  • Verify completed items have been inspected and, where applicable, retested
  • Confirm closure evidence is attached before an item is marked closed
  • Classify any remaining open item by safety/operational significance
  • Confirm any open item carried forward has a formally approved disposition
Hold Point

Hold Point: no critical operational or safety-related punch-list item remains open without a formally approved disposition.

TC-HFA-005Outstanding Snag Review
Verification Checks
  • Review all remaining snags with description, location, and responsible party
  • Confirm corrective action, completion, and verification are recorded for each snag
  • Classify each snag as closed, pending, accepted with condition, transferred to maintenance, or not accepted
  • Confirm snags transferred to maintenance are formally handed over with supporting information
  • Confirm snags accepted with condition are documented with the condition and responsible party
  • Verify no safety-related snag is left unclassified
Acceptance / Record

Acceptance Criteria: every remaining snag is classified, and any item not fully closed carries a documented disposition and owner.

C

Documentation Review

4 topics
TC-HFA-006Test-Report Review
Verification Checks
  • Verify each test report carries the correct document number, revision, and project reference
  • Confirm correct equipment/circuit identification on each report
  • Verify test date, test engineer, test equipment, and calibration reference are recorded
  • Confirm results, acceptance criteria, and pass/fail status are stated
  • Verify witness/signature and retest reference are present where applicable
  • Cross-check that reports correspond to the actual installed equipment and final configuration
Acceptance / Record

Acceptance Criteria: test reports are complete, correctly referenced, and verified to correspond to the actual installed equipment and final configuration.

TC-HFA-007Calibration-Document Review
Verification Checks
  • Verify calibration certificates are available for all critical test equipment used during commissioning
  • Confirm equipment identification, make/model, and serial number match the test records
  • Verify calibration date and validity period against each test date
  • Confirm traceability between calibration certificates and the corresponding test reports
  • Flag any test performed with equipment outside a valid calibration period
Hold Point

Hold Point: calibration status must be shown valid at the time each relevant measurement was performed — any gap is investigated before final acceptance.

TC-HFA-008As-Built Drawing Review
Verification Checks
  • Review as-built drawings for runway, taxiway, approach, PAPI, signage, stop-bar, and RGL systems
  • Verify cable routes, cable schedules, CCR and transformer locations, and circuit identification
  • Verify control wiring, ALCMS architecture, PLC I/O, network architecture, and earthing system drawings
  • Perform a drawing-to-field verification on a representative sample
  • Perform a field-to-drawing verification where discrepancies are identified
  • Confirm approved changes are reflected and drawings carry the correct revision status
Acceptance / Record

Acceptance Criteria: final drawings represent the actual commissioned installation, confirmed by drawing-to-field and field-to-drawing verification.

TC-HFA-009O&M-Document Review
Verification Checks
  • Verify O&M manuals are provided for CCRs, transformers, fixtures, PAPI, signs, ALCMS, and PLC equipment
  • Confirm troubleshooting guides and preventive-maintenance procedures are included
  • Verify spare-parts lists and recommended maintenance schedules are provided
  • Confirm warranty information and calibration/testing requirements are documented
  • Cross-check that O&M documentation reflects the actual installed equipment and configuration
Acceptance / Record

Acceptance Criteria: O&M documentation is complete and reflects the actual installed equipment and configuration.

D

Assets & Spares

2 topics
TC-HFA-010Asset-Register Verification
Verification Checks
  • Verify all commissioned assets (CCRs, transformers, fixtures, PAPI, signs, RGLs, panels, PLCs, HMI, ALCMS, communications equipment) are entered in the asset register
  • Confirm asset ID, description, manufacturer, model, and serial number for each entry
  • Verify location, circuit, installation date, warranty, and maintenance reference are recorded
  • Cross-check the register against the equipment schedule and as-built drawings
  • Identify and resolve any asset present on site but missing from the register
Acceptance / Record

Acceptance Criteria: every commissioned asset is correctly and completely entered in the asset register, cross-checked against the equipment schedule.

TC-HFA-011Spare-Parts Handover
Verification Checks
  • Verify the spare-parts register records description, part number, quantity, manufacturer, and condition for each item
  • Confirm storage condition, preservation requirements, and shelf-life information where applicable
  • Verify recommended critical spares are identified and included
  • Confirm storage and replacement instructions are provided
  • Record formal handover status for each spare-parts line item
Acceptance / Record

Acceptance Criteria: project-supplied spare parts are verified against the register and formally handed over with storage and replacement instructions.

E

People Readiness

2 topics
TC-HFA-012Training Completion Verification
Verification Checks
  • Confirm required operator and maintenance training has been delivered per the training plan
  • Verify training dates, participants, and trainer are recorded
  • Confirm training material and attendance records are retained
  • Verify competency assessment has been completed where required
  • Cross-check the training register against the scope of AGL, CCR, ALCMS, and safety topics required
Acceptance / Record

Acceptance Criteria: required operator and maintenance training is complete, with attendance, material, and competency assessment on record.

TC-HFA-013Client Witness Completion
Verification Checks
  • Review the record of FAT, SAT, electrical, photometry, functional, integration, and performance witness points
  • Confirm test reference, date, witness, result, and remarks are recorded for each activity
  • Verify witness/approval signature is present for each contractually required point
  • Identify any witness point not completed and its formal disposition
  • Confirm all contractually required witness points are completed or formally dispositioned
Acceptance / Record

Acceptance Criteria: all contractually required client/consultant witness points are completed or formally dispositioned, with signed records.

F

Compliance & Final Testing

2 topics
TC-HFA-014Regulatory Verification
Verification Checks
  • Identify applicable requirements from the airport authority, civil aviation authority, and project-specific regulations
  • Confirm required inspections, tests, approvals, and certificates for the specific airport/project
  • Verify required compliance records and documentation are complete
  • Cross-check that only requirements applicable to this particular project are included in the final acceptance checklist
  • Confirm outstanding regulatory items are tracked to closure or formal approval
Hold Point

Hold Point: applicable regulatory/authority requirements are confirmed satisfied, using only the requirements relevant to this specific airport/project.

TC-HFA-015Final Acceptance Testing
Verification Checks
  • Confirm all corrective actions from earlier reviews are complete before final acceptance testing begins
  • Conduct final lighting operation, switching, and intensity verification
  • Conduct final control, alarm, and communication verification
  • Conduct final emergency operation verification
  • Conduct final photometric and performance verification where required
  • Confirm the system is tested in its final installed, configured, and documented condition
Acceptance / Record

Acceptance Criteria: final acceptance tests confirm the system performs correctly in its final installed, configured, and documented condition.

G

Operational Acceptance

1 topic
TC-HFA-016Final Operational Acceptance
Verification Checks
  • Confirm required lighting circuits are available and CCRs are operational
  • Confirm control system, ALCMS, and alarms are operational
  • Confirm emergency operation is available
  • Confirm required photometric and electrical performance has been achieved
  • Confirm documentation, training, and critical punch items are complete or closed
  • Confirm regulatory requirements are satisfied
  • Record the final operational decision: Ready for Operation, Not Ready for Operation, or Conditional Acceptance
Acceptance / Record

Acceptance Criteria: the system is formally declared Ready for Operation, Not Ready for Operation, or Conditionally Accepted, with any conditions formally documented.

H

Handover Package

3 topics
TC-HFA-017Handover Package Preparation
Verification Checks
  • Compile the handover index, project information, and completion statement
  • Assemble electrical, CCR, transformer, fixture, cable/connector, and earthing test reports
  • Assemble runway, taxiway, approach, PAPI, sign, stop-bar, RGL, and ALCMS commissioning records
  • Assemble FAT, SAT, integration, photometry, and performance acceptance records
  • Assemble punch-list, snag-list, NCR, corrective-action, retest, and deviation records
  • Assemble as-built drawings, schedules, O&M manuals, and the asset register
  • Assemble spare-parts register, training records, warranty documents, and certificates
Acceptance / Record

Acceptance Criteria: the handover package is compiled per the recommended structure, with every section populated and cross-referenced.

TC-HFA-018Handover Certificate
Verification Checks
  • Confirm the certificate records project, airport, AGL system, and scope
  • Confirm completion date, testing completion, and documentation completion are stated
  • Record any outstanding conditions and the operational status
  • Confirm handover date, parties involved, and required signatures are present
  • Confirm the status recorded (full, conditional, or not accepted) follows the project contract terminology
Acceptance / Record

Acceptance Criteria: the handover certificate is completed, signed, and correctly records scope, status, and any outstanding conditions per the contract terminology.

TC-HFA-019Final Commissioning Report
Verification Checks
  • Confirm the executive summary states project, scope, systems commissioned, and final status
  • Confirm testing summary and results, photometric results, and system-integration summary are included
  • Confirm performance acceptance and faults/corrective-action summary are included
  • Confirm NCR/deviation status and punch/snag status are stated
  • Confirm documentation status, training, handover, and final acceptance status are stated
  • Verify the report is reviewed and formally approved
Acceptance / Record

Acceptance Criteria: the final consolidated commissioning report is complete per the recommended structure and formally approved.

I

Closure

1 topic
TC-HFA-020Project Closure
Verification Checks
  • Confirm all tests are completed and all critical failures, NCRs, punch-list, and snag-list items are closed
  • Confirm deviations are dispositioned and photometry and performance are accepted
  • Confirm as-built drawings are approved and O&M manuals are handed over
  • Confirm the asset register is completed and spares are handed over
  • Confirm training is completed and certificates are issued
  • Confirm handover is completed and the final commissioning report is approved
  • Confirm the final commissioning dossier is archived
Acceptance / Record

Acceptance Criteria: every technical and administrative closure condition is satisfied, the handover is complete, and the final dossier is formally archived — closing Division 23 and the project.

Open-Item Handling

When final review finds a gap or deviation mid-check, the same sequence applies across every topic in this division.

1
Identify

Determine exactly what evidence, document, or condition is missing or non-conforming.

2
Classify

Safety/operational-critical, contractual/regulatory, or administrative/minor.

3
Assess Impact

Does it block operational acceptance and handover, or can it be tracked as a residual condition?

4
Log

Add to the punch-list, snag-list, or NCR register with owner and target date.

5
Correct

Rectify, retest, or complete the missing documentation or action.

6
Re-Verify

Confirm closure against the same acceptance criteria.

7
Record

Update the master review tables, punch-list, and handover certificate before sign-off.

8
Escalate

Unresolved safety-critical or regulatory items withhold final operational acceptance and handover certification.

Frequently Asked Questions

Quick answers about Division 23 — Handover & Final Acceptance in the AGL Testing & Commissioning Manual.

Q1What is Division 23 — Handover & Final Acceptance in the AGL Testing & Commissioning Manual?

Division 23 of the AGL Testing & Commissioning Manual covers Handover & Final Acceptance. The final gate of the entire AGL commissioning process. Division 23 does not generate new field evidence — it converts the technical evidence produced across Divisions 01–22 into a formal handover and project-closure decision: the installed system, test evidence, photometric results, documentation, assets, spares, training, regulatory requirements and outstanding actions are reviewed, and the system is either accepted, conditionally accepted, or held pending closure. It contains 20 topics (TC-HFA-001 to TC-HFA-020) organised into 9 groups (A–I), each topic with its own verification checks.

Q2What is the philosophy behind Division 23 — Handover & Final Acceptance?

Final acceptance is not based on a single successful test. It is based on demonstrated completion of the installation, successful testing and performance verification, closure of deficiencies, completion of documentation, verification of assets and spares, completion of training, satisfaction of applicable regulatory requirements, and formal acceptance by the authorized parties.

Q3What is the step-by-step sequence in Division 23?

Every topic in this division follows the same underlying sequence, whatever the evidence being reviewed — and is checked against the same four acceptance domains before the project is signed off. Steps: Compile Evidence → Review Against Requirement → Identify Gap or Deviation → Close or Disposition → Re-Verify → Record & Sign Off. Focus areas: Installation & test completeness; Documentation & asset readiness; People & compliance readiness; Formal acceptance & closure.

Q4Which topics does Division 23 cover?

Division 23 has 20 topics in 9 groups. A — Physical & Test Review: Final Installation Inspection, Final Testing Review, Final Photometry Review. B — Deficiency Closure: Outstanding Punch-List Review, Outstanding Snag Review. C — Documentation Review: Test-Report Review, Calibration-Document Review, As-Built Drawing Review, O&M-Document Review. D — Assets & Spares: Asset-Register Verification, Spare-Parts Handover. E — People Readiness: Training Completion Verification, Client Witness Completion. F — Compliance & Final Testing: Regulatory Verification, Final Acceptance Testing. G — Operational Acceptance: Final Operational Acceptance. H — Handover Package: Handover Package Preparation, Handover Certificate, Final Commissioning Report. I — Closure: Project Closure.

Q5What is the Review Sequence in Division 23?

Division 23 runs as a staged gate rather than a single pass — each stage below builds on the one before it, and the division closes only once every stage is signed off. Physical & Test Review: Final installation, testing, and photometric evidence generated across Divisions 01–22 are complete and accepted; Deficiency Closure: Outstanding punch-list and snag items are closed or formally dispositioned; Documentation Review: Test reports, calibration records, as-built drawings, and O&M documentation are complete and correspond to the actual installation; Assets & Spares: The asset register is verified and project-supplied spare parts are formally handed over; People Readiness: Required operator/maintenance training and client witness points are complete; Compliance & Final Testing: Applicable regulatory requirements are satisfied and final acceptance testing is completed; Operational Acceptance: A formal decision is made on readiness for operational use; Handover Package: The handover package, certificate, and final commissioning report are compiled and issued; Closure: Every technical and administrative condition is satisfied and the project is formally closed.

Q6What must be in place before final review begins in Division 23?

Two requirement groups should be closed out before the division-23 team starts working through the topic list. Evidence Package: Complete Division 01–22 test reports, results, and calibration references; Approved as-built drawings and equipment/cable schedules; O&M manuals, asset register, and spare-parts documentation; Training records, attendance registers, and competency assessments; Applicable regulatory/authority requirements for this specific project. Review Team & Access: Confirm client, consultant, and airport-authority representation is available for witnessing; Confirm access to the completed installation for the final physical inspection; Confirm outstanding NCRs and corrective actions from earlier divisions are visible to the review team; Do not begin formal final acceptance review until Divisions 01–22 evidence is substantially complete.

Q7How are open items handled during final review in Division 23?

When final review finds a gap or deviation mid-check, the same sequence applies across every topic in this division. (1) Identify — Determine exactly what evidence, document, or condition is missing or non-conforming; (2) Classify — Safety/operational-critical, contractual/regulatory, or administrative/minor; (3) Assess Impact — Does it block operational acceptance and handover, or can it be tracked as a residual condition?; (4) Log — Add to the punch-list, snag-list, or NCR register with owner and target date; (5) Correct — Rectify, retest, or complete the missing documentation or action; (6) Re-Verify — Confirm closure against the same acceptance criteria; (7) Record — Update the master review tables, punch-list, and handover certificate before sign-off; (8) Escalate — Unresolved safety-critical or regulatory items withhold final operational acceptance and handover certification.

Go Further

Don't Just Hand It Over. Understand What Final Acceptance Actually Means.

Handover and final acceptance is where commissioning responsibility formally transfers to the operator.

Build the technical knowledge to understand acceptance criteria, outstanding-item management, and how a properly structured handover protects both the contractor and the operator long after the project closes.

Hand over with precision. Accept with confidence. Operate with certainty.