How do you troubleshoot an AGL cable?

Match the symptom to a place along the cable run, then test section by section with the circuit isolated.

CABLE TROUBLESHOOTING · SYMPTOM, PLACE, CHECKGROUNDCCRDUCTPIT12345BURIED RUNdig-in, abrasion1 CCR TERMINATION · 2 DUCT OR CROSSING · 3 JOINT4 BURIED RUN · 5 PIT AND CONNECTOR ENTRYALL LIGHTS OUTCable cut or joint open · 1, 2, 3, 4CCR TRIPS, EARTH FAULTInsulation damage, wet joint · 2, 3, 4INSULATION RESISTANCE FALLINGAgeing, moisture, minor damage · 3, 4, 5INTERMITTENT FAULTLoose or wet joint or termination · 1, 3, 5DAMAGE AFTER WORKSDig-in, crossing or duct · 2, 4ALWAYSTELL ATC · ISOLATE AND LOCK OFF THE CCR · PROVE DEAD · AUTHORISED ONLYLocate and mark the cable before any excavation. Repairs use approved joints and are retested.
open / buried run
earth fault / joint
duct / works damage
falling insulation
The Fact Cable fault tracing

The primary series cable carries the loop current from the CCR through every isolation transformer, so a cable fault shows up across the circuit. The symptom points to a place along the run. All lights out means the cable is open: cut, or failed at a joint or termination, found with continuity tests by section. A CCR trip or earth-fault alarm points to insulation damage or a wet joint, found with insulation resistance tests by section. A single earth fault on a floating series loop often does not stop the lights and shows only on earth-fault monitoring or an insulation test; a second fault can short out lights or trip the CCR. A slow fall in insulation resistance shows ageing or moisture, and an intermittent fault often traces to a loose or wet joint or termination.

The cable run is divided at terminations, joints and pits, and each section is tested. Cable records show where the cable runs and where the joints are, and fault-locating equipment can help pinpoint a position. Joints and terminations are checked early because they are made-up seals and fail more often than the factory cable. Damage after excavation or work at a crossing or duct is checked first at those places. After a repair the section is retested, ATC is told and the cable records are updated. Test methods and limits come from the cable specification, the manufacturer and the airport’s safe-working rules.

All lights outCut cable, open joint
CCR tripInsulation damage, wet joint
Falling IRAgeing, moisture
IntermittentLoose or wet joint
Check earlyJoints and terminations
Open testsContinuity by section
Earth testsInsulation resistance
ReferenceFAA AC 150/5345-7 (L-824 underground electrical cable); FAA AC 150/5340-26; ICAO Doc 9157 Part 5; cable manufacturer data and airport records
Awareness schematic only, not a fault-finding procedure. Series circuits carry high current and can be lethal, and buried cable may be live. Isolation, lock-off, test methods, limits and excavation rules come from the manufacturer, the standards and the airport’s own safe-working rules, and only trained and authorised personnel work on them.
Entry 20 · Fixture troubleshooting Entry 22 · Connector troubleshooting

Frequently Asked Questions

Q1What does a primary cable carry in an AGL circuit?

The primary series cable carries the constant current from the CCR round the whole loop, passing through each isolation transformer's primary. It is usually single-core, insulated for the circuit voltage, and laid in ducts or buried along the airfield.

Q2How is a cable fault located?

The circuit is isolated, then divided into sections at joints, pits or terminations. Continuity tests find an open section and insulation resistance tests find an earth fault. Cable route drawings and, where used, cable fault locating equipment help to pinpoint the position.

Q3What most often damages airfield cable?

Excavation and construction work, crossings and ducts where the cable is stressed or abraded, water ingress at joints, and ageing of the insulation. Rodents and ground movement can also play a part.

Q4Why can insulation resistance fall over time without a fault alarm?

Moisture, ageing or minor damage can lower insulation gradually while the CCR still runs. Trending the test readings shows the fall early, so the weak section can be found and repaired before it trips the circuit.

Q5Why are joints and terminations often the cause?

They are the points where the factory insulation is replaced by a made-up seal. Poor workmanship, water entry or movement can fail them first, so they are checked early when a cable fault is suspected.

Q6What must happen before anyone digs near a cable?

The cable route is checked against the records and located and marked on site, and the circuit is treated as live unless proven isolated. After any repair the section is retested and the cable records are updated.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.