What is a transformer connection?

A transformer connection is how a series isolation transformer is wired into an airfield lighting circuit. Its primary leads join the circuit cable in series, and its secondary leads feed a short cable to one light fitting.

PIT OR BASE CAN · BELOW GROUND PRIMARY SECONDARY ISOLATION TRANSFORMER LIGHT FITTING (LAMP OR LED) FROM CCR OR PREVIOUS LIGHT SERIES CIRCUIT CONSTANT CURRENT TO NEXT LIGHT OR BACK TO CCR PRIMARY LEADS PRIMARY CONNECTORS SECONDARY CONNECTORS SECONDARY CABLE TO ONE FITTING NO DIRECT ELECTRICAL PATH BETWEEN THE WINDINGS OPEN SECONDARY PRIMARY LOOP STAYS CLOSED · OTHER LIGHTS STAY ON OPEN PRIMARYPRIMARY LOOP OPEN · NO CURRENT · EVERY LIGHT ON THE CIRCUIT GOES OUT SCHEMATIC · AC CURRENT ALTERNATES · ARRANGEMENT ILLUSTRATIVE · NOT TO SCALE

Swipe to see the full diagram

primary cable (series circuit)
secondary cable to the fitting
pit or base can
connectors
The Fact Circuit practice

A transformer connection is how a series isolation transformer is joined into an airfield lighting circuit. All the lights on a circuit share one loop of primary cable that carries a constant current from the constant current regulator (CCR). The transformer’s primary leads are joined into that loop, so current comes in on one lead, passes through the primary winding and leaves on the other to carry on to the next light.

The secondary side is separate. A short cable from the secondary leads feeds only the one fitting, and the transformer passes energy to it magnetically, with no direct electrical path from the primary. That keeps the fitting isolated from the primary circuit, and it lets the primary loop stay closed when a lamp fails or a secondary cable is disconnected. The joints are made with purpose-made, sealed plug-and-receptacle or moulded connectors, so the transformer can be disconnected, tested or replaced without re-jointing the main cable. Unplugging a primary connector opens the series loop, so isolate and make the circuit safe under site procedures first, and treat the secondary as live as well.

Primary Leads and Connectors
Two leads from the primary winding join the circuit’s primary cable through connectors, putting the winding in series with every other light on the loop.
Isolation Transformer
Couples the primary and secondary windings magnetically. The two sides have no direct electrical connection to each other.
Secondary Leads and Cable
Secondary leads join a short cable that runs to the one light fitting this transformer feeds.
Sealing and Support
Each joint is sealed against moisture and supported so it is not strained, following the manufacturer’s jointing instructions. The housing for these joints is covered in Transformer Pit.
Primary sideIn series with the circuit
Secondary sideTo one light fitting
Current ratioCommonly 1:1 (e.g. 6.6 A : 6.6 A)
ReferenceFAA AC 150/5345-47 · AC 150/5345-26 · ICAO Doc 9157 Part 5
Diagram is a schematic and not to scale. Connector style, lead length and jointing method vary by manufacturer and project specification; follow the design drawings, the manufacturer’s instructions and the applicable standard.
Entry 13 · Transformer pit Entry 15 · Transformer circuit position

Frequently Asked Questions

Q1What is a transformer connection in AGL?

The way a series isolation transformer is wired into an airfield lighting circuit. Its primary leads connect in series with the circuit’s primary cable, and its secondary leads connect through a short cable to the light fitting.

Q2Is the transformer primary connected in series or in parallel?

In series. The primary winding is one link in the circuit’s loop, so the same constant current from the constant current regulator (CCR) passes through the primary of every transformer on that circuit. Each secondary then feeds only its own fitting.

Q3Why do the other lights stay on when one lamp fails?

When a lamp fails or its secondary cable is disconnected, the secondary stops carrying current, but the primary winding is still part of the loop. Series isolation transformers are designed to allow this, so the primary current keeps flowing and the other lights stay lit. An open secondary can develop a raised voltage and heat the transformer, so it is still treated as live and corrected promptly. A break on the primary side is different: it opens the whole series loop.

Q4What can go wrong at a transformer connection?

Water in a connector, a loose or badly made joint, or damaged insulation can cause a high-resistance joint, heating or an earth fault, and a fault on the primary side can affect the whole circuit. This is why connections are sealed, supported and checked with continuity and insulation-resistance tests during installation and maintenance.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.