What are buried and elevated transformers?

Series isolation transformers installed below ground or above it, and how the two positions differ in protection, access and risk.

SAME TRANSFORMER, TWO POSITIONS BURIED · BELOW GROUND GROUND LEVEL LOOP CABLE FROM CCR ON TO NEXT LIGHT PIT / BASE CAN LEAD TO FITTING BURIED = PROTECTED FROM WEATHER AND IMPACT RISK: WATER, FLOODED PIT, FROSTLOCATE BEFORE DIGGING ELEVATED · ABOVE GROUND GROUND LEVEL LOOP CABLE FROM CCR ON TO NEXT LIGHT TRANSFORMER IN ENCLOSURE FRANGIBLE SUPPORT FITTING ELEVATED = EASIER TO REACH, MORE EXPOSED RISK: SUN, WIND, VIBRATION, IMPACTFRANGIBLE WHERE REQUIRED WORKING ON A BURIED OR ELEVATED UNIT · ISOLATE FIRST · RE-ENERGISE LAST ISOLATE CCR OFF · LOCKED OFF PROVEN DEAD ACCESS PIT OR STRUCTURE SAFE, DRY ACCESS INSPECT HOUSING · SEALS · LEADS LOOK FOR WATER OR DAMAGE TEST CONTINUITY · INSULATION BEFORE ENERGISING RESTORE RE-SEAL · RE-ENERGISE VERIFY AND RECORD BURIED FIGHTS WATER · ELEVATED FIGHTS WEATHER AND IMPACT · BOTH NEED THE CIRCUIT ISOLATED FIRST
buried unit
elevated unit and loop cable
The Fact FAA AC 150/5345-47 · ICAO Annex 14 · ICAO Doc 9157 Part 5

A series isolation transformer can sit below ground or above it. A buried unit is installed in a base can, a transformer housing or a pit. An elevated unit is mounted above ground, for example in an enclosure, a fixture stem or a support. Either way its primary is in the series loop and its secondary feeds the fitting.

1Buried: protected, but wet

Below ground the unit is shielded from weather and impact, and nothing stands up to be hit. The price is water: a pit can flood, seals can fail and frost can heave a housing. Reaching it means opening the pit, and buried cables must be located before anyone digs.

2Elevated: easy to reach, exposed

Above ground the unit is easier to reach and keeps the connections out of the pit water. It is exposed to sun, wind, vibration and impact. On the operational area, equipment and supports must be frangible where required and mounted as low as practicable, so the enclosure and its support must meet that requirement.

3The circuit is live either way

Position changes the hazards, not the electrics. The primary is part of a live series loop, so the circuit must be switched off, isolated, locked off and proved dead before any work, and discharged or earthed as the site procedure requires, whether that means a wet pit or working at height.

4Match the whole unit

A buried and an elevated unit do the same job. A replacement must still have the same current ratio and a suitable wattage rating, and the position is set by the design, not chosen on site.

PointBuriedElevated
PositionBelow ground, in a base can, housing or pitAbove ground, in an enclosure, stem or support
ProtectionFrom weather and impactFrom pit water and flooding
Main riskWater ingress, flooding, frostSun, wind, vibration, impact
AccessOpen the pit; locate before diggingReach the enclosure; height work on structures
Special pointSeals and drainageFrangibility where required
The drawing and table are generic. Most installations bury the transformer; elevated mounting is the exception, for example in an enclosure on an approach-light structure. Which position is used depends on the fixture type, the design and the authority’s requirement, and real housings and enclosures differ. Never open a primary connection on an energised circuit. Follow the manufacturer’s data, the design drawings, the applicable specification and the airport’s procedures.
Entry 16 · Plug-in isolation transformers Entry 18 · Transformer load

Frequently Asked Questions

Q1What is a buried isolation transformer?

It is a series isolation transformer installed below ground, in a base can, a transformer housing or a pit, with its primary in the series loop and its secondary lead running up to the fitting. It is protected from weather and impact, but exposed to water, flooding and frost.

Q2What is an elevated isolation transformer?

It is a series isolation transformer mounted above ground, for example in an enclosure, a fixture stem or a support, where the fitting stands above ground. It is easier to reach, but exposed to sun, wind, vibration and impact.

Q3Does the position change what the transformer does?

No. A buried and an elevated unit do the same electrical job: the primary is in the series loop and the secondary feeds the fitting. The current ratio and wattage rating still come from the nameplate and must suit the circuit and the fixture.

Q4Why does frangibility matter for elevated units?

Equipment and supports on the operational area are required to be frangible where specified, and mounted as low as practicable, so that they break away rather than damage an aircraft. An elevated transformer and its enclosure must fit that requirement, so check ICAO Annex 14 and the authority's requirement.

Q5What are the main hazards when working on each?

For a buried unit they are a wet or flooded pit and buried cables that must be located before digging. For an elevated unit they are working at height and an exposed enclosure. In both cases the circuit must be isolated, locked off, proved dead and discharged or earthed as the site procedure requires, because the primary is part of a live series loop.

Q6Who decides whether a unit is buried or elevated?

The design, which depends on the fixture type, the site conditions and the authority's requirement. A transformer should not be relocated on site without the designer's agreement, because cable lengths, sealing and frangibility all depend on its position.

Precision AGL Academy

See It. Understand It. Then Learn How to Engineer It.

Recognising an AGL system visually is the first step. The next step is knowing how to design, install, test, commission and maintain them correctly.

Build Practical AGL Engineering Skills

Go deeper with structured training from Precision AGL Academy, covering:

AGL Fundamentals Design & Electrical Engineering Approach Lighting Photometry Installation & Commissioning Maintenance & Troubleshooting

Learn how each light, sign and circuit works as part of a complete airport lighting system, not just as an isolated diagram.

See. Understand. Apply. Engineer.