THE AGL ENGINEERING CENTRE by Precision AGL Academy · Testing & Commissioning

Airfield Lighting Testing & Commissioning Guide

How to prove an installed AGL system is correctly installed, electrically safe, functionally operational and optically compliant: cable and insulation tests, CCR, transformers, circuits, photometry, PAPI, signs, controls, punch lists and handover records. Commissioning is more than checking that the lights turn on.

Overview

What Testing and Commissioning Mean

Airfield lighting testing and commissioning verifies that an installed AGL system is correctly installed, electrically safe, functionally operational and able to provide the intended visual guidance performance. It is not a final check that the lights turn on: it covers the chain from the power supply and CCR through the primary series circuit, isolation transformers and connectors to the fixtures, visual aids, signs and control system.

Testing produces evidence; commissioning uses that evidence to show the system is complete, functional and ready for operation.
Install inspection
Cable tests
Electrical tests
Equipment
Energize
Functional
Brightness steps
Photometry
PAPI / signs / controls
Final inspection & records
The exact test sequence and acceptance criteria come from the approved design, project specification, manufacturer requirements and the applicable aviation authority standards.
Definitions

Testing vs Commissioning, and Why the Whole System Matters

Testing can include

Cable testsInsulation resistanceContinuityTransformersConnector inspectionCCRCircuit resistance / impedanceFunctionalBrightness stepsPhotometryPAPISignsControl system

Commissioning also includes

Installation quality reviewCheck against approved drawingsDefect correctionPunch-list closureFinal inspectionTest-record compilationAs-built verificationO&M documentationHandover

Path: CCR, primary series cable, isolation transformer, secondary connector, light fixture. Control runs control system, CCR, series circuit, fixtures. PAPI, signs, approach lighting and stop bars have their own power and control.

A defect anywhere affects the result:

  • A cable can have continuity but poor insulation
  • A transformer can be installed correctly but be defective
  • A light can operate with poor photometric output
  • A CCR can produce current but not change step correctly
  • A PAPI can illuminate but be aimed wrongly
  • A sign can be lit but have a control or optical fault
ActivityPurpose
Installation inspectionVerify physical installation
Cable testingVerify electrical circuit integrity
Equipment testingVerify individual component operation
Circuit testingVerify complete electrical circuit
Functional testingVerify operational behaviour
Photometric testingVerify optical performance
Integrated testingVerify system interaction
Final inspectionVerify completion
DocumentationCreate formal commissioning evidence
HandoverTransfer the completed system to operations and maintenance
A project can pass individual equipment tests and still fail commissioning because an integrated function was not configured correctly.
COMMISSIONING SEQUENCE · IN WHAT ORDER PASS · RECORD · HOLD · THEN THE NEXT STAGE 1 PRE-COMMISSION Installation checked Circuit tests done Records ready HOLD: ready to energize 2 ENERGIZATION Controlled switch-on Steps raised in turn Readings watched HOLD: stable on all steps 3 FUNCTIONAL Each light and control Steps and alarms Local and remote HOLD: works as designed 4 INTEGRATION Circuits run together Interlocks proven Fault behaviour HOLD: system agrees 5 ALCMS LINK Control signals Status feedback Failure handling HOLD: command = response 6 PAPI Aiming and settings Glide path angle Flight check if required HOLD: angles confirmed 7 SIGNS Legends correct Brightness steps Control and status HOLD: signs correct 8 ACCEPTANCE Records reviewed Key tests witnessed Certificate signed HOLD: owner accepts A STAGE FAILS CORRECT · RE-TEST · REPEAT ALL EIGHT PASSED READY FOR SERVICE SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 1. The commissioning sequence: each stage passed and recorded before the next begins.AGL Visual Encyclopedia: What is the commissioning sequence?
Pre-Commissioning

Installation Inspection, As-Built Verification and Checklist

Light fixtures

Type, location, orientation, elevation.

  • Mounting, lens condition, drainage
  • Cable entry and connector installation

Housings and junction boxes

Location, access and sealing.

  • Secure installation, drainage, cable routing
  • Enclosure condition, connector arrangement
  • Identification

Primary cables and CCRs

Routing, joints and terminations.

  • Identification, mechanical protection, separation
  • CCR location, enclosure, ventilation, grounding, labels, control connections

Test against the installed configuration, not only the design drawing. Review single-line diagrams, circuit drawings, layouts, cable, transformer, fixture and CCR schedules, control drawings, PAPI drawings, sign schedules and data sheets. Record every field change for the as-built set, especially a changed cable route, circuit division, transformer location or fixture position.

Before energization, verify

Installation

Installation complete
Equipment correctly identified
Cable routes verified
Primary circuit terminations complete
Transformers installed
Connectors installed
Light fixtures, PAPI and signs installed
0 / 0 complete

Readiness

Control-system wiring complete
CCR installed
Grounding and bonding completed as designed
Construction debris removed
FOD inspection completed
Test instruments calibrated
Safety procedures approved
Approved commissioning procedure available
0 / 0 complete
PRE-COMMISSIONING · STATIC CHECKS BEFORE POWER DE-ENERGISED · CCR LOCKED OUT · NO LIVE TESTS 1 DOCUMENTS As-built drawings Circuit schedules Permit & test plan RECORD: documents 2 INSTALLATION Fixtures aligned Torque & seating Labels & cleanliness RECORD: inspection 3 CABLES Loop continuity Insulation resistance Joints & connectors RECORD: cable log 4 EARTHING Earth resistance Bonding continuity Earth pits RECORD: earth log 5 EQUIPMENT CCR & controls Transformers & lamps Settings recorded RECORD: settings HOLD POINT READINESS SIGN-OFF · RECORDS REVIEWED 6 OPEN ITEM RECTIFY · RE-TEST CLEARED READY FOR ENERGIZATION SCHEMATIC · CHECK LISTS SHORTENED · NOT TO SCALE
Figure 2. Pre-commissioning: static, de-energised checks that prove the system is built and connected correctly.AGL Visual Encyclopedia: What is pre-commissioning?
Electrical Testing

Cable, Insulation, Continuity and Circuit Impedance

Cable testing

Potential tests depend on cable type, circuit arrangement, voltage, specification and electrical requirements: insulation resistance, continuity, conductor identification, cable integrity, fault location, sheath checks and circuit resistance or impedance. Test before final commissioning where practical so construction defects are fixed before energization.

Insulation resistance

Helps find damaged cable, moisture ingress, defective joints, transformer insulation problems, damaged connectors and termination defects. Test voltage, connections, duration and acceptance criteria come from the approved test procedure.

Do not use a generic insulation-resistance number as a universal AGL acceptance limit.

Continuity is not insulation integrity

Continuity finds open circuits, wrong connections, poor joints, wrong terminations and damaged conductors. A cable can show continuity PASS while insulation FAIL, so both tests are needed where specified.

Circuit resistance / impedance

Depends on cable length, conductors, number and type of transformers, fixture load, temperature, configuration and connections. Compare it with design calculations, manufacturer information, approved criteria, factory or site data and the commissioning baseline. A significant difference should be investigated.

Insulation test record fieldImpedance verification record field
Circuit number, cable identificationCircuit identification
Instrument and serial numberCable length and configuration
Calibration statusNumber and type of connected transformers
Test voltage and durationMeasurement conditions and test equipment
Temperature or conditionsMeasured value and design/reference value
Measured resistance, acceptance criterion, resultDifference and assessment
Possible causes of a large impedance discrepancy: wrong cable, incorrect circuit length, added or removed loads, incorrect transformer, poor connection, unexpected topology or measurement error.
WHOLE LOOP · TWO TESTS continuity and insulation to earth SPLIT AT PITS · LOCATE test the loop one section at a time CCR END Ω MΩ EARTH 1 2 A HIGH B HIGH C LOW D HIGH 3 4 1CONTINUITYthe loop is one unbroken path 2INSULATION RESISTANCEconductor to earth should read high 3SPLIT AT PITStest each section on its own 4LOCATE AND RECORDthe low section holds the fault CABLE SOUND COMPLETE LOOP, HIGH INSULATION Matches the baseline, so it can be energised FAULT FOUND ONE SECTION OPEN OR LEAKING Split at pits until one section reads wrong SCHEMATIC · NOT TO SCALE · TEST VALUES COME FROM THE SPECIFICATION
Figure 3. Cable testing in a series circuit: proving one unbroken, well-insulated conductor.AGL Visual Encyclopedia: What is cable testing in a series circuit?
Equipment

Transformers, Connectors and CCR Testing

Isolation transformer

Follow the manufacturer instructions and project specification.

  • Physical and nameplate inspection
  • Primary and secondary checks
  • Insulation, winding continuity, polarity where applicable
  • Damage and moisture ingress

Nameplate verification

Must match the approved equipment schedule.

  • Manufacturer, model, rating, serial number
  • Primary and secondary characteristics
  • Project identification and circuit association
  • A wrong rating causes downstream lighting problems

Connectors

Inspect every connector before energization.

  • Correct type, assembly and termination
  • Secure, no damage, moisture or corrosion
  • Correct identification
  • Defects cause high resistance, intermittent faults or open circuits

CCR commissioning

Consider incoming supply, output current, intensity steps, current regulation, control response, local and remote control, monitoring, alarms, fault indications, protective functions, interlocks, communication and standby functions where applicable. Follow the manufacturer's commissioning procedure for internal adjustments and protective functions. The FAA specification for CCRs and regulator monitors is AC 150/5345-10H.

Current-step testing

Verify each step: the command is received, the CCR moves to the correct condition, output is stable, monitoring reports the state and the lighting responds. Take current values and tolerances from the CCR specification, not a generic table.

Local control

Test ON/OFF, step selection, status and alarm indication, reset and protective trips where specified. Confirm both command and response.

Remote control

Test from the airport's actual control system: ON/OFF, intensity, acknowledgement, feedback, faults, loss of communication, local/remote selection and interlocks.

FITTING DISCONNECTED SECONDARY ISOLATION TRANSFORMER ISOLATED · DE-ENERGISED PRIMARY SERIES CIRCUIT ISOLATED AT THE CCR LOCKED OFF · PROVEN DEAD EARTH / CASE INSULATION TESTER READS HIGH ILLUSTRATIVE · TEST VOLTAGE AND LIMITS PER SPECIFICATION
Figure 4. Transformer testing: insulation checks between primary, secondary and earth with the circuit isolated.AGL Visual Encyclopedia: How is a transformer tested?
Functional Testing

Functional and Brightness-Step Testing

Complete-circuit functional test

Show that the whole circuit operates together, not only that each fixture works. The chain should be:

01

Command

02

CCR response

03

Correct current / intensity

04

All connected fixtures respond

05

Correct visual pattern

06

Monitoring confirms status; no unexpected alarms

Brightness-step testing

For each commanded step record: commanded condition, CCR response, circuit current, fixture response, control-system indication, abnormal behaviour and alarms. It can reveal:

  • Incorrect CCR programming or missing intensity levels
  • Unstable current or incorrect control signals
  • Communication problems and monitoring errors
  • Failed or uneven fixtures
  • Wrong local/remote configuration

Treat it as an integrated commissioning test, not simply a CCR test.

FUNCTIONAL TESTING · DOES IT DO ITS JOB LIVE SYSTEM · OPERATED AS A USER WOULD 1 CIRCUITS Each circuit selected Right fixtures lit Colour & direction RECORD: lit check 2 BRIGHTNESS Every step selected Lamps respond evenly Current matches step RECORD: steps 3 CONTROLS Local control Remote control Selector & interlocks RECORD: controls 4 MONITORING Status indications Alarm responses Fail-safe behaviour RECORD: alarms 5 SEQUENCES Flashing & sequence Stop-bar selection Where fitted RECORD: modes FUNCTION VERIFIED EVERY CIRCUIT · EVERY MODE 6 DEFECT ISOLATE · FIX · RE-TEST PASSED READY FOR INTEGRATION SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
Figure 5. Functional testing: operating checks that every circuit, brightness step and control does what the design intends.AGL Visual Encyclopedia: What is functional testing?
Photometry

Photometric Verification

Photometry verifies the optical result: intensity, beam distribution, colour, coverage, orientation, alignment and fixture-to-fixture consistency. It may be required for runway edge, threshold and end, centreline, touchdown zone, approach, taxiway edge and centreline lighting, stop bars, runway guard lights and PAPI. The method must match the lighting function and the acceptance criteria. The FAA specification for runway, taxiway, heliport and vertiport light fixtures is AC 150/5345-46F.

Typical sequence

01

Verify test equipment calibration

02

Confirm fixture identification

03

Confirm operating intensity

04

Establish measurement geometry

05

Measure required optical parameters

06

Compare results with approved criteria

07

Identify failed or degraded units

08

Perform corrective action

09

Repeat the measurement

10

Issue the final photometric report

Keep the link between each measurement, fixture location and acceptance criterion.

Electrical to optical: electrical input, CCR, series circuit, transformer, light fixture, optical system, measured light output. Electrical commissioning shows the system supplies the expected operating condition; photometry verifies the final optical result.

PAPI

PAPI Testing

PAPI needs specialized commissioning because its function depends on optical geometry as well as electrical operation. The FAA specification for PAPI systems is AC 150/5345-28H.

Functional

Operation first.

  • All units operate, brightness appropriate
  • Control commands received
  • Indications correct and stable, no flicker

Alignment

An engineering measurement.

  • Reference and unit elevation, horizontal position
  • Spacing, azimuth, vertical aiming, runway relationship
  • Do not confirm by judging red/white from the ground

Photometric

Retain data and calibration records.

  • Intensity, beam coverage, colour
  • Alignment-related parameters and transition characteristics where applicable
  • Consistency among units
PAPI WING BAR · SIDE VIEW OF THE FOUR TRANSITION ANGLES 2°30′2°50′3°10′3°30′ 3°00′ ABOVE SLOPE · WHITE BELOW SLOPE · RED RUNWAY 21345 1Electrical checks2Elevation angle: inclinometer3Azimuth aiming along runway4Colour + sharp transition5Flight inspection SCHEMATIC · ANGLES EXAGGERATED, NOT TO SCALE · HIGHEST SETTING IS THE UNIT NEAREST THE RUNWAY
Figure 6. How a PAPI is tested: five checks for soundness, angle, aim and the colour change point.AGL Visual Encyclopedia: How is a PAPI tested?
Signs and Controls

Sign, Control-System and SCADA Testing

Signs

FAA AC 150/5340-18H covers siting, design and installation of airport signs and AC 150/5345-44L covers the specification for runway and taxiway signs; both are listed as active.

  • Installation, location, orientation, legend, identification
  • Mechanical condition, electrical connections
  • Illumination, brightness and control, monitoring, circuit association
  • Emergency/backup behaviour where applicable
  • Functional test: command, sign energized, correct legend, status feedback; verify each independently controlled sign against its control point

Control system

  • Local and remote controls, intensity commands, circuit selection
  • Status feedback, equipment alarms, CCR monitoring
  • Communication links, interlocks, emergency controls
  • Fail-safe behaviour where specified

SCADA / monitoring

Verify equipment, circuit and CCR status, current or intensity information, alarms, communication-loss and fault indication, command acknowledgement, event logging and time/date. Test both directions: control to field, and field to monitoring.

Failure simulations (communication loss, CCR fault, circuit fault, power failure, controller failure, invalid command) belong only in the approved procedure with operational safeguards. Do not introduce uncontrolled failures into an operational airport to demonstrate an alarm.
SIGN TESTING1 WHAT IS TESTED1 FUNCTIONSign lights upWhole message lit evenlyEvery brightness step2 ELECTRICALContinuity of wiringInsulation to earthEarth bond sound3 LIGHTBrightness is adequateFace clean, colours correctLegible at distance4 POSITIONUpright and alignedFacing the right wayView not blocked2 THE TEST SEQUENCE1ISOLATEOff, locked out, proved dead2TESTFunction, electrical, light, position3COMPAREAgainst baseline and past records4RESTORE & RECORDRe-energise, log the resultIsolate and prove the circuit dead before any electrical test. The primary is in the series loop.SCHEMATIC · TEST LISTS ILLUSTRATIVE · VALUES AND INTERVALS SET BY THE SPECIFICATION AND SITE PROGRAMME
Figure 7. Sign testing: function, electrical tests, light and position compared with the requirement.AGL Visual Encyclopedia: What is sign testing?
Workflow

Integrated Commissioning and the End-to-End Sequence

The strongest test follows the operational chain: the operator selects an intensity, the control system sends the command, the CCR changes step, the primary circuit responds, fixtures illuminate, photometric output matches the required condition and the monitoring system reports the correct status.

Test progressively: component, then circuit, then system, then integrated operation. Do not energize and troubleshoot the entire airfield system at once.

01

Design and document review

02

Pre-commissioning inspection

03

Cable continuity testing

04

Insulation resistance testing

05

Transformer and connector inspection

06

Circuit resistance / impedance verification

07

CCR testing

08

Initial energization

09

Functional testing

10

Brightness-step testing

11

Photometric testing

12

PAPI testing

13

Sign testing

14

Control and monitoring testing

15

Integrated system testing

16

Final inspection

17

Punch-list closure

18

Retesting

19

As-built and documentation review

20

Final commissioning approval and handover

Interactive

Retest Selector: What to Repeat After Corrective Work

Pick a repair to see which tests should be repeated.

Required retest
Any failed test is followed by the appropriate retest. A completed repair is not demonstrated performance, so close a punch-list item only after the required verification passes.
Control of the Process

Punch Lists, FAT / SAT, Hold Points and Safety

Punch list

Typical items: wrong fixture orientation, damaged connector, missing label, cable identification, incomplete sealing, incorrect transformer, failed insulation test, low photometric result, PAPI alignment, sign-control mismatch, CCR alarm, SCADA point.

  • Unique reference and location
  • Description and responsible party
  • Corrective action and status
  • Retest requirement and closure date

Factory vs site acceptance

FAT is done before shipment: construction, functionality, electrical performance, control interfaces, alarms, factory configuration and documents. SAT is done after installation: site wiring, power, field interfaces, the actual control system, communications and field performance. For CCRs, control panels and monitoring systems, FAT and SAT complement site commissioning; they do not replace it.

PointExample
Hold pointCable testing complete, approval before circuit energization
Witness pointCCR commissioning, consultant or authority witness
Hold pointPhotometric acceptance, approval before operational handover
Document reviewFinal commissioning dossier, approval before closeout

Commissioning safety

High-voltage hazardsElectrical isolationLockout / tagoutTest-equipment safetyAirside accessRunway / taxiway closuresAirport operations / ATC contactVehicle controlPersonnel protectionFOD managementWeather restrictions
Electrical testing should be done only by suitably qualified personnel using approved procedures and equipment. Define scope, responsibilities, sequence, equipment, safety, acceptance criteria, methods, forms, witness requirements, retest procedure and documentation before testing starts.
FINAL ACCEPTANCE · IS IT READY TO HAND OVER REVIEWED · WITNESSED · CLOSED · SIGNED 1 RECORDS All test results in Within the limits Nothing missing RECORD: review 2 WITNESS Key tests shown Owner watches Matches records RECORD: witnessed 3 PUNCH LIST Open items listed Each one closed Re-tested, ticked RECORD: closure 4 HANDOVER As-built drawings O&M manuals Spares & training RECORD: documents 5 SIGN-OFF Certificate drawn up Owner signs Warranty starts RECORD: certificate SYSTEM ACCEPTED OWNER SATISFIED · CERTIFICATE SIGNED 6 NOT ACCEPTED CORRECT · RE-TEST · RE-SUBMIT ACCEPTED READY FOR SERVICE SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 8. Final acceptance: reviewing evidence, closing defects and handing the system over.AGL Visual Encyclopedia: What is final acceptance?
Troubleshooting

Common AGL Commissioning Failures

Click a failure to see the possible causes.

Cable insulation failure

Possible causes

  • Cable damage, moisture
  • Poor joint, incorrect termination
  • Construction damage

Open circuit

Possible causes

  • Broken conductor, incorrect connection
  • Failed connector, loose termination

Abnormal circuit impedance

Possible causes

  • Incorrect cable, unexpected circuit length
  • Incorrect transformer, poor connection
  • Incorrect circuit configuration

CCR does not reach required step

Possible causes

  • Configuration problem
  • Control-system issue
  • CCR fault, monitoring issue

One light does not operate

Possible causes

  • Transformer, connector
  • Fixture, secondary wiring

Multiple lights do not operate

Possible causes

  • Primary cable, CCR
  • Control system, circuit fault

Photometric failure

Possible causes

  • Contamination, wrong fixture, incorrect optics
  • Alignment, degraded light source
  • Electrical operating condition

PAPI failure

Possible causes

  • Incorrect aiming, elevation error
  • Optical problem, failed light source
  • Control problem, mechanical disturbance

Sign does not respond correctly

Possible causes

  • Wiring, address/configuration, controller
  • Incorrect circuit, lamp/LED assembly
  • Monitoring/control problem
Documentation

Test Records, Baseline, Dossier and Report

FieldExample
Airport / Runway-Taxiway / CircuitProject airport, RWY/TWY ID, circuit ID
Equipment and equipment IDCCR / transformer / light, asset ID
Test typeInsulation / current / photometry
Instrument, serial number, calibrationMake and model, instrument ID, certificate reference
Test conditionSpecified operating state
Measured result and acceptance criterionRecorded value, controlled requirement
Status and corrective actionPass / fail, description
Retest result, technician, datePass / fail, name or ID, test date

Commissioning baseline

Reference for all future maintenance.

  • CCR output, circuit characteristics, transformer data
  • Fixture identification, photometric performance
  • PAPI alignment, sign operation, control configuration

Commissioning dossier

What the handover package normally holds.

  • Project data and commissioning date, approved, red-line and as-built drawings
  • Equipment records, certificates, calibration certificates, spare-parts lists
  • All test records, punch list, retests, final inspection
  • Commissioning certificate, O&M manuals, training, handover

Commissioning report

Should answer seven questions.

  • Installed correctly? Electrically safe and functional?
  • Lighting operated correctly? Optical system performed?
  • PAPI and signs correct? Control system correct?
  • All defects closed?

Acceptance rests on objective evidence: installation, electrical, functional, optical, control/monitoring evidence, final inspection and complete documentation. Record actual measurements, not PASS/FAIL only, wherever a quantitative result exists. Keep every result traceable: airport, runway/taxiway, circuit, equipment, test, result.

TEST DOCUMENTATION · THE WRITTEN EVIDENCE PLANNED · RECORDED · CHECKED · SIGNED · FILED 1 PLAN Test plan agreed Limits stated Sheets prepared RECORD: test plan 2 RECORD Values written live Date, time, tester Instrument noted RECORD: test sheets 3 VERIFY Within the limits Calibration current Nothing left blank RECORD: check 4 SIGN Tester signs Witness signs Engineer signs RECORD: sign-offs 5 FILE Report compiled Indexed, traceable In handover pack RECORD: test report RECORD COMPLETE? TRACEABLE · SIGNED · WITHIN LIMITS 6 INCOMPLETE OR UNCLEAR CORRECT · RE-TEST · RE-FILE COMPLETE READY FOR HANDOVER SCHEMATIC · STEPS SHORTENED · NOT TO SCALE
Figure 9. Test documentation: what was tested, how, with what, the result and who signed it.AGL Visual Encyclopedia: What is test documentation?
Special Cases

Rehabilitation, LED Conversion and Common Mistakes

Testing during rehabilitation

Commissioning is also required after runway or taxiway lighting replacement, CCR, cable or transformer replacement, control upgrade, LED conversion, PAPI or sign replacement and pavement reconstruction. The scope should reflect the work done: a small replacement does not need the programme of a full reconstruction, but the affected interfaces must be verified.

LED commissioning

Check fixture, LED module, optics, intensity settings, colour, and compatibility with controls, CCR, transformer and monitoring, plus photometric performance. Do not accept an LED fixture just because it saves power or lights up.

Common mistakes

  • Testing only whether lights turn on
  • Skipping insulation testing
  • Using uncalibrated test equipment
  • Not recording the operating intensity
  • Treating all lights as identical
  • Ignoring control-system feedback
  • Closing defects without retesting
  • Not preserving baseline data
Standards

Standards and Reference Framework

ICAO

Annex 14 Vol. I with applicable aerodrome design and maintenance guidance.

FAA

AC 150/5340-30J, 26C, 5345-10H, 5345-46F, 5340-18H, 5345-28H.

PROJECT

Approved design, contract specification and controlled equipment documentation.

MAKER

Manufacturer instructions and equipment ratings.

FAA referenceSubject
AC 150/5340-30JDesign and Installation Details for Airport Visual Aids
AC 150/5340-26CMaintenance of Airport Visual Aid Facilities
AC 150/5345-10HConstant Current Regulators and Regulator Monitors
AC 150/5345-46FRunway, Taxiway, Heliport and Vertiport Light Fixtures
AC 150/5340-18HStandards for Airport Sign Systems
AC 150/5345-44LRunway and Taxiway Signs
AC 150/5345-28HPrecision Approach Path Indicator (PAPI) Systems

These FAA documents appear on the FAA's list of advisory circulars required for use in AIP-funded projects (checklist dated 5 March 2025). AC 150/5340-18H and AC 150/5345-44L are shown as active on their FAA records, both issued 30 September 2024. The ICAO Store lists Annex 14 Volume I as the 9th Edition (July 2022), with Amendment 18 dated 4 August 2025 and corrigenda issued in 2023 and 2026, including Corrigendum No. 3 dated 8 June 2026. Check the ICAO Store for the current edition, amendments and corrigenda before relying on a specific edition.

Do not mix these frameworks indiscriminately. Exact test voltages, insulation-resistance acceptance values, current tolerances, photometric limits and PAPI tolerances are not universal. They depend on the applicable authority requirements, approved specification, equipment ratings and manufacturer instructions. Check the current references before issuing a commissioning procedure or acceptance certificate.

References

HOW REQUIREMENTS TRAVEL INTO TESTING 1 REQUIREMENT LIST Requirements that must be proved by measurement or operation OUTPUT: TEST ITEMS 2 TEST PLAN Test type, method, instruments and acceptance criteria OUTPUT: TEST PROCEDURES 3 PREPARE Calibrated instruments, isolation, permits and safe access OUTPUT: READY TO TEST 4 CARRY OUT TESTS Factory, site and commissioning tests OUTPUT: MEASURED RESULTS 5 EVALUATE Compare each result with its acceptance criterion OUTPUT: PASS, RETEST OR NON-CONFORMANCE 6 RECORD & CLOSE Signed records, matrix updated, items closed OUTPUT: TEST RECORDS FEEDBACK LOOP A failed test goes to investigation and repair, then back to retest; the acceptance criterion is never changed without formal approval. CRITERIA FIRST · THEN PREPARE, TEST, EVALUATE AND RECORD SIMPLIFIED SEQUENCE · FOLLOW YOUR SITE PERMIT AND ISOLATION PROCEDURE
Figure 10. How requirements flow into AGL testing: each requirement becomes a test with a method and acceptance criterion.AGL Visual Encyclopedia: How do requirements flow into AGL testing?
Checklists

AGL Testing Checklist and Handover Checklist

Pre-commissioning

Approved drawings available
Equipment schedules verified
Installation complete
Visual inspection complete
Equipment IDs verified
Test instruments calibrated
0 / 0 complete

Electrical

Cable continuity
Insulation resistance
Circuit resistance / impedance
Transformer testing
Connector inspection
CCR testing
Current steps verified
Protective functions checked
0 / 0 complete

Functional

Circuit ON/OFF
Brightness steps
Local control
Remote control
Monitoring
Alarms
Interlocks
Event logging checked
0 / 0 complete

Optical

Photometer calibrated
Runway photometry
Taxiway photometry
Approach light testing
PAPI photometry and alignment
Colour checks
Beam coverage verified
0 / 0 complete

Final

Sign testing
PAPI testing
Final inspection
Punch-list closure
As-built documentation
O&M documentation
Handover
0 / 0 complete

Handover: records

Test certificates complete
Calibration certificates included
Photometric report included
PAPI report included
Sign test report included
Control-system test report included
0 / 0 complete

Handover: closeout

Punch list closed
As-built drawings updated
O&M manuals submitted
Training completed
Handover accepted
0 / 0 complete

Prove the system, then keep the baseline

Quantitative, traceable and repeatable commissioning records serve project acceptance and become the baseline for maintenance, troubleshooting and performance monitoring.

Test Yourself

Quick Knowledge Check

Q1. A cable shows continuity PASS. What does that tell you about insulation?

A. It is also acceptable
B. Nothing by itself; insulation resistance must be tested separately
C. Insulation is not needed
D. Only the CCR matters

Q2. Why should a generic insulation-resistance value not be used as a universal limit?

A. It never matters
B. The correct value depends on the actual circuit, equipment and approved procedure
C. Only FAA has one
D. It changes daily

Q3. Brightness-step testing is best described as:

A. Only a CCR test
B. An integrated test of command, CCR, circuit, fixtures and monitoring
C. A paint check
D. Optional for all projects

Q4. After replacing a fixture, what should be done?

A. Nothing
B. A functional retest, plus photometric retest where required
C. Replace the CCR
D. Only a visual check

Q5. Why is the commissioning baseline valuable?

A. It replaces maintenance
B. Future maintenance results can be compared with the original condition
C. It is only for auditors
D. It sets universal limits
Explore More

Explore More AGL Engineering

MAINTENANCE

AGL Maintenance

Preventive and corrective maintenance.

Open AGL Maintenance →
PERFORMANCE

AGL Photometric Testing Guide

Field photometry and reporting.

Open AGL Photometric Testing Guide →
PERFORMANCE

Runway Lighting Photometry

Intensity, coverage, colour and testing.

Open Runway Lighting Photometry →
PERFORMANCE

Taxiway Lighting Photometry

Edge, centreline, stop bar and guard lights.

Open Taxiway Lighting Photometry →
CIRCUIT

CCR Working Principle

Constant current and series circuits.

Open CCR Working Principle →
COMPONENT

Airport Isolating Transformer

Types, ratings and failure modes.

Open Airport Isolating Transformer →
CIVIL

Junction Boxes & Light Bases

Housings, bases and installation.

Open Junction Boxes & Light Bases →
VISUAL AID

PAPI Alignment & Maintenance

Aiming, testing and maintenance.

Open PAPI Alignment & Maintenance →
STANDARDS

ICAO PAPI Requirements

Annex 14 requirements for PAPI.

Open ICAO PAPI Requirements →
PROCESS

Testing & Commissioning Manual

Wider testing and commissioning reference.

Open Testing & Commissioning Manual →
DIAGNOSTICS

AGL Troubleshooting Engine

Symptom-led fault finding.

Open AGL Troubleshooting Engine →
INSTALLATION

Installation & Commissioning

Installation practice for AGL.

Open Installation & Commissioning →
AGL Engineering Hub

Explore the AGL Engineering Knowledge Hub

Fundamentals

Standards & Compliance

Runway, Taxiway & Approach Lighting

Surface Movement & Safety

PAPI

Electrical Engineering & Power

Photometry & Testing

Maintenance, Inspection & Safety

Resources, Documentation & Careers

FAQ

AGL Testing & Commissioning FAQ

Q1What is airfield lighting commissioning?

Airfield lighting commissioning is the formal process of verifying that an installed AGL system has been correctly installed, electrically sound, operationally functional and capable of meeting its applicable performance requirements.

Q2What tests are required for AGL commissioning?

Typical tests include cable continuity, insulation resistance, transformer checks, connector inspection, CCR testing, circuit measurements, functional testing, brightness-step testing and photometric verification. PAPI, signs and control systems require additional dedicated tests.

Q3What is an AGL testing checklist?

An AGL testing checklist is a structured list used to verify that the electrical, optical, mechanical, functional and control aspects of an airport lighting installation have been tested and documented.

Q4Why is insulation resistance testing required?

It helps identify damaged or degraded insulation, moisture, defective joints and other conditions that can compromise circuit integrity.

Q5Is continuity testing enough?

No. Continuity demonstrates that an intended electrical path exists; it does not by itself demonstrate acceptable insulation condition.

Q6How is a CCR tested during commissioning?

CCR testing can include input power, output current, intensity steps, current regulation, alarms, controls, monitoring, local/remote operation and protective functions, according to the applicable specification and manufacturer procedure.

Q7What is circuit impedance testing?

It is the measurement of the electrical characteristics of the installed circuit and can be compared with design calculations or commissioning baselines to identify abnormal circuit conditions.

Q8Is photometry part of commissioning?

Where required by the project or applicable standard, yes. Photometry verifies the optical performance of the installed lights rather than only their electrical operation.

Q9How is PAPI commissioned?

PAPI commissioning includes functional operation plus verification of position, elevation, alignment, aiming and optical performance as applicable.

Q10Are airport signs included in AGL commissioning?

Where the project includes lighted/sign systems, sign installation, electrical function, control and monitoring should be commissioned as applicable.

Q11What documents are required at handover?

The final package commonly includes test certificates, calibration records, photometric results, equipment records, as-built drawings, PAPI/sign/control-system test records, punch-list closure records, O&M manuals and commissioning certificates.

Q12What happens when an AGL test fails?

The failed result should be investigated, the cause identified, corrective action completed and the affected test repeated. The final record should contain both the original failure and the successful retest.

Field Insight

Engineering & Expert Notes

Know What Is Testing and What Is Commissioning
Scope

Testing checks individual items and circuits; commissioning proves the integrated system works as intended. Plan both.

Complete Cable and Insulation Tests Before Energisation
Electrical

Early detection of faults prevents damage and delay. Repeat tests if work disturbs cables afterwards.

Test All Brightness Steps
Functional

Check operation at each intensity step and during changes between steps, not only at full brightness.

Include Photometry and Alignment
Optical

Document the optical performance of key lights and verify PAPI and other aimed units.

Define Retest Rules
Retests

Agree what must be repeated after a repair or change. This avoids arguments and keeps records consistent.

Leave a Baseline for the Operator
Baseline

Provide test records, settings and photos so the operator can compare future measurements with commissioning data.

Precision AGL Academy

Understand AGL. Build Your Engineering Skills.

You now understand how an AGL installation is tested and commissioned — from cable and insulation tests to photometry, PAPI, signs, controls and handover records.

Take the next step with Precision AGL Academy.

Learn AGL Step by Step

Build your knowledge through structured technical learning covering:

AGL Fundamentals Components Electrical Systems Design Photometry Testing Troubleshooting Maintenance

Move from understanding how AGL works to developing the practical knowledge needed to analyse, operate and maintain complete AGL systems.

Understand the system. Build the knowledge. Apply the engineering.