PAPI Alignment, Testing & Maintenance Field Guide

How to install, level, align, aim, test and maintain a PAPI: site survey, foundation, unit spacing, aiming angles, electrical installation, photometry, maintenance checklists, records and troubleshooting. A PAPI that is electrically operational can still be aimed wrongly, and one that passed commissioning can later move.

Overview

What a Complete PAPI Installation Involves

A Precision Approach Path Indicator (PAPI) gives pilots visual information about their position relative to the desired approach path. Correct performance depends on far more than installing and switching on the units: the system must be sited, positioned, levelled, aligned, aimed, connected, tested and maintained.

Survey and siting
Foundation
Unit install
Level
Align and aim
Electrical
Test and photometry
Maintain
Confirm the current edition of each reference before use. FAA AC 150/5340-30J (installation), AC 150/5345-28H (equipment) and AC 150/5340-26C (maintenance) are cited here. For international projects, ICAO Annex 14 Vol. I, national requirements and approved airport design documents also apply.
Siting

Site Survey, Siting and Threshold Crossing Height

Site survey should establish

  • Threshold, runway centreline and edge
  • Longitudinal and transverse runway profile
  • Proposed PAPI location, ground and PAPI elevation
  • Aircraft group, TCH and desired approach angle
  • Obstacles, ILS or other approach guidance
  • Utilities, cable routes, drainage, maintenance access

Siting and TCH

Location comes from an approved siting calculation, never a convenient distance from the threshold. PAPI location, PAPI elevation, threshold elevation, approach angle and aircraft characteristics together give the approved geometry, and the intended TCH must suit the aircraft and runway operation.

Do not use one universal distance. Aircraft, runway geometry, ILS relationships and obstacles change the answer.

Foundation

Foundation, Elevation and Drainage

Stable reference

The foundation provides stable support, accurate position, mechanical rigidity, protection against settlement and maintenance access. Build it from controlled survey information, not estimates from ground conditions.

Elevation matters

Beam geometry depends on physical unit elevation. A wrong foundation elevation gives incorrect TCH, effective approach angle and beam geometry, plus excess adjustment at the mounts.

Drainage

Standing water causes deterioration, corrosion, cable and connector problems, movement and electrical faults. Provide drainage suited to local conditions.

FOUNDATION · SECTION footing, bolts, duct stub-up, earth and frangible coupling WING BAR · PLAN four footings, set out in one line to the runway GROUND LEVEL CONCRETE FOOTING COMPACTED BASE DUCT DUCT STUB-UP EARTH ROD PAPI UNIT FRANGIBLE COUPLING ANCHOR BOLTS RUNWAY U4 U3 U2 U1 EQUAL SPACING OFFSET FROM RUNWAY EDGE ONE STRAIGHT LINE ALL SET OUT FROM SURVEY SIX FOUNDATION STEPS · IN ORDER 1 SET OUT set from survey, in one line, at design offset 2 EXCAVATE to design depth, firm, compacted and drained 3 PREPARE formwork, duct, earth and bolt template in place 4 CAST concrete placed and compacted, no voids at bolts 5 LEVEL top and bolts level and true to the drawing 6 CURE + RECORD cure fully, then record as-built and mount unit
Figure 1. The footing under each PAPI unit — set out in one line, firm, level and true, carrying the anchor bolts, duct stub-up and earth connection, so the unit keeps the angle it was set to.AGL Visual Encyclopedia: What is a PAPI foundation?
Unit Installation

Unit Position, Spacing and Runway Offset

A standard four-unit PAPI is four units in a horizontal row, installed to the approved layout. Check sequence, spacing, runway offset, elevation, azimuth, orientation, mounting stability, adjustment access and frangibility where applicable, then survey the final positions.

ParameterFAA AC 150/5340-30J value (as cited)Note
Unit spacing (L-880/L-881)20 to 30 ft (6 to 9 m) centre-to-centreVariation limited to ±1 ft (0.3 m)
Inboard unit from runway edgeAt least 50 ft (15 m)30 ft (10 m) allowed for small non-jet general-aviation runways
Horizontal aimingOutward, parallel to runway centreline within ±0.5°Check with survey or alignment equipment
Beam-centre elevationAll unit beam centres within ±1 in (25 mm) of a horizontal planeCommon reference plane
FAA values are specific to FAA guidance. For ICAO, EASA, national-authority or military projects, use the applicable requirement and the approved design.

Record actual spacing

Unit 1 ↔ Unit 2Unit 2 ↔ Unit 3Unit 3 ↔ Unit 4
Visually equal spacing does not prove the measured values are within tolerance.

Installation and frangibility

Where frangibility requirements apply, install the approved breakaway arrangement. Do not introduce unapproved rigid supports, excessive structure, improper foundations or non-approved mounting modifications. Consider the unit, mounting arrangement and foundation together; the applicable airport design standard controls the final arrangement.

THRESHOLD RUNWAY APPROACH UNIT A · NEAREST RUNWAY UNIT B UNIT C UNIT D · FARTHEST WING BAR · 4 UNITS ≈ 300 m OFFSET FROM RUNWAY EDGE EQUAL SPACING OPTIONAL SECOND WING BAR · RIGHT SIDE NOT TO SCALE · LINE OF UNITS IS AT RIGHT ANGLES TO THE RUNWAY CENTRELINE APPROACH · PLAN VIEW
Figure 2. How the four units of a wing bar stand beside the runway: one straight line, equally spaced, in a fixed order, so the pilot reads them as a single bar of lights.AGL Visual Encyclopedia: What is the PAPI unit arrangement?
Level & Alignment

Levelling, Mounting and Horizontal Alignment

Levelling

The aim is not for each unit to "look level" but to establish the required physical relationship between all four optical systems. Check unit elevation and tilt, housing level, mounting-leg adjustment, foundation settlement and unit-to-unit difference.

Mounting legs

FAA AC 150/5345-28H requires at least three adjustable mounting legs for levelling, unless an alternative shows equivalent rigidity and levelling capability. Take the final measurement after the hardware is secured.

01

Position the unit

Place it per the approved layout.

02

Establish the reference plane

Common plane for all four units.

03

Adjust mounting legs

Bring the unit level.

04

Verify housing stability

Check for movement under hand load.

05

Lock the adjustment

Tighten all hardware.

06

Recheck after tightening

Tightening can shift the setting.

Mechanical rigidity: FAA AC 150/5345-28H requires units to withstand wind loading and snow or ice loading without shifting the light pattern, so foundation, fasteners, housing and mounting legs all matter.
THRESHOLD RUNWAY EXTENDED RUNWAY CENTRELINE UNIT 1 UNIT 2 UNIT 3 UNIT 4 · OUT OF AZIMUTH AZIMUTH ERROR CORRECT: PARALLEL APPROACHING AIRCRAFT NOT TO SCALE · ERROR EXAGGERATED · LINES SHOW BEAM AXIS ONLY APPROACH · PLAN VIEW
Figure 3. Turning each PAPI unit in the horizontal plane so its beam runs parallel to the runway centreline, toward the approaching aircraft.AGL Visual Encyclopedia: What is PAPI azimuth alignment?
Aiming

PAPI Aiming Angles and Verification

The units are not all aimed at the same angle. Their different angles create the sequence 4 White, 3 White + 1 Red, 2 White + 2 Red, 1 White + 3 Red and 4 Red as the aircraft position changes.

UnitStandard FAA L-880 offsetHG4 aircraft with ILS (FAA)
Nearest runway30′ above glide path35′ above
Next unit10′ above15′ above
Next unit10′ below15′ below
Farthest unit30′ below35′ below
Establish the correct configuration from the approved design.
01

Establish approved glide path

02

Establish physical reference plane

03

Set unit elevation

04

Set horizontal alignment

05

Set individual vertical angle

06

Lock adjustment

07

Verify

Precision inclinometer, optical or survey equipment, manufacturer-approved aiming device or calibrated digital angle equipment, as the required accuracy demands.

Record actual values, not just "PAPI aligned"

UnitDesign angleActual angleDifferenceStatus
Unit 1Approved valueMeasuredCalculatedPass/Fail
Unit 2Approved valueMeasuredCalculatedPass/Fail
Unit 3Approved valueMeasuredCalculatedPass/Fail
Unit 4Approved valueMeasuredCalculatedPass/Fail
3° SLOPE UNIT A · 3°30′ UNIT B · 3°10′ UNIT C · 2°50′ UNIT D · 2°30′ ELEVATION ANGLE PAPI UNIT INCLINOMETER ON REFERENCE SURFACE ABOVE A UNIT'S ANGLE · THAT UNIT SHOWS WHITE BELOW A UNIT'S ANGLE · THAT UNIT SHOWS RED NOT TO SCALE · ANGLES EXAGGERATED · FOUR UNITS SHOWN FROM THE SIDE AS ONE POINT APPROACH · SIDE VIEW
Figure 4. The vertical angle at which each PAPI unit’s beam changes from white to red. Four units, four angles, spread around the approach slope.AGL Visual Encyclopedia: What is the PAPI elevation angle?
Interactive

PAPI Aiming Angle Calculator

Choose a glide path and configuration to see the four unit angles. Add these as the "design angle" column in your aiming record.

3.00°
Nearest runway
—
Unit 2
—
Unit 3
—
Farthest unit
—
A learning aid using the FAA offsets cited above. Final angles must come from the approved design and the applicable standard.
Electrical

Electrical Installation, Power Supply and Wiring

Installation

Follow the approved electrical design and equipment documents. Equipment can include AC supply, power control unit, CCR/series circuit, isolation transformer, secondary connections, local and remote control, monitoring and photocell brightness control.

Before energizing

Verify supply voltage, frequency, circuit identification, protective devices, grounding, cable insulation, connections, transformer rating and control wiring. Never assume a replacement unit can be connected to an existing circuit without checking its electrical characteristics.

Wiring inspection

Inspect supply cable, primary and secondary connections, control and monitoring wiring, grounding, cable glands and connectors. Look for loose terminals, damaged insulation, moisture, corrosion, mechanical strain and incorrect connections.

PAPI POWER SUPPLY TWO WAYS TO POWER THE WING BAR WHAT THE SUPPLY MUST BE SERIES-CIRCUIT PAPI · MOST COMMON CCRCONSTANT CABLESERIES LOOP ISOLATINGTRANSFORMER UNIT LAMPSU1 – U4 LOW-VOLTAGE PAPI · SOME TYPES LV FEEDMAINS PAPI SUPPLY+ CONTROL UNIT LAMPSU1 – U4 STANDBY SUPPLY WHERE THE DESIGN REQUIRES STEADY same current or stable voltage at each step MATCHED rated to the unit's lamp load SAFE isolated, earthed, insulated and protected AVAILABLE standby and changeover where required SETS BRIGHTNESS, NOT COLOUR the colour change comes from each unit's angle FROM SOURCE TO LAMP SourceCCR or LV feed Pathseries loop or radial feed At the unittransformer or LV SCHEMATIC · VARIES BY PAPI TYPE AND MAKER · RATINGS COME FROM THE DESIGN · NOT TO SCALE
Figure 5. Normally one constant-current loop from the CCR, with an isolating transformer at each unit. Some types use a low-voltage feed instead. Either way, the supply sets the brightness and never the colour.AGL Visual Encyclopedia: How is a PAPI powered?
Verification

Functional Test and Light Indication Test

Power and operation

All units receive the required supply and operate correctly.

Colour and brightness

Red/white indication appears correctly and the intended intensity setting operates.

Controls, monitoring, interlocks

Local and remote control, alarms, status signals and any runway-lighting interlock work as designed.

Aircraft positionExpected indication
Too high4 White
Slightly high3 White + 1 Red
On path2 White + 2 Red
Slightly low1 White + 3 Red
Too low4 Red
The functional and indication checks verify electrical and operational behaviour. Use a controlled observation method, and do not treat them as a substitute for measured alignment and photometry.
PAPI WING BAR · SIDE VIEW OF THE FOUR TRANSITION ANGLES 2°30′2°50′3°10′3°30′ 3°00′ ABOVE SLOPE · WHITE BELOW SLOPE · RED RUNWAY 21345 1Electrical checks2Elevation angle: inclinometer3Azimuth aiming along runway4Colour + sharp transition5Flight inspection SCHEMATIC · ANGLES EXAGGERATED, NOT TO SCALE · HIGHEST SETTING IS THE UNIT NEAREST THE RUNWAY
Figure 6. Five checks that prove each unit is sound, set at the right angle, aimed down the runway and changing colour exactly where it should.AGL Visual Encyclopedia: How is a PAPI tested?
Photometry

Photometric Testing and Equipment Calibration

PAPI photometry is broader than brightness. Depending on the requirement it verifies intensity, beam pattern, colour/chromaticity, red/white transition, horizontal and vertical distribution and full-intensity performance. FAA AC 150/5345-28H contains the photometric and chromaticity requirements and requires calibrated test equipment.

Equipment

PAPI photometer, calibrated photometric sensor, angular measurement system, alignment equipment, data acquisition, and colour/chromaticity equipment where required. Check identification, certificate, validity, condition, power, settings and reference configuration before testing, and retain a traceable certificate with the records.

Test conditions

The procedure may specify full intensity, measurement distance and angles, beam position, horizontal coverage setting, vertical reference, temperature and test sequence. Keep conditions controlled.

Colour and red/white transition

A unit can look bright yet have a colour problem from filter degradation, optical damage, LED performance, contamination, incorrect optical assembly or temperature. A poor transition gives an unclear indication, inconsistent unit-to-unit behaviour and a wrong perceived approach position, so test the whole optical system, not just centre-beam intensity.

3° GLIDE PATH A · 3°30′ B · 3°10′ C · 2°50′ D · 2°30′ TOO HIGH4 WHITE SLIGHTLY HIGH1 RED · 3 WHITE ON SLOPE2 RED · 2 WHITE SLIGHTLY LOW3 RED · 1 WHITE TOO LOW4 RED ONE UNIT · FRONT VIEW OF BEAM WHITE · ABOVE ANGLE SHARP SPLIT ≤ 3′ RED · BELOW ANGLE TRANSITION ANGLE SET PER UNIT NOT TO SCALE · ANGLES EXAGGERATED PAPI WING BAR · SIDE VIEW
Figure 7. Each PAPI unit sends out one beam, white above and red below. Four units set at slightly different angles turn that beam into a glide-path signal.AGL Visual Encyclopedia: What is the PAPI beam?
Two Levels of Assessment

Alignment vs Photometry, Visual Inspection vs Measurement

Alignment asks

Is the unit physically aimed in the correct direction?

Photometry asks

Does the optical system produce the required light output, colour and beam pattern?

A unit can have correct aiming with poor photometry, good photometry with wrong aiming, or both faults at once. Commissioning verifies both.

CheckVisual inspectionMeasurement
Unit on/offYesYes
Physical damageYes—
ContaminationYesYes
LevelLimitedYes
Aiming angleLimitedYes
IntensitySubjectiveYes
Beam patternLimitedYes
ColourVisual indicationYes
DocumentationLimitedYes
A PAPI can look normal while still having an alignment or photometric deficiency.
Maintenance

PAPI Maintenance: Daily, Monthly and Optical, Mechanical, Electrical Checks

Base maintenance on the airport programme, manufacturer instructions, authority requirements, operational experience, environment and defect history. FAA AC 150/5340-26C gives PAPI preventive-maintenance procedures.

Daily (FAA 150/5340-26C)

Confirm the PAPI is operating with equal brightness, and keep spare lamps and, where applicable, spare bypass fuses. For LED systems follow the manufacturer procedure rather than incandescent practice. Also check for visible damage, obstruction, contamination and signs of misalignment.

Monthly (FAA 150/5340-26C)

Control operation, photocell brightness control, runway-lighting interlock, radio and remote control, damage from mowing or snowplows, cleaning lamps and filters, mechanical parts, burned wires or connections, and cracked insulators, lamps or filters. Adapt to the installed equipment.

Optical

Clean lens, filter, protective window, housing, heater, ventilation; check moisture. Dirt, dust, insects, salt and oil reduce output, and the equipment standard addresses rain, snow, dew, frost and ice on lens surfaces.

Mechanical

Housing, mounting legs, fasteners, foundation, level, alignment, frangible parts, corrosion. Ask: has anything changed the geometry since commissioning?

Electrical

Supply voltage, connections, fuses and protection, cable, transformer, control circuit, remote control, monitoring, grounding. Look for burned terminals, water ingress and heating.

UNIT A UNIT B UNIT C UNIT D 1 2 3 4 5 6 7 INSPECTION POINTS 1 LENS DIRT, CRACKS, CONDENSATION 2 HOUSING SEALS, CORROSION, DAMAGE 3 MOUNT FRANGIBLE COUPLING, LEVEL, BOLTS 4 LAMP / LED OUTPUT EQUAL ON ALL UNITS 5 CABLE CONNECTOR, ENTRY, EARTHING 6 GROUND GRASS, SNOW, DEBRIS IN BEAM 7 ELEVATION SETTING INCLINOMETER CHECK SCHEMATIC · FRONT VIEW OF WING BAR · NOT TO SCALE
Figure 8. A walk along the wing bar to check that all four units are clean, sound, lit equally, clear of obstruction and still set at their angles.AGL Visual Encyclopedia: What is a PAPI inspection?
Event-Driven Checks

When to Re-Check Alignment and Photometry

EventWhat to do
Light-unit replacementCheck position, level, azimuth, vertical aiming, electrical connection, function and photometry where required, returning the unit to the approved geometric and optical condition
Physical impact (vehicles, mowers, snowplows, wind, ground movement)Do not rely on visual inspection: check foundation, mounting, level, azimuth, aiming, optics, electrics and photometry
Optical change (lamp, LED module, filter, lens, beam adjustment)Photometric verification, because optical performance may have changed
Heavy weather, floodingCheck position, housing, foundation, level, aiming, connections, water ingress and optics; consider alignment and photometry before relying on it operationally
Nearby civil works (resurfacing, shoulders, drainage, trenching, grading)Reassess elevation, relative runway elevation, drainage, line of sight and stability, even if the units were never touched
Repeated aiming driftFind the physical cause (loose hardware, foundation movement, deformation, impact, vibration, wrong method) instead of re-adjusting

Coastal

Corrosion, salt contamination, connectors.

Snow and ice

Snowplow damage, ice, lens heating, exposed foundations.

Dusty

Lens contamination, filter condition, cleanliness.

High rainfall

Drainage, water ingress, connector sealing.

Troubleshooting

Common PAPI Faults and Troubleshooting Sequence

Click a fault to see where to investigate first.

One unit dark

Possible Cause

  • Failed lamp or led
  • Fuse or protection
  • Power supply
  • Connection
  • Control fault
  • Internal electronics

One unit dimmer

Possible Cause

  • Light-source degradation
  • Optical contamination
  • Power problem
  • Internal optical fault
  • Ccr or current problem

Wrong red/white indication

Possible Cause

  • Incorrect aiming
  • Wrong unit sequence
  • Optical problem
  • Incorrect elevation
  • Physical movement

All units misaligned

Possible Cause

  • Foundation movement
  • Incorrect survey reference
  • Runway geometry change
  • Common installation error

One unit misaligned

Possible Cause

  • Mechanical impact
  • Loose mounting
  • Damaged adjustment mechanism
  • Incorrect maintenance

Repeated aiming drift

Possible Cause

  • Foundation
  • Loose hardware
  • Deformation
  • Impact
  • Vibration
  • Wrong adjustment method

Remote control failure

Possible Cause

  • Control wiring
  • Interface
  • Control equipment

Post-maintenance failure

Possible Cause

  • Installation
  • Aiming
  • Electrical connection
  • Photometry
Observe
Confirm position
Unit operation
Supply
Physical condition
Level
Azimuth
Vertical aiming
Optics
Photometry
Rectify and retest

All four units wrong

Check common conditions first: observation position, siting geometry, reference measurement, common supply or control setting, overall PAPI elevation and location. Do not adjust four units individually before eliminating a common-system problem.

One unit wrong or unequal brightness

Check that unit's supply, connector, light source, optics, mounting, level and aiming angle. For brightness, split electrical, optical, mechanical and photometric causes, and follow visual observation with measurement.

Troubleshooting quick reference

ProblemFirst areas to check
One unit darkPower, fuse, light source, connector
One unit dimSupply, optics, light source, photometry
Wrong colourOptics, filter, light source
Wrong red/white transitionOptical system, aiming, photometry
All units wrongSiting, reference, common supply, geometry
One unit misalignedMounting, level, aiming mechanism
Repeated aiming driftFoundation, hardware, mechanical stability
Remote control failureControl wiring, interface, control equipment
Unequal brightnessElectrical supply, light source, optics
Post-maintenance failureInstallation, aiming, electrical connection, photometry
PAPI TROUBLESHOOTING · SYMPTOM, CAUSE, CHECKRUNWAY EDGEWING BAR · 4 UNITS · ABOUT 300 M BEYOND THRESHOLDUNIT 12°30′UNIT 22°50′UNIT 33°10′UNIT 43°30′EACH UNIT FED BYITS OWN ISOLATINGTRANSFORMERSETTING ANGLES SHOWN FOR A 3° SLOPE · HIGHEST NEAREST THE RUNWAY1SYMPTOMONE UNIT DARK/DIMCause: lamp or LED, lead,connector or secondaryCheck: look, then secondary2SYMPTOMALL UNITS OUTCause: CCR off or openloop: primary, joint, cableCheck: CCR, loop continuity3SYMPTOMWRONG SLOPECause: unit moved by aknock or settlementCheck: inclinometer, re-aim4SYMPTOMUNSHARP / UNEQUALCause: dirty or cracked lens,water, debris in frontCheck: lens, housing, view5SYMPTOMCCR EARTH FAULTCause: water in housing,connector or cableCheck: insulation to earthISOLATE AT THE CCR · LOCK OFF · PROVE DEAD · ATC CLEARANCE BEFORE WORK
Figure 9. The symptom shows whether a unit, the circuit, the aim or the optics failed, and a short set of visual, electrical and inclinometer checks confirms it.AGL Visual Encyclopedia: How do you troubleshoot a PAPI?
Workflows

Installation and Maintenance Workflows

Routine maintenance combined with objective performance verification.

Installation: 15 steps

Site survey
Siting calculation
Foundation construction
Unit positioning
Spacing verification
Levelling
Horizontal alignment
Vertical aiming
Electrical installation
Functional test
Photometric test
Final adjustment
Retest
Documentation
Operational acceptance

Maintenance cycle

Inspect
Clean
Check electrical system
Check mechanical condition
Check alignment
Measure
Identify deficiency
Rectify
Retest
Record
Records

Commissioning, Maintenance and Fault Records

Commissioning report

Project (airport, runway, threshold, designation, date); equipment (manufacturer, model, serial, type); survey (coordinates, elevation, spacing, runway offset, foundation elevation); alignment (horizontal, levels, aiming angles); electrical; functional tests; photometry (equipment, calibration, geometry, intensity, colour, beam pattern, pass/fail); supporting records.

Maintenance report

Date, runway, unit, work performed, fault, parts replaced, alignment adjustment, electrical test, photometry, retest, technician, equipment used, remarks.

Fault register example

DateUnitFaultCauseActionRetest
DateUnit 1Low intensityOptical contaminationCleanedPass
DateUnit 3MisalignmentMechanical movementRealignedPass
DateUnit 2No outputElectrical faultRepairedPass

Alignment history: keep previous angle, current angle, adjustment date, technician, reason, test equipment and calibration status per unit. A pattern of small corrections can reveal foundation or mechanical movement.

PAPI COMMISSIONING · IS THE GLIDE PATH RIGHT SITED · AIMED · PROVED BEFORE PILOTS RELY ON IT 1 SITING Position vs design Offset from runway Units in line RECORD: position 2 LEVEL & AIM Units firm, levelled Angle set per unit Calibrated instrument RECORD: angles 3 ELECTRICAL Circuit energised Brightness steps Units match in output RECORD: circuit 4 SIGNAL CHECK Red & white seen From approach path Obstacles cleared RECORD: signal 5 FLIGHT CHECK Flight inspection Glide path confirmed Transition as designed RECORD: flight PAPI COMMISSIONED EVERY UNIT · RIGHT ANGLE 6 DEFECT RE-AIM · FIX · RE-TEST PASSED READY FOR ACCEPTANCE SCHEMATIC · CHECKS SHORTENED · NOT TO SCALE
Figure 10. Siting, aiming and proving the approach path indicator — so the red and white signal a pilot sees marks the correct glide path.AGL Visual Encyclopedia: What is PAPI commissioning?
Checklists

Installation and Maintenance Quality Checklists

Click an item to mark it complete.

Installation Acceptance

Correct type, units and sequence
Correct spacing and runway distance
Foundation stable
Beam centres at correct elevation
Horizontal alignment within tolerance
Individual aiming angles correct
Electrical and controls complete
Documentation complete
0 / 8 complete

Alignment

Horizontal alignment checked
Unit elevation checked
Unit-to-unit level checked
Aiming angles verified
Unit spacing checked
0 / 5 complete

Maintenance Quality

Units and optics clean
Lens and housing undamaged
Mounting and foundation secure
Aiming unchanged or restored
Connections secure
Controls and monitoring working
Records updated
0 / 7 complete

Photometry

Test equipment calibrated
Intensity measured
Beam pattern checked
Colour checked
Red/white transition checked
Results recorded
Deficiencies rectified
Retest completed
0 / 8 complete
Avoid These

Common PAPI Installation Mistakes

1

Using a generic PAPI distance

Distance comes from the approved siting process.

2

Aiming all four units at one angle

The units need different aiming angles.

3

Ignoring unit elevation

Small elevation differences change PAPI geometry.

4

Checking only visual appearance

Visual inspection cannot replace measurement.

5

Forgetting foundation movement

An unstable foundation causes recurring aiming problems.

6

Ignoring horizontal alignment

Correct vertical aiming is not enough if azimuth is wrong.

7

No photometric retest

Aiming alone does not prove optical compliance.

8

No records

Without baseline aiming and photometry records, maintenance gets much harder.

Reference

Standards, References and Numerical Values

FAA AC 150/5340-30J

Design and Installation Details for Airport Visual Aids: PAPI siting, spacing, alignment, mounting.

FAA AC 150/5345-28H

PAPI Systems equipment standard: light units, photometric characteristics.

FAA AC 150/5340-26C

Maintenance of Airport Visual Aid Facilities, including PAPI preventive maintenance.

ICAO Annex 14, Vol. I

International SARPs for aerodrome design and operation, including visual aids.

Spacing, runway offset, aiming angles, TCH, mounting tolerances and obstacle clearance are not universal. The FAA figures in this guide come from FAA guidance as cited. Between FAA, ICAO, EASA, national-authority, military and airport-specific projects, the approved design and applicable authority control. Always use the controlled edition.
Final Engineering Perspective

Do not maintain PAPI only by looking at it. Maintain the geometry, optics, electrical system and measured performance.

Install accurately. Aim precisely. Test objectively. Maintain systematically.

Test Yourself

Quick Knowledge Check

Q1. Why can a PAPI that passed commissioning later give wrong guidance?

A. LEDs change colour overnight
B. Mechanical damage or foundation movement can change its geometry
C. Isolating transformers drift
D. It cannot

Q2. After replacing a PAPI light unit, what should be re-checked?

A. Only that it lights
B. Position, level, azimuth, aiming, electrics, function and photometry where required
C. Only the colour
D. Nothing if the model is identical

Q3. What should come first when all four units give a wrong indication?

A. Re-aim each unit separately
B. Replace all four units
C. Eliminate common-system causes such as observation position, geometry and supply
D. Increase intensity

Q4. Why is photometry needed in addition to an alignment check?

A. It checks the foundation
B. A correctly aimed unit can still have poor intensity, colour or beam pattern
C. It replaces levelling
D. It is only for LED units

Q5. What should be recorded for each unit at commissioning?

A. "PAPI aligned"
B. Design angle, actual angle, difference and status
C. Only the serial number
D. Only a photograph
Explore More

Explore More AGL Engineering

VISUAL AID

PAPI Engineering Guide

Working principle, geometry and siting.

Open PAPI Engineering Guide →
HANDBOOK

PAPI Installation & Aiming Handbook

Installation procedure, aiming and the indication simulator.

Open PAPI Installation & Aiming Handbook →
MAINTENANCE

PAPI/APAPI Maintenance

Preventive and corrective maintenance.

Open PAPI/APAPI Maintenance →
INSPECTION

PAPI/APAPI Inspection

Inspection routines for PAPI and APAPI.

Open PAPI/APAPI Inspection →
PROCESS

PAPI Testing & Commissioning

Test and commission PAPI and APAPI.

Open PAPI Testing & Commissioning →
DIAGNOSTICS

PAPI/APAPI Failures

Diagnose abnormal indications and faults.

Open PAPI/APAPI Failures →
PERFORMANCE

AGL Photometry

Airport photometers and photometric reporting.

Open AGL Photometry →
ELECTRICAL

AGL Isolating Transformers

Transformer ratings, construction and testing.

Open AGL Isolating Transformers →
ELECTRICAL

CCR Deep Dive

The series circuit and CCR operation.

Open CCR Deep Dive →
STANDARDS

ICAO Annex 14 AGL Requirements

SARPs covering visual aids.

Open ICAO Annex 14 AGL Requirements →
ELECTRICAL

Airport Isolating Transformer

AGL transformers, 6.6 A and 20 A systems, ratings and testing.

Open Airport Isolating Transformer →
INFRASTRUCTURE

Airport Junction Box & Transformer Housing

Light bases, transformer housings, cable entry and drainage.

Open Airport Junction Box & Transformer Housing →
ELECTRICAL

CCR Working Principle

How the CCR supplies and controls the AGL series circuit.

Open CCR Working Principle →

Install Accurately. Maintain Systematically.

From survey to aiming records, photometry and maintenance history, explore the complete AGL knowledge base for PAPI engineering.

AGL Engineering Hub

Explore the AGL Engineering Knowledge Hub

Fundamentals

Standards & Compliance

Runway, Taxiway & Approach Lighting

Surface Movement & Safety

PAPI

Electrical Engineering & Power

Photometry & Testing

Maintenance, Inspection & Safety

Resources, Documentation & Careers

FAQ

PAPI Installation and Maintenance FAQ

Q1How is a PAPI installed?

Site survey, approved siting, foundation construction, unit positioning, spacing, levelling, horizontal alignment, vertical aiming, electrical connection, functional testing and photometric verification.

Q2How do you align PAPI lights?

Establish the runway reference, position the units, level them, set azimuth and adjust each unit to its approved vertical aiming angle.

Q3Are all PAPI units aimed at the same angle?

No. Each unit is aimed at a different elevation relative to the selected approach path.

Q4What are the standard PAPI aiming angles?

They depend on the selected approach path and the applicable design standard. FAA guidance gives four-unit offsets of 30 minutes above, 10 above, 10 below and 30 below the pre-selected glide path for the standard installation.

Q5What is the spacing between PAPI units?

For FAA L-880/L-881 installations the cited spacing is 20 to 30 ft (6 to 9 m) centre-to-centre with a maximum variation of ±1 ft (0.3 m). Other authorities may specify different values.

Q6How far should PAPI be from the runway?

It depends on the approved siting calculation, runway geometry, TCH, aircraft characteristics and applicable standards. FAA guidance gives specific lateral and longitudinal siting requirements.

Q7What is PAPI elevation?

The physical elevation of the light units relative to the runway and the approved reference geometry.

Q8Why is PAPI levelling important?

The vertical orientation of each unit determines its effective beam angle and therefore the guidance given to pilots.

Q9What is PAPI photometry?

Measurement of optical performance, including applicable intensity, beam distribution and colour characteristics.

Q10When should PAPI photometry be performed?

During commissioning and whenever the inspection, maintenance, authority or project procedure requires it, especially after optical adjustment, unit replacement or major maintenance.

Q11What equipment is used for PAPI photometry?

A calibrated PAPI photometer, angular measurement equipment and, where required, colour or chromaticity measurement equipment.

Q12Does PAPI maintenance require alignment checks?

Per the approved maintenance programme and whenever there is evidence of movement, impact, civil work or an abnormal visual indication.

Q13What should be checked daily on PAPI?

FAA maintenance guidance includes confirming the PAPI is operating with equal brightness. For LED systems follow the airport and manufacturer procedure.

Q14What should be checked during periodic PAPI maintenance?

Controls, optical cleanliness, mechanical condition, wiring, connectors, mounting, alignment and applicable photometric performance.

Q15What causes PAPI misalignment?

Mechanical impact, loose mounting, foundation movement, incorrect installation, maintenance error or nearby civil works.

Q16What causes unequal PAPI brightness?

Light-source degradation, optical contamination, electrical faults, incorrect intensity control or internal equipment problems.

Q17Can PAPI be visually inspected without photometry?

Visual inspection is useful for routine maintenance but does not replace objective photometric verification where it is required.

Q18What should be done after replacing a PAPI light unit?

Verify position, level, horizontal alignment, vertical aiming, electrical connection and the required operational and photometric performance.

Field Insight

Engineering & Expert Notes

Start With the Survey Data
Siting

Verify distances and elevations against the design before touching the units.

Record Angles Before and After Adjustment
Alignment

Keeping both sets of readings shows what changed and why.

Check Levelling and Mounting Stability
Mounting

Loose fixings or settling foundations can shift the beam over time.

Verify Colour Transition Sharpness
Photometry

The change between red and white should be crisp, which is easy to miss without measurement.

Re-Check After Any Disturbance
Maintenance

Impacts, mowing damage and civil work may move units even if nothing looks wrong.

Update the Maintenance Record
Records

Log checks and adjustments to maintain a history of the installation.

Precision AGL Academy

Understand AGL. Build Your Engineering Skills.

You now understand how PAPI provides visual approach slope guidance — from unit arrangement and angular settings to siting, commissioning and troubleshooting.

Take the next step with Precision AGL Academy.

Learn AGL Step by Step

Build your knowledge through structured technical learning covering:

AGL Fundamentals Components Electrical Systems Design Photometry Testing Troubleshooting Maintenance

Move from understanding how AGL works to developing the practical knowledge needed to analyse, operate and maintain complete AGL systems.

Understand the system. Build the knowledge. Apply the engineering.