NOTAMs (Notice to Airmen)
An AGL engineering and operational guide to aerodrome notices. A NOTAM is an aeronautical notice issued through the appropriate aviation information system to communicate the establishment, condition, change or removal of an aeronautical facility, service, procedure or hazard — when that information is timely and operationally significant. For Airfield Ground Lighting, a NOTAM is not simply an engineering maintenance record. It is an operational safety communication.
1. What Is a NOTAM?
NOTAM stands for Notice to Airmen. Its purpose is to provide timely operational information to aviation users about conditions that may affect flight operations. The exact circumstances requiring a NOTAM are determined by applicable aeronautical information regulations and the responsible aerodrome/aviation authority — not by an individual engineer's judgement alone.
Examples of what a NOTAM can cover:
A serviceability level only means something if it is measured the same way every time and reported to the people who need it. Each light is checked against the 50 per cent line, the lights are counted by type, the result is compared with the objective and the adjacency rule, and the outcome is logged and passed on.
AGL Visual Encyclopedia: Serviceability measured and reported
Why NOTAMs Matter in AGL
An AGL defect can be more than a maintenance problem — it can change what visual guidance an aircraft actually receives. The engineering team identifies and communicates the technical condition through the airport's established reporting process; the authorized aeronautical information function determines and issues the operational notice.
The red lights and cross markings that say part of a runway or taxiway cannot be used, and why the normal lights are switched off inside it.
AGL Visual Encyclopedia: Closed runway marking lights Closed taxiway and unserviceability lighting
NOTAM vs Maintenance Report
These are different documents. A maintenance engineer should not treat a maintenance report as automatically equivalent to a NOTAM — the two serve different audiences and different purposes, even when they originate from the same fault.
| Maintenance Report | NOTAM |
|---|---|
| Technical record | Operational information |
| Used by engineering/maintenance | Used by aviation operational users |
| Records inspection/failure | Communicates operationally significant information |
| Contains technical details | Uses standardized aeronautical information |
| Internal/project record | Published through authorized aeronautical information channels |
Turn each maintenance requirement into a planned task with an interval and an acceptable condition, then isolate, work, verify, restore and record.
AGL Visual Encyclopedia: How do requirements flow into AGL maintenance
When Can AGL Problems Become NOTAM-Relevant?
Whether a particular condition requires a NOTAM depends on its operational significance and the applicable aeronautical information procedures — not on the fact that a fault exists. Potential examples include:
Runway Lighting
- Unavailable
- Partially unavailable
- Edge lights affected
- Centreline lights affected
Taxiway Lighting
- Unavailable
- Stop bars affected
- Temporary configuration changes
Approach Lighting
- Unavailable or degraded system
- Significant lighting restrictions
PAPI
- Unavailable
- Under maintenance / restriction
Airfield Signs
- Unavailable
- Lighting-related works affecting operations
The Governing Question
Not "is something wrong?" but "does this change published or expected operational conditions, per applicable procedure?"
A count only matters if it sets work in motion. Each result falls into one of three bands: within the objective, at the action level, or not met. Each band has its own response, from routine scheduling to telling airfield control straight away.
AGL Visual Encyclopedia: How does a serviceability result trigger maintenance
The AGL-to-NOTAM Chain
The key principle: engineering identifies and verifies the condition. Authorized operational/aeronautical information personnel determine and issue the appropriate notice.
Make the circuit safe, read the symptom at the CCR, then narrow the fault down section by section until one part remains.
AGL Visual Encyclopedia: A fault isolated in a series circuit
NOTAM Considerations Across Lighting Systems
Runway Lighting
Contributes to visual guidance during aircraft operations.
- Complete runway lighting failure
- Partial runway edge-light failure
- Centreline lighting outage
- Threshold / TDZ lighting condition
- Runway end lighting condition
- Reduced lighting capability
- Lighting system under maintenance
Taxiway Lighting
Supports aircraft ground movement.
- Edge / centreline lighting unavailable
- Stop bar lighting unavailable
- Runway guard light condition
- Lighting system restricted during maintenance
- Temporary configuration
Approach Lighting
Provides visual information during the transition toward the runway.
- Centreline lighting
- Crossbars
- Sequenced flashing components
- Other approach-lighting elements
Identify exactly which portion of the system is affected — never simply report "approach lights faulty."
Understand how airport ground lighting systems, visual aids, electrical circuits and control equipment fit together in a typical airport layout.
AGL Visual Encyclopedia: What does a complete AGL airport layout look like
NOTAM and PAPI: "Light ON" ≠ "Correctly Serviceable"
PAPI is an important visual approach aid. Potential conditions include complete outage, one or more light units unavailable, misalignment, maintenance or an operational restriction. However, a PAPI that is physically illuminated is not necessarily operationally correct.
Light ON does not automatically mean PAPI correctly aligned and serviceable. Technical verification should therefore accompany operational reporting.
A powered, visibly lit PAPI can still present a false glide-path indication — the fault is optical, not electrical, so it will not show up as "light off"
Signs, Planned Maintenance & Emergency Failure
Illuminated Signs
Operational importance depends on location, sign function and applicable airport procedures.
- Sign completely unavailable
- Sign partially illuminated
- Incorrect sign displayed
- Sign electrical failure
- Sign undergoing replacement or temporary removal
Emergency AGL Failure
Speed matters, but accuracy matters equally. Never communicate an unverified technical assumption as an operational fact.
- Immediate detection → confirm condition
- Notify airport operations
- Assess operational impact
- Initiate applicable aeronautical information procedure
- Rectify → test → restore → update/cancel
Planned maintenance workflow: Maintenance Plan → Affected AGL Identified → Operational Impact Assessed → Airport Operations / ATC / AIS Coordination → Required Notice or Restriction → Maintenance Work → Testing → Restoration → Notice Cancellation/Update if applicable.
The order of work after a fault — report and assess, locate while live, isolate and prove dead, repair, test, then restore, verify and record the cause, so the fault is fixed and does not come back.
AGL Visual Encyclopedia: The corrective maintenance sequence Sign maintenance
Engineering Information Required — and Why Exact Location Is Critical
Avoid vague statements such as "Runway lights not working." When reporting an AGL condition internally for possible aeronautical information action, capture the following.
NOTAM Information Flow & Who Issues a NOTAM
A NOTAM is not normally issued by an AGL technician simply because a lighting fault has been discovered. The issuance process is governed by the applicable State aeronautical information framework and airport procedures; AGL personnel provide accurate technical information to the authorized function.
NOTAM vs Fault Log, SNOWTAM & AIP
Several documents look related but serve distinct purposes — and can originate from the same event without being interchangeable.
| Document | What It Communicates |
|---|---|
| AGL Fault Log | Equipment, failure, measurements, diagnosis, repair, technician, test results. |
| NOTAM | Operationally significant condition, affected facility, relevant period, operational status, restoration/update information. |
| SNOWTAM | A specialized aerodrome condition report tied to runway surface conditions from snow, slush, ice, frost or related contamination. AGL failures are normally handled through the NOTAM/aeronautical information process, not treated as SNOWTAM information. |
| AIP | Relatively permanent aeronautical information of lasting operational relevance. |
A useful principle: AIP = Published Aeronautical Information. NOTAM = Time-Critical Change / Condition Information. The exact publication mechanism is governed by the applicable State AIS framework.
"Lights ON" Does Not Equal "System Restored"
Restoration is not complete simply because the technician repairs the equipment. A fixture may illuminate while still having incorrect intensity, incorrect colour, poor alignment, intermittent operation, incorrect circuit configuration, damaged optics or other performance problems.
Photometry becomes important when a defect affects actual optical performance. Fixture electrically operational does not automatically establish required photometric performance achieved. Where applicable, photometric verification supports the technical confirmation of restoration.
The controlled return of a circuit to service once maintenance is done: everything cleared and closed up, tested, the isolation removed in order, the circuit re-energised and checked, and the work recorded. The job is not finished when the last bolt is tight.
AGL Visual Encyclopedia: Post-maintenance restoration
CCR, Series-Circuit & Individual Light Failures
CCR Failure
Can affect an entire lighting circuit — runway, taxiway, approach or PAPI outage, or reduced intensity capability.
Trace: Which CCR → Which circuit → Which lighting system → What operational effect?
Series-Circuit Failure
A single fault can affect multiple lighting units.
- Cable fault
- Earth fault
- Open circuit
- Transformer failure
- Connector failure
- CCR problem
Individual Light Failure
A single failed fixture does not automatically mean a NOTAM is required. The engineering/operations team must determine:
- Location
- Function
- Number of failed units
- Remaining serviceable lights
- Operational significance
- Applicable reporting criteria
Technical failure ≠ Automatically NOTAM.
The same symptom — lights not performing correctly — can originate at three very different levels, each with a different NOTAM implication
Replacement, Project Work & Commissioning
Before replacing AGL equipment or starting project work, coordinate with airport operations and the authorized aeronautical information function before affecting operational facilities.
Before Planned Replacement, Consider
- Which system is affected?
- Is the system operationally required?
- How long will it be unavailable?
- Does the work affect runway/taxiway availability?
- Are temporary measures available?
- What coordination is required?
- Is an aeronautical information action required?
Project & Commissioning Changes Can Include
- Runway lighting modifications
- Taxiway closure
- Approach lighting work / PAPI replacement
- Sign installation, cable works, CCR replacement
- Lighting system under testing
- Temporary runway restrictions
- PAPI installation
- Approach lighting construction
- Taxiway lighting modification
- New signs under commissioning
The fixed order for AGL maintenance: plan and get the permit, brief, isolate and prove dead, work within the permit, test and restore, then hand back and record.
AGL Visual Encyclopedia: The safe maintenance sequence Electrical isolation
AGL NOTAM Internal Reporting Form
A practical internal template AGL teams can adapt to capture the information the authorized NOTAM function will need.
NOTAM Communication Checklist for AGL Engineers
When reporting a lighting problem, walk through each of these before you communicate it. This resets on reload.
What & Where
When & Extent
Impact & Status
Restoration & Evidence
NOTAM Data Accuracy & Time Management
Incorrect NOTAM information can create operational confusion. Common information errors include:
Engineering should clearly record detection time, notification time, maintenance start, maintenance completion, testing completion and restoration confirmation — creating a traceable timeline. Aeronautical information commonly uses UTC for standardized time reporting; engineering records may use local time, but the responsible procedure should be followed when providing information for aeronautical information processing. A time-zone mistake can create an operationally significant error.
The NOTAM Lifecycle
Identify the condition.
Confirm the technical condition.
Determine operational significance.
Verified information to authorized function.
NOTAM issued if required.
Repair and monitor.
Confirm serviceability.
Reflect the restored condition.
The planned order of work on a scheduled visit — plan and permit, look while live, isolate, clean, inspect and test, then restore, verify and record, so wear is found and fixed before a light fails.
AGL Visual Encyclopedia: The preventive maintenance sequence
NOTAM Quality Control & the AGL NOTAM Decision Framework
Before information is passed to the authorized NOTAM function, check: correct airport, correct facility, correct runway/taxiway, correct lighting system, correct affected area, condition verified, start time recorded, expected restoration established if appropriate, maintenance team and operations informed, and supporting test records available.
Use This as an Internal Engineering Decision Aid
Step 1 — Is there an AGL abnormality? NO → Normal operation. YES → Continue.
Step 2 — Is the condition verified? NO → Investigate. YES → Continue.
Step 3 — Does it affect an aeronautical facility or operational capability? NO → Maintenance record. YES → Continue.
Step 4 — Is the condition operationally significant under applicable procedures? NO → Normal maintenance/control process. YES → Notify the authorized airport/AIS function.
Step 5 — Is NOTAM or another aeronautical information action required? Decision by authorized function.
Step 6 — Repair and verify.
Step 7 — Update/cancel the applicable information as required.
Most abnormalities exit early as routine maintenance — only conditions that clear every gate reach the authorized NOTAM function
NOTAM Documentation Package
For significant AGL events, maintain a complete auditable chain from fault to restoration.
Common NOTAM-Related Mistakes
Click a card to expand it.
Mistake 1
Wrong Assumption
- Assuming every AGL fault requires a NOTAM.
Mistake 2
Under-Reporting
- Failing to report an operationally significant lighting outage.
Mistake 3
Unverified Reporting
- Giving an unverified technical description.
Mistake 4
Location Error
- Using the wrong runway/taxiway identifier.
Mistake 5
Time Error
- Using incorrect effective times.
Mistake 6
Stale Notice
- Failing to update the notice after restoration.
Mistake 7
Premature Restoration
- Considering a repaired fixture automatically restored without required verification.
Mistake 8
Terminology Confusion
- Confusing maintenance records with NOTAMs.
Mistake 9
Coordination Gap
- Ignoring operational coordination during planned maintenance.
Mistake 10
Broken Traceability
- Failing to maintain traceability between the technical defect and operational notification.
NOTAM vs NOTAM-Like Internal Alerts
Don't mix terminology. An airport may have internal maintenance alerts, engineering notifications, operations alerts, control-room alarms or work permits — these are not necessarily NOTAMs. A NOTAM is part of the formal aeronautical information framework.
Practical AGL Scenario
Scenario: A runway edge-lighting circuit develops a fault during night operations.
Detect
CCR/circuit alarm or visual report.
Verify
Engineer confirms the affected circuit.
Identify
Determine affected runway and lighting section.
Notify
Inform airport operations according to procedure.
Assess
Authorized personnel determine operational significance.
Aeronautical Information
Applicable NOTAM action is taken if required.
Repair
Fault is isolated and rectified.
Test
Electrical and functional tests completed.
Verify
Required system performance confirmed.
Restore
Responsible function updates/cancels applicable information.
NOTAM and Troubleshooting
Your AGL Troubleshooting Engine can connect technically to the NOTAM workflow. This should be a decision-support pathway, not an automatic NOTAM generator.
Match the symptom to the likely places in the loop, then narrow the fault down by section with the circuit isolated.
AGL Visual Encyclopedia: How do you troubleshoot a series circuit
NOTAM and Maintenance Management
A mature AGL maintenance system should connect the fault through to the applicable notice, creating a complete traceable workflow:
Using condition data and trends to forecast when equipment needs attention — so work is done before failure, but not before it is needed.
AGL Visual Encyclopedia: Predictive maintenance
From NOTAM to Reliability Improvement
Repeated NOTAM events for the same equipment should trigger engineering analysis. A NOTAM should not always be treated as the end of the process.
Watch For Recurrence
Repeated PAPI outage → repeated CCR fault → repeated transformer failure → repeated connector failure → repeated cable earth fault may indicate a deeper reliability issue.
- Failure frequency
- Failure duration
- Equipment type & location
- Root cause
- Restoration time
- Recurrence
Trend Analysis
A mature airport maintenance system tracks the number of AGL-related operational notices against:
- Runway / taxiway
- Equipment, manufacturer, component
- Failure mode
- Month, weather, maintenance activity
NOTAM and AGL Engineering Responsibility
AGL Technician
Detects and reports the technical condition.
AGL Engineer
Verifies, diagnoses and documents the condition.
Maintenance Control
Coordinates repair and operational communication.
Airport Operations / ATC
Assesses operational implications per airport procedures.
AIS / NOTAM Authority
Processes and publishes the aeronautical information as required.
NOTAM and Emergency Response
For critical AGL failures, the engineering team should never delay an urgent operational notification simply because complete root-cause analysis is still underway. The initial communication should accurately describe the known verified condition.
Making a series lighting circuit safe to work on — supply locked out, loop disconnected at the CCR, then proved dead and earthed.
AGL Visual Encyclopedia: Circuit isolation
NOTAM and Safety Management
NOTAMs form part of a broader operational safety system. They help ensure that aviation users are informed when aerodrome conditions differ from expected conditions. For AGL engineering, this creates the principle: a defect that changes operational capability must be communicated through the airport's approved safety and aeronautical information process.
The Most Important NOTAM Principle for AGL Engineers
Do not think of a NOTAM as a document created after a failure. Think of it as part of the operational safety response to a change in aerodrome conditions. The engineering responsibility is to provide information that is:
NOTAM Standards & References
NOTAM procedures are governed by the applicable international and national aeronautical information framework. For India, the exact NOTAM workflow, authority and publication requirements should be checked against the current applicable DGCA/AIS framework and airport procedures — never rely on an old NOTAM format or procedure simply because it appears in a historical document.
Annex 15, Aeronautical Information Services; Annex 14, Aerodromes.
ICAO Procedures for Air Navigation Services — Aeronautical Information Management.
Applicable State AIS/NOTAM regulations and DGCA requirements in India.
Airport Operations Manual, Aerodrome Manual, local NOTAM procedures, AGL maintenance and emergency procedures.
Quick Knowledge Check
Q1. A NOTAM is best described as:
Q2. A PAPI unit is illuminated. What does this confirm on its own?
Q3. Who is normally authorized to decide on and issue a NOTAM?
Q4. A single failed runway edge fixture out of many is found. What should happen first?
Complete AGL NOTAM Workflow
Detect the AGL abnormality → verify the actual technical condition → identify the exact affected facility and location → assess potential operational significance → report verified information to the responsible airport function → authorized personnel publish the required aeronautical information → maintain by repairing and monitoring → test to confirm technical restoration → verify operational serviceability → update or cancel so published information reflects the restored condition.
53. Final Engineering Principle
AGL Failure → Operational Impact → Verified Information → Authorized Notification → Corrective Action → Verified Restoration.
A NOTAM does not repair an AGL system. It communicates an operationally significant condition while the technical team works to restore the facility. For AGL engineers, the objective is not merely "issue a NOTAM." The objective is to identify the real condition, communicate it accurately through the approved process, restore the system correctly, verify serviceability, and ensure the aeronautical information remains current.
Accurate. Timely. Traceable.
NOTAMs turn a verified AGL condition into a safety communication aviation users can act on. Explore the reporting discipline, decision framework and standards behind it.
Airfield Lighting NOTAM Procedure
Airfield lighting NOTAM procedure
The airfield lighting NOTAM procedure begins when a lighting fault or planned work affects what pilots can rely on. The AGL team reports the facts to the airport operations office, which decides whether a NOTAM is needed and issues it through the authorised channel. When the system is repaired and checked, the same route is used to cancel or amend the NOTAM. Follow your aerodrome's own procedure and the aviation authority's rules.
Explore the AGL Engineering Knowledge Hub
Fundamentals
Standards & Compliance
Runway, Taxiway & Approach Lighting
Surface Movement & Safety
PAPI
Electrical Engineering & Power
Photometry & Testing
Maintenance, Inspection & Safety
Resources, Documentation & Careers
Frequently Asked Questions
Q1What is a NOTAM?
NOTAM stands for Notice to Airmen. It communicates the establishment, condition, change or removal of an aeronautical facility, service, procedure or hazard when that information is timely and operationally significant. The circumstances requiring one are determined by applicable aeronautical information regulations and the responsible authority, not by an individual engineer's judgement alone.
Q2Why do NOTAMs matter for airfield ground lighting?
An AGL defect can be more than a maintenance problem, since it can change the visual guidance an aircraft actually receives. Engineering identifies and communicates the technical condition through the airport's reporting process, and the authorized aeronautical information function determines and issues the operational notice.
Q3What is the difference between a NOTAM and a maintenance report?
A maintenance report is a technical record for engineering and maintenance use, containing technical details of inspections or failures. A NOTAM is operational information for aviation users, using standardized aeronautical information published through authorized channels. One should not be treated as automatically equivalent to the other.
Q4Who decides whether a NOTAM is issued for an AGL fault?
Authorized operational and aeronautical information personnel determine and issue the notice. Engineering identifies and verifies the condition and reports it through the established process.
Q5When can an AGL problem become NOTAM-relevant?
It depends on operational significance and the applicable procedures, not simply on a fault existing. Examples include unavailable or partially unavailable runway lighting, affected taxiway lighting or stop bars, unavailable or degraded approach lighting, PAPI outages or restrictions, and unavailable airfield signs. The governing question is whether the condition changes published or expected operational conditions.
Q6What is the AGL-to-NOTAM chain?
AGL fault, detection, technical verification, operational impact assessment, report to the authorized airport function, NOTAM decision, NOTAM issuance, maintenance or rectification, verification, and finally NOTAM cancellation or update.
Q7Does a lit PAPI mean it is serviceable?
No. A PAPI that is physically illuminated is not necessarily operationally correct. A powered, visibly lit PAPI can still present a false glide-path indication, where the fault is optical rather than electrical, so technical verification should accompany operational reporting.
Q8How precisely should approach lighting faults be reported?
Identify exactly which portion of the system is affected, such as centreline lighting, crossbars, sequenced flashing components or other elements, rather than simply reporting that the approach lights are faulty.
Q9What should happen during an emergency AGL failure?
Speed matters, but accuracy matters equally. Confirm the condition, notify airport operations, assess the operational impact, initiate the applicable aeronautical information procedure, then rectify, test, restore and update or cancel the notice. Never communicate an unverified technical assumption as an operational fact.
Q10How is planned AGL maintenance coordinated with NOTAMs?
The workflow runs from the maintenance plan and identification of affected AGL, through operational impact assessment and coordination with airport operations, ATC and AIS, to any required notice or restriction, then the maintenance work, testing, restoration and notice cancellation or update if applicable.
Engineering & Expert Notes
A Fault Log Is Not a NOTAM
PrincipleUnderstand when a maintenance finding affects operations and needs to be notified.
Timeliness Matters
TimingStart notification promptly and follow your airport's procedure for who issues it.
Light On Does Not Mean Compliant
PAPI and AGLA light that is on may be misaligned or degraded. Consider whether the function is actually available.
Be Clear and Specific
WordingDescribe what is unavailable and where. Vague wording leaves operators guessing.
Cancel and Update Accurately
UpdatesKeep information current as work progresses and when the facility is returned to service.
Record the Chain of Decisions
RecordsKeep a record of the engineering input, decision and issue time for later review.
Understand AGL. Build Your Engineering Skills.
You now understand how NOTAMs connect AGL faults, outages and maintenance activity to real operational decisions on the airfield.
Take the next step with Precision AGL Academy.
Learn AGL Step by Step
Build your knowledge through structured technical learning covering:
Move from understanding how AGL works to developing the practical knowledge needed to analyse, operate and maintain complete AGL systems.
Follow the Academy
Important Notice, Disclaimer & Limitation of Liability
Please read before relying on any content on this page or on any record downloaded from it.
- Purpose and intended users. This page is an independent educational and informational reference for competent, suitably trained and authorised airfield ground lighting (AGL) and aerodrome personnel. It is not professional engineering, legal or regulatory advice, and using it creates no professional or client relationship. Learning-path and Academy references describe stages of learning only and are not a certification, accreditation or authorisation.
- Safety. Work on series circuits, constant current regulators (CCRs), isolating transformers, cables, connectors and lighting fixtures can be fatal. Always apply the aerodrome’s permit-to-work and isolation/LOTO procedures, prove dead, use correctly rated instruments and PPE, and follow the manufacturer’s instructions. Nothing here authorises work on live equipment or the bypassing of any safety device or interlock.
- Aviation operations. Nothing on this page authorises return to service, the installation, adjustment or modification of any aviation visual aid, a change of operating category (CAT I/II/III), a NOTAM or any aerodrome certification decision. These rest with the aerodrome operator, the air navigation service provider and the competent regulator.
- Standards, regulations and named sources. References to ICAO, FAA, EASA, DGCA, AAI, IEC, IEEE, ISO, BIS and other standards, regulations, AIP material and published sources, and statements about what a named airport, State or authority has published, are summaries for orientation as understood when the page was prepared. They are not official text, may be incomplete, amended or superseded, and have not been independently verified. Consult the current official editions, including the current AIP, AIRAC cycle and NOTAMs. Following this content does not guarantee compliance with any law, standard or approval, and official documents, regulations, the approved design and manufacturers’ instructions always prevail.
- Generic content; no warranty. Values, tolerances, intervals, sequences, examples, checklists and pass/fail or “compliant” wording are generic and indicative; real installations differ in design, make, model, age and condition. Content is provided “as is” and “as available”, without warranty of any kind, express or implied, including accuracy, completeness, currency or fitness for a particular purpose.
- Diagrams. Diagrams on this page are original schematic illustrations, are not to scale and are not engineering drawings. Do not use them to work on, connect, set or modify equipment.
- Limitation of liability. To the fullest extent permitted by applicable law, Precision AGL Academy and its owners, authors and contributors are not liable for any injury, death, loss, damage, downtime, penalty or regulatory consequence, whether direct or indirect, arising from the use of, reliance on, or inability to use this content. Nothing in this notice excludes or limits any liability that cannot lawfully be excluded or limited.
- Independence and trademarks. This is an independent publication, not affiliated with or endorsed by ICAO, the FAA, EASA, the IEC, DGCA, AAI, any airport, regulator, employer or equipment manufacturer. Third-party names, standard designations and trademarks (including Megger®) belong to their respective owners and are used for identification only.
- Copyright and use. © 2026 Precision AGL Academy. All rights reserved. The text, structure, diagrams and compilation of this page are protected by copyright. You may read it and use it for personal reference and internal training, keeping this notice attached; any other copying, republication, scraping or commercial use needs our prior written permission. Credited third-party photographs remain subject to their owners’ terms.